Chapter 38 Quiz: Quotes, Contracts, and Permits
Part A: Multiple Choice
1. When comparing three contractor bids for a bathroom renovation, Bid A is $18,400, Bid B is $14,200, and Bid C is $16,800. Which is the correct first step before drawing any conclusions from these numbers?
a) Select Bid B because it's the lowest b) Verify that all three bids cover the same scope of work, including permits, demo, and material specifications c) Average the three bids and select the contractor closest to the average d) Reject Bid B because being 22% lower than the others is an automatic red flag
2. In a contractor bid, an "allowance" for tile at $4,000 means:
a) The contractor will install tile and the total cost including labor will be no more than $4,000 b) A placeholder budget amount for tile that will be adjusted to reflect the actual tile you select — and which may be significantly higher c) The contractor has already purchased tile valued at $4,000 for your project d) Tile is excluded from the project and you will handle it separately for no more than $4,000
3. Which of the following elements is NOT required in a residential contractor contract?
a) Start date and estimated completion date b) Change order procedure c) A list of all homeowners in the neighborhood who have used the contractor d) Payment schedule tied to specific milestones
4. A proper change order procedure requires which of the following BEFORE additional work is performed?
a) Verbal agreement between the homeowner and contractor, with the contractor noting it in their project file b) A written change order describing the scope change, cost, and schedule impact, signed by both parties c) An email from the homeowner saying "go ahead" is sufficient as long as it's in writing d) The homeowner's attorney must review all change orders before they're signed
5. Which payment schedule structure best follows the principle of keeping payments slightly behind completed work?
a) 70% upfront, 30% on completion b) 100% in equal weekly installments regardless of progress c) 25% at signing, 35% at rough-in completion, 30% at substantial completion, 10% at punch list completion d) 50% at signing, 50% when the homeowner is satisfied
6. A mechanics lien on your property can be filed by which of the following parties, even if you have paid your general contractor in full?
a) Only the general contractor b) Only parties who have a direct contract with you (the homeowner) c) Subcontractors, suppliers, or laborers hired by your general contractor who weren't paid by the GC d) Only your mortgage lender
7. What is the primary purpose of a conditional lien waiver provided by a subcontractor?
a) It confirms that the subcontractor was licensed to perform the work b) It waives the subcontractor's right to file a mechanics lien against your property, conditioned on the payment actually clearing c) It releases the homeowner from all liability for the subcontractor's work quality d) It transfers the subcontractor's warranty obligations to the homeowner
8. Which of the following is a legitimate reason for a contractor to request a larger-than-usual upfront deposit?
a) The contractor's business has been slow and they need cash flow b) The contractor has a good reputation and established track record c) Custom-manufactured materials (such as custom windows or specialty cabinetry) require a supplier deposit before fabrication begins d) The project timeline is longer than usual
9. In the context of dispute resolution, which method is most appropriate for a $4,500 dispute over incomplete work where the contractor has become unresponsive?
a) International commercial arbitration b) Federal consumer protection court c) Small claims court (if the amount is within your state's threshold) after documenting the issue in writing and making a formal written demand d) Hiring a mediator and splitting the $3,000-$5,000 cost for a one-day mediation session
10. The "punch list" in a construction project refers to:
a) The list of items that must be purchased by the homeowner before work begins b) The list of deficiencies and incomplete items that must be resolved before final payment is released c) The list of permit inspections required throughout the project d) The contractor's internal schedule for daily work tasks
Part B: Short Answer
11. Explain the "allowances trap" using a specific example, and describe two steps a homeowner can take before signing a contract to protect themselves from this risk.
12. A contractor has been working on your kitchen renovation for five weeks. He verbally asks about adding recessed lighting in the dining room while he's there, and you say "sure, that sounds great." He completes the work and invoices you $1,400 for the lighting. You believe you said yes only to getting a quote. Describe the problem this scenario illustrates and how a proper change order process would have prevented it.
13. Explain what a mechanics lien is, who can file one, and why a homeowner who has paid their general contractor in full could still have a lien placed on their property.
14. Describe what the "final retention" in a payment schedule is, why it's important, and what should happen before the homeowner releases this final payment.
15. Miguel Rodriguez spent four hours reviewing the contractor contract for his flood mitigation project and requested changes to three provisions. The chapter describes this as the "boring" part that produced a "boring" outcome — a project that came in $200 over budget with one properly documented change order. What is the connection between the upfront contract work and the project outcome? What would a "not boring" contractor story typically mean?
Answer Key
Part A
- b — Comparing bids before normalizing scope is comparing apples to oranges. The adjustment step often significantly changes the apparent price relationships.
- b — An allowance is a placeholder. The final cost is adjusted when actual selections are made. Allowances that are set too low are a systematic cause of renovation budget overruns.
- c — No contract requirement involves neighborhood references. All other options are among the 13 required elements in Section 38.3.
- b — Written, signed change orders before work proceeds is the core protective mechanism. Verbal agreements (a) create the "I thought you meant" scenario. Email without counter-signature (c) is better than nothing but falls short of a proper signed change order. Attorney review (d) is not required and would be impractical for routine project changes.
- c — This structure keeps the homeowner's exposure roughly proportional to work completed throughout the project, with a meaningful retention at the end. The 70% upfront (a) leaves the homeowner severely exposed. Weekly installments without progress ties (b) can create payment-ahead-of-work situations. 50% at signing (d) is a large upfront exposure.
- c — Mechanics lien laws in every US state allow subcontractors, suppliers, and laborers who weren't paid by the GC to file liens against the property. This is the core risk addressed by lien waivers.
- b — A conditional lien waiver waives the right to lien conditioned on payment clearing. The conditionality protects the subcontractor (they're not waiving their rights before they're actually paid) while protecting the homeowner (once payment clears, the waiver is final).
- c — Custom materials requiring supplier deposits are the only legitimate justification for a larger-than-standard upfront payment. The other options are not legitimate business justifications.
- c — For a $4,500 dispute, small claims court (most state thresholds are $5,000-$15,000) is the efficient path after documenting the issue and making a formal written demand. Mediation (d) costs more than the dispute; federal court (b) doesn't apply to residential contractor disputes; international arbitration (a) is obviously inappropriate.
- b — The punch list is the documented list of deficiencies and incomplete items that must be resolved before final payment is released.
Part B — Sample Responses
11. The allowances trap: a contractor includes a "$3,000 allowance for bathroom tile" in their bid. This makes the total bid price appear lower than if realistic tile costs were included. When the homeowner visits a tile showroom, they discover that even a modest tile selection for a 60-square-foot bathroom — including trim pieces, installation materials, and labor — runs $5,500-$7,500. The $3,000 allowance becomes a $2,500-$4,500 surprise. Two protective steps: (1) Before signing, identify every allowance in the contract and visit the appropriate supplier to verify that the allowance amount is realistic for what you actually want. Get a quote, not just a price list. (2) Ask the contractor explicitly: "Is this allowance based on mid-grade product, and can you show me examples of what this budget actually buys?" A contractor who can't show you a concrete example is speculating.
12. This scenario illustrates the informal verbal change order problem described in Section 38.4. You and the contractor have different understandings of whether an agreement was reached and what it covered. With no written change order, there is no objective record of what was agreed. A proper change order process would have required the contractor to provide a written change order describing the lighting work and stating the $1,400 cost before any work was performed. You would have reviewed it, asked any questions, and signed it (or declined) before work proceeded. Both parties would have been clear on the commitment. The written record would have prevented the dispute entirely.
13. A mechanics lien is a legal claim filed against a property by someone who performed work on it or supplied materials to it and wasn't paid. In US law, the right to file a mechanics lien extends to subcontractors, suppliers, and laborers — not just the party who has a direct contract with the homeowner. If a homeowner pays their general contractor in full but the GC fails to pay a tile subcontractor, that tile sub can file a mechanics lien against the homeowner's property. The lien attaches to the title and prevents the homeowner from selling or refinancing until it's resolved — even though the homeowner fulfilled their obligation by paying the GC. This is why lien waivers from both the GC and significant subcontractors are essential.
14. Final retention is the last payment — typically 10-15% of the contract price — held back until the project is fully complete. It's important because it's the homeowner's primary leverage to ensure all contracted work is actually finished, punch list items are addressed, and all inspections have been passed. A contractor who has been paid 100% before completion has no financial incentive to return for callbacks and punch list items. The homeowner should release the final retention only after: all contracted work is complete, all change orders are complete, all required inspections have passed, a punch list walkthrough has been conducted with the contractor, and all items on the punch list have been resolved.
15. Contract work determines the framework within which the project operates. When scope is clearly defined, change order procedures are explicit, and payment milestones are tied to verifiable completion, there is less ambiguity for disputes to fill. The one $200 change order in the Rodriguez project was documented, signed, and filed — it was not a surprise on the final invoice. A "not boring" contractor story typically means: project ran significantly over budget (informal scope additions, undocumented changes), final invoice was a surprise (payment structure allowed the contractor to be paid ahead of work, or final payment included items not agreed to), or dispute about what was included in the original scope (vague scope language, no change order discipline). The paperwork is boring. The alternative is not.