Appendix C — Estimating Reference: CSI Divisions, Unit Costs, Productivity, Waste Factors

C.0 How to use this appendix — and the one thing you must not do with it

Chapter 12 taught you how to price one thing: quantity, productivity, rate, plus material, plus waste. Chapter 13 taught you how to assemble the whole number. This appendix is the lookup layer underneath both of them — the division map, the conversion between the two organizing systems, the crew compositions, the adjustment factors, the waste table, the burden template, the general-conditions checklist, and the two checklists you run before a number leaves the building.

And then, at the end, the section that matters more than everything above it: how to build your own historical cost database, which is the only source of numbers that will ever actually be right for your market and your crews.

⚠️ The standing warning

Every unit cost, production rate, crew composition, wage, burden percentage, waste factor, and adjustment factor in this appendix is illustrative teaching data. This is not a price book. Do not bid off it.

The numbers here are internally consistent with each other and with the worked examples in the book, so the arithmetic teaches something real. That is their entire job. They are not survey data, they are not adjusted to your market, and they do not know your crews, your foremen, your form system, your soils, your union agreement, your workers' compensation class rates, or what the ready-mix plant quoted you this morning.

Real numbers come from three places, in this order of reliability: your own company's historical cost data · current quotes from the market you are actually building in · published cost data adjusted for time, location, and size. Section C.11 is about generating the first one, which is the reason this appendix's numbers can afford to be illustrative.

You will see that warning restated at the head of every table of money in §C.5. That is deliberate.

A note on what is cited and how. MasterFormat and UniFormat are published by the Construction Specifications Institute and Construction Specifications Canada; both are periodically revised, and division and element titles change between editions. Published cost data — RSMeans is the most widely used in North America — and the cost indices published by Engineering News-Record are real, useful, and referenced here by name and function only. Nothing in this appendix quotes a line number, an index value, a location factor, or a published productivity table. Where a professional body has published extensively on a subject — AACE International on cost engineering and forensic analysis, the Mechanical Contractors Association of America and the National Electrical Contractors Association on labor productivity and inefficiency factors — this appendix says so and sends you to them. It does not invent their contents.


C.1 CSI MasterFormat, division by division

MasterFormat is the numbering standard that organizes the specification, and — because the specification is how the market sells work — it organizes the estimate, the bid packages, the cost codes, and the schedule of values as well. Chapter 7 covers it as a document system; Chapter 13 covers it as an estimating container. Its purpose in an estimate is narrow and enormous: completeness and non-duplication. An estimate is wrong in exactly two ways — something is missing, or something is in twice — and a division structure catches both, because every scope item has one obvious home.

The third column of the table below is the one you will not find elsewhere: the classic scope gap that lives at the boundary between this division and the next one. Money does not fall out of the middle of a division. Inside a division the subcontractor is expert, motivated, and will not miss much. Money falls off the edges, where two competent bidders each reasonably assume the other one has it. That is the whole argument of Chapter 16, and this table is its lookup form.

C.1.1 Procurement and general requirements

Div Title What belongs here Who typically bids it The classic scope gap at its boundary
00 Procurement and Contracting Requirements Invitation to bid, instructions to bidders, bid form, bid and contract bonds, the agreement, general and supplementary conditions Nobody. This is not cost — it is the rules Alternates, allowances, and unit prices are described in 00 and priced in the divisions. Bidders read 00 for the rules and never carry the alternate. A missed alternate is a non-responsive bid, not a cost problem
01 General Requirements Temporary facilities and controls, cleaning, safety, quality requirements, submittal and scheduling procedures, waste management, closeout The general contractor. This becomes your general conditions (§C.9) Every trade assumes "the GC provides power, water, hoisting, and dumpsters." The amperage, the hours, the locations, and the premium-time rate live in 01 and nowhere else. If your scope sheets do not restate them, each subcontractor priced a different building

C.1.2 Facility construction subgroup — Divisions 02–19

Div Title What belongs here Who typically bids it The classic scope gap at its boundary
02 Existing Conditions Selective and structural demolition, hazardous-material abatement, site remediation, existing utility removal and abandonment, surveys and assessments Demolition contractor; licensed abatement specialist 02 ↔ 31. Where demolition ends and excavation begins. Existing foundations, slabs, and abandoned utilities below grade are claimed by neither: the demo contractor priced what it could see, the excavator priced dirt
03 Concrete Cast-in-place concrete, formwork, reinforcing, accessories, precast structural and architectural precast, toppings, grouts, curing and finishing Concrete contractor (Kestrel self-performs cast-in-place); precast fabricator/erector 03 ↔ 05. Composite metal deck is Division 05 and its lightweight topping is Division 03, so the pour stops, edge forms, closure angles, and deck-edge detailing sit exactly on the line. Also 03 ↔ 05 on embeds, anchor bolts, and setting templates: who furnishes, who sets, and who surveys them
04 Masonry CMU, brick, stone, mortar and grout, masonry reinforcing and accessories, flashing at masonry, masonry cleaning Mason 04 ↔ 07. Through-wall flashing and weeps are specified in 07 and installed by 04, and are routinely excluded by both. 04 ↔ 03 on cast stone sills and copings — the classic orphan, sitting between the masonry and precast packages, excluded by each because each assumes the other
05 Metals Structural steel, metal deck, open-web joists, miscellaneous metals, stairs, railings, cold-formed structural framing Steel fabricator/erector; miscellaneous metals fabricator 05 ↔ 06. Wood blocking versus light-gauge backing. 05 ↔ 09 on load-bearing versus non-structural metal framing at exterior walls, which is delegated design in one and a stud-and-track trade in the other
06 Wood, Plastics and Composites Rough carpentry, blocking and backing, sheathing, architectural millwork, casework, solid surface, plastic fabrications Carpenter (Kestrel self-performs rough carpentry); millwork shop 06 ↔ 09. In-wall blocking and backing in metal-stud partitions. This is the single most common gap in interior work. The drywall bidder writes "blocking by others"; the carpentry estimate covers wood-framed openings and millwork and never contemplated 3,900 LF of strap inside stud walls. On Northgate that gap was $107,000
07 Thermal and Moisture Protection Roofing, waterproofing, dampproofing, air and vapor barriers, insulation, firestopping, joint sealants, sheet metal flashing, roof specialties Roofer; waterproofer; firestopping specialist; sealant contractor 07 ↔ 08. The air-barrier transition at every opening, slab edge, and curtain-wall perimeter. This is the seam that cost Northgate's curtain-wall submittal nine weeks. 07 ↔ 09 on head-of-wall joints (part of the rated assembly, usually drywall) versus penetration firestopping (usually a dedicated package)
08 Openings Curtain wall, storefront, doors and frames, hardware, glazing, automatic entrances, access doors, louvers Glazing contractor; door and hardware supplier 08 ↔ 28. Electrified hardware: strikes, mag-locks, and power transfers are furnished in 08 and wired in 28, and the interface is nobody's until somebody writes it down. 08 ↔ 23 on louvers — architectural louvers are 08, mechanical louvers are 23, and the ones on the drawings are usually neither
09 Finishes Non-structural metal framing, gypsum board, plaster, tile, acoustical ceilings, flooring, painting, wall coverings Drywall/interiors contractor; flooring contractor; painter 09 ↔ 21/22/23/26/28. Access panels: mechanical, plumbing, and electrical furnish them; drywall or ceilings install them; the count is never stated. On Northgate the number is 186 and it is a line in the scope sheet
10 Specialties Toilet compartments and accessories, signage, lockers, fire-extinguisher cabinets, wall and corner protection, partitions Specialties supplier/installer 10 ↔ 06/09. The blocking a grab bar screws into. Discovered at 4:30 p.m. by a person holding a grab bar and a screw gun. 10 ↔ 21 on cabinets (10) versus the extinguishers inside them (21, or the owner)
11 Equipment Food service, loading-dock, waste handling, laboratory and medical equipment, projection, athletic Equipment vendors 11 ↔ 22/26. The final connection. This is the largest recurring gap in Division 11: the vendor furnishes and sets, somebody has to bring the utility to within a stated distance, and somebody has to make the final connection. Say all three in the scope sheet or you will buy one of them twice and none of them once
12 Furnishings Window treatments, fixed casework and seating, entrance mats and frames, site furnishings inside the building line Furnishings vendors 12 ↔ 06. Shop-fabricated architectural casework (06) versus manufactured casework (12) — and the blocking behind either one
13 Special Construction Radio-frequency and radiation shielding, clean rooms, pre-engineered structures, vaults, pools, integrated assemblies Specialty subcontractors 13 ↔ 09. Lead-lined gypsum board at imaging. On Northgate all three drywall bidders excluded it, which made it invisible on the bid tab and still left it unbought. It went to Division 13 with the shielding contractor. Circle shared exclusions separately, always
14 Conveying Equipment Elevators, escalators, lifts, material handling, pneumatic tube Elevator manufacturer 14 ↔ 03/05. Hoistway construction, pit, sump and pump, divider beams, hoist beam, and the rail-support steel. 14 ↔ 26 on machine-room and cab power; 14 ↔ 28 on fire-alarm interface and elevator recall — which is a certificate-of-occupancy item, not a nice-to-have
15–19 Reserved Not assigned in the current structure Chapter 13 groups these with the other empty divisions on a commercial building. The finer point: these are reserved numbers, not unused categories. Facility services moved to the 20s in the 2004 restructuring. If you see Division 15 (mechanical) or 16 (electrical) on a drawing set, you are looking at a document produced under the pre-2004 numbering, and you should confirm which edition the whole project manual follows before you file anything

C.1.3 Facility services subgroup — Divisions 20–29

Div Title What belongs here Who typically bids it The classic scope gap at its boundary
20 Reserved
21 Fire Suppression Sprinklers, standpipes, fire pumps, clean-agent systems, fire-suppression water service Fire protection contractor 21 ↔ 22 at the fire service entrance and backflow preventer. 21 ↔ 26 on fire-pump feeder and controller. 21 ↔ 28 on flow, tamper, and pressure-switch wiring — the device is 21, the wire is 28, and the interface test is what fails at final inspection
22 Plumbing Domestic water, sanitary, storm, natural gas, medical gas, fixtures, water heaters, insulation Plumber 22 ↔ 33. The five-foot line. Where site utilities stop and building plumbing starts. State the dimension in the scope sheet; do not assume a convention. Medical gas is a Division 22 scope that general contractors routinely buy with the mechanical package — legitimate, and it must be said in writing to every bidder, or you get the Ridgeline result: a $268,000 hole with $340,000 of daylight showing through it
23 Heating, Ventilating and Air Conditioning Ductwork, air handlers, chillers, boilers, hydronic and refrigerant piping, terminal units, testing and balancing Mechanical contractor 23 ↔ 25. Controls: who furnishes the device, who installs it, who wires it, who programs it, who commissions it. The most contested seam in the building. 23 ↔ 26 on motor starters, variable-frequency drives, and line versus low voltage. 23 ↔ 07 on roof curbs, curb flashing, and the equipment screen
24 Reserved
25 Integrated Automation Building automation, direct digital controls, network infrastructure for facility systems, systems integration Controls contractor 25 ↔ 23/26/27. Every device this division touches is installed by somebody else. Its scope is defined almost entirely by exclusions, which is why the controls package needs its own scope-review call
26 Electrical Service and distribution, branch wiring, lighting and controls, generators, transfer switches, grounding, raceway Electrician 26 ↔ 27/28. Pathway versus cable: conduit, back-boxes, sleeves, and j-hooks under 26; the cable and the head end under 27/28. If the scope sheet does not name it, you buy the cable and no conduit. 26 ↔ 33 on the primary duct bank and the utility company's demarcation point
27 Communications Structured cabling, audiovisual, distributed antenna, nurse-call and paging backbone Low-voltage contractor 27 ↔ 26 (as above) and 27 ↔ 06/09 on backing for wall-mounted displays and racks. Rack and cabinet seismic anchorage is delegated design that nobody bids
28 Electronic Safety and Security Fire alarm, access control, video surveillance, intrusion detection, mass notification Fire alarm contractor; security contractor 28 ↔ 14/21/23. Interfaces: elevator recall, sprinkler flow and tamper, smoke-damper control and testing, duct detectors (usually furnished by 28, installed by 23, wired by 28). Every one of these is a certificate-of-occupancy item, and every one of them is discovered in the last three weeks
29 Reserved

C.1.4 Site and infrastructure subgroup — Divisions 30–39

Div Title What belongs here Who typically bids it The classic scope gap at its boundary
30 Reserved
31 Earthwork Clearing, mass and structural excavation, fill and backfill, shoring and underpinning, dewatering, erosion and sediment control, soil treatment, driven piles and drilled shafts Site/excavation contractor; specialty foundation contractor 31 ↔ 33. Trench excavation, bedding, and backfill for site utilities — the utility contractor prices pipe, the excavator prices dirt, and the trench belongs to whoever wrote it down. 31 ↔ 03 on over-excavation and engineered fill under footings, which is a unit-price scope hiding inside a lump-sum package
32 Exterior Improvements Paving, curbs and gutters, sidewalks, pavement markings, fencing and gates, retaining walls, planting, irrigation, site furnishings Sitework contractor; landscape contractor 32 ↔ 31 on subgrade preparation, proof-rolling, and who owns a failed subgrade. 32 ↔ 26 on site lighting: bases (32 or 03), conduit (26), poles and fixtures (26), and the base design (delegated)
33 Utilities Site sanitary, storm, water, fire service, gas, primary electrical duct bank and structures, stormwater detention Site utility contractor 33 ↔ 22/26 at the five-foot line, and 33 ↔ the serving utility, whose scope, schedule, and fees are set by the utility and are almost never in your bid documents. Utility company lead times are a schedule risk, not a cost risk, and they belong on your constraint log (Chapter 27) from week one
34 Transportation Rail, transit, airfield construction, roadway equipment, traffic signals and control Heavy civil contractors Used on infrastructure work. On the Cottonwood Creek Bridge Replacement (Chapter 38) the relevant boundary is 34 ↔ 32 on pavement, striping, and traffic control
35 Waterway and Marine Construction Dredging, coastal and marine construction, dams, waterway equipment Marine contractors Marine mobilization and demobilization is a discrete, very large line item and is not "included"
36–39 Reserved

C.1.5 Process equipment subgroup — Divisions 40–48

These are the divisions a building contractor almost never opens and an industrial contractor lives in. They exist because a refinery, a water treatment plant, a food processing line, or a generating station has scope that does not fit a building's vocabulary.

Div Title What belongs here Who typically bids it
40 Process Interconnections Process piping and tubing, process instrumentation and control, insulation for process systems Process piping and instrumentation contractors
41 Material Processing and Handling Equipment Conveyors, bulk handling, industrial cranes and hoists, lifts, storage and retrieval Equipment integrators
42 Process Heating, Cooling and Drying Equipment Industrial furnaces, kilns, dryers, heat exchangers, cooling towers serving process loads Process equipment vendors
43 Process Gas and Liquid Handling, Purification and Storage Equipment Pumps, compressors, blowers, mixers, filtration and separation, tanks and vessels Process equipment vendors
44 Pollution and Waste Control Equipment Air pollution control, water and wastewater treatment equipment, solid-waste handling Environmental equipment vendors
45 Industry-Specific Manufacturing Equipment Manufacturing lines and equipment particular to one industry Owner's process vendors
46 Water and Wastewater Equipment Screening, clarification, digestion, disinfection, biological treatment equipment Municipal treatment specialists
47 Reserved
48 Electrical Power Generation Generating equipment, generator assemblies, and their electrical power generation systems Power plant contractors

Three rules for using the division table.

One: an empty division is a documented zero, and you write it as a dash. A dash means I looked. A missing row means nothing at all, and six weeks later nobody can tell the difference between "we decided it was zero" and "we forgot."

Two: packages are not divisions. MasterFormat organizes the specification. Your bid packages organize the market. They almost never line up. Northgate's enclosure package spans Divisions 03, 05, 07, and 08 by itself. The division tells you where to file it; the scope sheet tells you who bought it — and the scope sheet is in Appendix D.

Three: confirm the edition. MasterFormat is revised periodically. Division and section titles move, and a project manual produced under one edition and amended under another is a real thing that happens. Read the table of contents in the front of your project manual and file to that, not to this table.


C.2 UniFormat, and the crosswalk you actually need

MasterFormat organizes by work result — by trade, by product, by how the market sells. That is exactly what you want when you have a designed building and you are buying it.

It is exactly what you do not want when you have a program, a massing study, and an owner asking whether the enclosure should be precast or metal panel.

UniFormat organizes the same building by system and building element. It is available early, because you can say "exterior enclosure" long before you know it is precast. It keeps a building system whole, so a value-engineering comparison prices everything the change drags with it rather than just the visible half. This is the format Tomás Reyes reaches for in Chapter 11, and the one Chapter 7 introduces.

C.2.1 The Level 1 categories

Code Category Contains
A Substructure Foundations, slab on grade, basement construction
B Shell Superstructure, exterior enclosure, roofing
C Interiors Interior construction, stairs, interior finishes
D Services Conveying, plumbing, HVAC, fire protection, electrical
E Equipment and Furnishings Fixed equipment, furnishings
F Special Construction and Demolition Special structures, selective demolition
G Building Sitework Site preparation, improvements, civil utilities

C.2.2 When each one is the right tool

UniFormat MasterFormat
Organizes by Building system Trade / work result
Used for Conceptual estimating, design-phase cost planning, value engineering, elemental benchmarking Detailed estimating, specifications, bid packages, subcontracts, cost codes, schedules of values
Available when Very early — before anything is designed Late — you need a designed product to assign a section
Typical question "What is the enclosure costing us per SF of wall?" "What is the precast subcontract worth?"
Typical unit $/SF of gross floor area; $/SF of element (wall, roof, floor) $/CY, $/SFCA, $/LF, $/TON, $/EA
Fails when Somebody tries to buy from it Somebody tries to compare systems with it

C.2.3 The crosswalk — UniFormat element to MasterFormat division to subcontract

This is the table readers ask for and rarely find. Read it left to right and you are moving from "what is this building made of" to "who do I call." Read it right to left and you are moving from a pile of subcontracts back to a system you can compare against an alternative.

The last column is the point. Every place a single UniFormat element decomposes into more than one subcontract is a place where scope can fall on the floor.

UniFormat element What it is MasterFormat divisions that build it Typical number of separate subcontracts The boundary that costs money
A10 Foundations Footings, foundation walls, grade beams, pile caps, piles and shafts 31 (excavation, backfill, shafts) · 03 (concrete, formwork, reinforcing) · 05 (embeds, anchor bolts) · 07 (below-grade waterproofing, underslab vapor barrier) 3–4 Over-excavation and engineered fill: unit-price work living inside a lump-sum package
A20 Basement Construction Basement walls and slabs, excavation support that stays 31 (shoring, dewatering) · 03 · 07 (waterproofing, drainage board) 3 Waterproofing termination at the wall/footing joint, and who protects it during backfill
B10 Superstructure Floor and roof structural frames, decks, structural slabs, stairs structure 03 (topping, structural slabs) · 05 (steel, joists, deck, misc. metals) · 06 (wood framing, sheathing) 2–3 Deck-edge detailing, pour stops, and closure angles: 03 pours against them, 05 furnishes them
B2010 Exterior Walls The opaque enclosure — cladding, backup, insulation, air barrier, sealants 03 (architectural precast) · 04 (masonry veneer) · 05 (cold-formed framing) · 06 (sheathing, blocking) · 07 (air barrier, insulation, sealants, flashing) · 09 (gypsum sheathing, interior face) 4+ Air-barrier continuity at every transition, and the embeds the panels hang from
B2020 Exterior Windows Curtain wall, storefront, punched windows, glazing 08 (curtain wall, glazing) · 05 (support steel) · 07 (perimeter sealant, transition membrane) 2–3 The perimeter joint: the glazier stops at the frame, the waterproofer stops at the wall
B2030 Exterior Doors Exterior door assemblies and automatic entrances 08 (doors, frames, hardware, automatic operators) · 26/28 (power, access control) 2–3 Power transfer and electrified hardware — furnished 08, wired 28
B3010 Roof Coverings Membrane, insulation, flashing, roof specialties 07 (roofing, flashing, specialties) · 05 (deck) · 06 (nailers, blocking) · 22 (roof drains) · 23 (curbs) 3–5 Curbs, pipe supports, and every penetration: 23 sets the curb, 07 flashes it, and the sequence is a schedule problem
B3020 Roof Openings Hatches, skylights, smoke vents 07 · 08 · 28 (smoke vent control) 2–3 Fall protection at every roof opening is nobody's line item until you write it
C1010 Interior Partitions Framing, board, insulation, in-wall components 09 (framing, board) · 06 (blocking) · 07 (firestopping, acoustic sealant) · 13 (shielded assemblies) 3–4 Blocking and backing; head-of-wall joints versus penetration firestopping
C1020 Interior Doors Doors, frames, hardware, access doors 08 · 09 (installation of frames in gypsum assemblies) · 06 (wood doors) 2–3 Frame installation and the hardware punch that follows it
C20 Stairs Stair construction and finishes 05 (pan stairs, rails) · 03 (fill) · 09 (finishes) 2–3 Stair-tread fill and nosings, which live between the steel and the flooring
C30 Interior Finishes Wall, floor, and ceiling finishes 09 (all of it) · 12 (mats) · 10 (wall protection) 3–5 Floor preparation and moisture testing: excluded by the flooring contractor, owned by the slab
D10 Conveying Elevators, escalators, lifts 14 (equipment) · 03/05 (hoistway, pit, beams) · 26 (power, lighting) · 28 (recall) 3–4 The hoistway itself and the fire-alarm interface
D20 Plumbing Domestic water, sanitary, storm, gas, medical gas, fixtures 22 · 33 (at the line) · 07 (roof drain flashing) 2 The five-foot line, and the final connection to owner-furnished equipment
D30 HVAC Heat generation and distribution, cooling, air distribution, controls, testing and balancing 23 · 25 (controls) · 26 (power, starters, VFDs) · 07 (curbs, insulation at envelope) 3–4 The controls boundary. Furnish, install, wire, program, commission — five verbs, at least three companies
D40 Fire Protection Sprinklers, standpipes, fire pumps, suppression 21 · 26 (pump power) · 28 (alarm interface) · 22 (fire service) 2–4 Every interface, and the fire pump's power and controller
D50 Electrical Service, distribution, lighting, communications, safety and security 26 · 27 · 28 · 25 · 48 (generation, on process work) 3–5 Pathway versus cable. Boxes, conduit, and sleeves are the recurring hole
E10 Equipment Fixed and specialty equipment 11 · 22/26 (rough-in and final connection) · 06 (blocking, support) 2–4 The final connection. State furnish, set, rough-in, and connect as four separate obligations
E20 Furnishings Fixed casework, seating, window treatments, mats 12 · 06 (millwork, blocking) 2 Blocking, again
F10 Special Construction Shielding, clean rooms, integrated assemblies, pre-engineered structures 13 · 09 (adjacent assemblies) · 23/26 (services penetrating them) 2–3 Every penetration through a shielded or rated special assembly
F20 Selective Demolition Demolition and abatement of existing construction 02 1–2 The below-grade unknown, and the abatement scope nobody surveyed
G10 Site Preparation Clearing, demolition of site improvements, earthwork, erosion control 31 · 02 · 32 (erosion control) 1–2 Topsoil: stripped, stockpiled, and respread is three operations, priced as one
G20 Site Improvements Paving, walks, curbs, landscape, irrigation, fencing, site furnishings 32 · 31 (subgrade) · 03 (curbs, walks) · 26 (site lighting) 2–4 Subgrade responsibility and site lighting bases
G30 Site Civil/Mechanical Utilities Sanitary, storm, water, gas, detention 33 · 31 (trenching) · 22 (at the line) 2–3 Trenching, bedding, backfill, and the serving utility's own scope
G40 Site Electrical Utilities Primary distribution, duct bank, site power 33 · 26 · 31 (trench) 2–3 The duct bank: concrete (03), conduit (26), trench (31), and the utility's demarcation

How to use the crosswalk in practice.

Going left to right — conceptual estimate to bid package. You have a UniFormat estimate at $/SF of element. Before you can buy any of it you must decompose each element into divisions and then group divisions into packages. Every place the "subcontracts" column reads 3 or more, write a scope sheet before you write a bid package.

Going right to left — bid results back to a system view. When an owner asks "why is the enclosure over budget," a division report cannot answer. Roll Divisions 03, 04, 05, 07, and 08 back up into B2010 and B2020, express it as $/SF of wall against 38,500 SF of curtain wall and 21,000 SF of precast, and now you have a comparison the owner can act on.

The teaching point, stated once. The translation between the two formats is where scope gaps are born. They are not born inside a specification section. They are born in the act of taking a building organized one way and buying it organized another way.


C.3 Illustrative unit costs by division

⚠️ Illustrative teaching data. Not a price book. Do not bid off this section.

Every figure below is a range, not a point value, and the ranges are wide because reality is wide. The right-hand column is the most useful part of every table: the single biggest driver of variation for that item. When your number falls outside a range, the driver column tells you where to look first.

Items marked are the canonical worked values from the Northgate Outpatient Pavilion or the Cottonwood Creek Bridge Replacement, built from first principles in Chapter 12 and Chapter 13. They are internally consistent with the rest of the book. They are still illustrative.

C.3.1 Division 02 — Existing Conditions

Item Unit Illustrative range Biggest driver of variation
Building demolition, structure only, above grade SF of building $6 – $22 Structure type and whether salvage/recycling is required
Selective interior demolition, occupied building SF $3 – $12 Occupancy, infection control or dust partitions, work hours
Slab and foundation removal, below grade CY $45 – $130 Reinforcing, depth, and access for equipment
Asbestos abatement, non-friable flooring SF $4 – $14 Regulatory regime, containment class, and disposal distance
Abandoned utility removal LF $18 – $70 Whether the line is located, and whether it is live

C.3.2 Division 03 — Concrete

Item Unit Illustrative range Biggest driver of variation
Ready-mix, 4,000 psi, quoted (before tax and delivery extras) CY $140 – $195 † $160 Cementitious content, admixtures, delivery radius, market
Concrete material, all-in per CY (tax, short-load, curing, accessories) CY $160 – $215 † $177.90 Sales-tax treatment, pour size, short-load frequency
Lightweight concrete, elevated slab topping CY $175 – $235 † $198 Aggregate availability; lightweight is a regional commodity
Spread footings — concrete placed and finished (excludes forms and rebar) CY $200 – $300 † $242.34 Placement method (chute vs. pump) and footing scatter
Foundation walls — concrete placed and finished CY $230 – $340 Wall height, number of corners and step-downs
Slab on grade, complete (vapor barrier, reinforcing, place, finish, cure, saw) SF $6.50 – $10.50 † $8.15 Thickness, flatness tolerance, and finish class
Slab on grade, direct cost only SF $5.00 – $7.50 † $6.13 The gap to the carried number is supervision, small tools, productivity contingency, and self-perform markup
Formwork, foundation walls (both faces, ≈10 ft, good reuse) SFCA $5.00 – $8.50 † $6.28 Reuse cycles. Panel amortization dominates
Formwork, footings and pile caps (low height, short runs) SFCA $7.50 – $12.00 Little reuse, high setup per SF — expect footing formwork to run above wall formwork per SFCA
Formwork, columns and elevated beams SFCA $8.00 – $16.00 Shape, height, and finish class
Reinforcing steel, furnished, fabricated, delivered, installed LB $0.90 – $1.35 † $1.05 Bar size mix, bends, coating, inspection regime
Reinforcing steel, epoxy-coated, heavy bending, DOT inspection LB $1.25 – $1.75 † $1.42 (Cottonwood Creek) Coating, bend complexity, traffic control, inspection
Class A structural concrete, bridge substructure CY $560 – $850 † $685 (Cottonwood Creek) Access, forming complexity, placement over water
36-inch drilled shaft, complete LF $320 – $520 † $412 (Cottonwood Creek) Soil and rock conditions, casing, spoils handling
Architectural precast panels, furnished and erected SF of panel $48 – $95 Finish, panel size, repetition, connection complexity, crane

C.3.3 Division 04 — Masonry

Item Unit Illustrative range Biggest driver of variation
8-inch CMU, standard, laid SF of wall $17 – $30 Wall height, scaffolding, reinforcing and grout frequency
8-inch CMU, reinforced and fully grouted SF of wall $24 – $40 Grout spacing — the difference between "some cells" and "all cells" is enormous
Burnished or ground-face CMU SF of wall $30 – $55 Unit cost and the care required in laying and cleaning
Brick veneer, modular, running bond SF of wall $28 – $52 Brick cost, wall height, and pattern complexity
Cast stone sills and copings LF $60 – $180 Piece size, profile, anchorage
Additional CMU, unit price for change work SF $25 – $34 † $26.90 – $31.20 (Northgate masonry bid tab) Which bidder, and what the unit price is stated to include

C.3.4 Division 05 — Metals

Item Unit Illustrative range Biggest driver of variation
Structural steel, furnished and erected, 3–6 story frame TON $3,900 – $6,200 † $4,850 Tons per piece. Connection count per ton drives fabrication and erection more than weight does
Structural steel erection only (labor, crane, crew) TON $520 – $850 † $655 base rate Crane availability, site access, sequence, and whether a second crew is running
Composite metal deck, furnished and installed SF $2.75 – $4.50 † $3.35 Gauge, depth, span, and shear-stud count
Open-web steel joists, furnished and erected TON $3,600 – $5,800 Span, depth, and bridging requirements
Miscellaneous metals — lintels, embeds, angles, supports LB $2.50 – $6.00 Piece count. Miscellaneous metals is a piece trade priced by weight, which is why it always over-runs
Pan-filled stairs and rails riser $600 – $1,400 Rail type, finish, and code-required guard details

C.3.5 Division 06 — Wood, Plastics and Composites

Item Unit Illustrative range Biggest driver of variation
Rough carpentry, blocking and nailers, framed LF $4.50 – $11.00 Location (in-wall vs. at roof), height, and fastening method
In-wall backing plates, 16-gauge strap or plywood EA $22 – $70 Size, location, and whether it is installed with the framing or afterward
Wood-framed floor and roof, platform framing SF of floor $9 – $20 Span, engineered lumber content, lumber market
Plastic-laminate casework, standard LF $190 – $420 Configuration, hardware grade, countertop material
Solid-surface countertop, fabricated and installed LF $95 – $260 Material, edge profile, sink cutouts

C.3.6 Division 07 — Thermal and Moisture Protection

Item Unit Illustrative range Biggest driver of variation
TPO single-ply membrane roof, fully adhered, with insulation SF $9 – $19 Insulation R-value and thickness, warranty term, penetration count
Below-grade waterproofing, sheet-applied SF $6 – $16 System type, detailing at penetrations, protection course
Self-adhered air and water barrier, wall SF $3.00 – $7.50 Transitions. The field of the wall is cheap; the transitions are the cost
Continuous exterior insulation, mineral wool with clips SF $6 – $14 Thickness, clip system, thermal-break requirement
Spray-applied fireproofing SF of surface $2.50 – $7.00 Required hourly rating, member shapes, access
Firestopping, through-penetrations EA $45 – $180 System type, rating, and whether the penetration was sleeved
Exterior joint sealant, two-part LF $5 – $14 Joint size, backer, substrate prep, and height above grade

C.3.7 Division 08 — Openings

Item Unit Illustrative range Biggest driver of variation
Unitized aluminum curtain wall, furnished and installed SF $85 – $200 Unit size, glass makeup, thermal and performance requirements, hoisting method
Stick-built aluminum curtain wall SF $65 – $145 Field labor content — stick systems trade shop cost for field cost
Aluminum storefront SF $55 – $110 Framing depth, finish, and door count
Hollow metal door, frame, and hardware, complete opening $1,400 – $4,200 Hardware set. The door is cheap; the hardware set is the number
Wood door in hollow metal frame, complete opening $1,600 – $4,800 Veneer, fire rating, and hardware
Automatic sliding entrance EA $16,000 – $45,000 Configuration, breakout requirement, controls

C.3.8 Division 09 — Finishes

Item Unit Illustrative range Biggest driver of variation
Metal-stud partition framing (framing only, no board) SF of wall $3.20 – $5.50 † $4.14 Stud gauge and spacing, wall height, opening density, and access
Gypsum board, hung and finished, one face, Level 4 SF of face $2.10 – $3.40 Finish level, ceiling height, and rework rate
Gypsum board material only SF $0.34 – $0.58 † $0.42 Board type, thickness, and market
Complete partition, framed and boarded both faces, Level 4 SF of wall $9 – $17 Everything above, plus rating and insulation
Shaft wall assembly SF $12 – $24 Height, rating, and whether it is built from one side
Acoustical ceiling grid and tile SF $4.50 – $11.00 Tile grade, grid type, seismic requirements, border cuts
Resilient flooring, luxury vinyl tile SF $5.00 – $12.00 Substrate preparation and moisture mitigation, which is where the money hides
Porcelain tile, floor, thin-set SF $12 – $30 Tile size, pattern, waterproof membrane
Painting, gypsum walls, two coats over primer SF $0.85 – $2.20 Surface prep, color changes, height, and cutting-in density

C.3.9 Divisions 10–14 — Specialties through Conveying

Item Unit Illustrative range Biggest driver of variation
Toilet compartments, solid plastic, floor-mounted stall $1,100 – $2,600 Material and mounting style
Toilet accessories, typical restroom set restroom $900 – $3,200 Accessory count and grade
Interior signage, code and wayfinding SF of building $0.60 – $2.50 Wayfinding program complexity
Wall protection, corner guards and rails LF $18 – $60 Material and healthcare requirements
Commercial food service equipment, café SF of café $110 – $340 Menu and equipment list — a vendor number, not an estimate
Window treatments, roller shades, manual SF of window $9 – $28 Fabric, motorization, and pocket details
RF shielding and lead lining, imaging suite SF of shielded surface $28 – $90 Shielding level required by the physicist's report
Passenger elevator, 3,500 lb, 4 stops EA $190,000 – $340,000 Speed, finishes, code requirements, and market

C.3.10 Divisions 21–28 — Facility services

MEP is a third of the money on a building like Northgate — Divisions 21 through 28 total $12,935,000, or 32.3% of the cost of work. It is also the family of divisions where $/SF of building is a far more reliable estimating and checking measure than any component unit price, because the systems are designed as systems.

Item Unit Illustrative range Biggest driver of variation
Wet-pipe sprinkler system, light hazard SF of building $3.00 – $7.00 † $4.24 Hazard classification, ceiling type, seismic bracing
Plumbing, complete, healthcare outpatient SF of building $9 – $22 † $13.48 Fixture count and medical gas scope
HVAC, complete, healthcare outpatient SF of building $28 – $58 † $39.32 Air-change requirements, redundancy, filtration
Sheet metal ductwork, fabricated and installed LB $9 – $18 Gauge mix, fitting density, and hanger requirements
Building automation and DDC controls SF of building $2.50 – $7.00 † $3.56 Point count and integration scope
Electrical, complete, healthcare outpatient SF of building $22 – $46 † $29.24 Service size, generator, lighting package, low-voltage split
Structured cabling and communications backbone SF of building $2.50 – $8.00 † $4.39 Drop count and AV scope
Fire alarm, access control, and video SF of building $2.00 – $6.00 † $3.75 Device density and security program

C.3.11 Divisions 31–33 — Sitework

Item Unit Illustrative range Biggest driver of variation
Mass excavation, cut and load BCY $4.50 – $12.00 Haul distance on site, material, and equipment fleet match
Haul off site and dump, including tipping LCY $12 – $28 † $18.50 Round-trip haul time and tipping fee. Note the unit is loose, not bank
Structural excavation, bridge substructure CY $28 – $55 † $38.50 (Cottonwood Creek) Dewatering, sheeting, and working over water
Import borrow, delivered and placed CY $12 – $26 † $16.50 Haul distance from the borrow source
Trench excavation and backfill, building utilities CY $7 – $16 † $9.50 Depth, protective system, and existing utility congestion
Pipe-zone bedding stone CY $24 – $42 † $31.00 Aggregate market and haul
4-inch SDR-35 PVC sanitary, installed complete LF $22 – $40 † $27.66 Depth, protective system, and production rate assumption
Asphalt paving, 3-inch binder plus 1½-inch surface SY $22 – $40 † $28 Liquid asphalt price, which moves independently of everything else
Concrete sidewalk, 4-inch SF $7 – $16 Thickness, finish, jointing, and quantity
Concrete curb and gutter LF $22 – $48 Radius work versus tangent
Landscape and irrigation SF of landscaped area $3 – $14 Plant size and irrigation coverage

C.3.12 Whole-building benchmarks — the check, not the estimate

These are for sanity-checking a completed estimate, and for conceptual work before quantities exist. Use them the way §12.4.5 uses them: take off a quantity, extend it, then convert the answer into a unit you have history for and ask whether it looks like reality.

Building type Illustrative $/SF range Anchor
Outpatient medical / ambulatory surgery $310 – $420 $360/SF — Northgate, $47,500,000 ÷ 132,000 SF
Municipal community/recreation center $250 – $340 $283.33/SF — Willow Street, $6,800,000 ÷ 24,000 SF
Public elementary school $230 – $330 Rivermont Elementary #12, $22.4M
Public library $280 – $400 Ridgeline Regional Library, $31.4M
Speculative office, core and shell $130 – $230 Shell only — fit-out is a separate number
Warehouse / distribution, tilt-up $70 – $150 Clear height and dock count drive it
Production single-family housing $130 – $230 Harbor Ridge; excludes land and lot development

A caution about $/SF that is worth more than the table. A dollar-per-square-foot number is a statement about a building type in a market in a year. It is a check, not an estimate, and its accuracy is bounded by the completeness of the design, not by the estimator's skill. If your detailed summary says $268/SF on a building whose comparables run $310–$385, do not congratulate yourself — go find what fell out.


C.4 Productivity rates and crew compositions

These are the trades a construction manager most often self-performs or must independently price. For each: a representative crew, a production-rate range, and the man-hours per unit equivalent.

⚠️ Illustrative. These are planning values from a teaching text, not measured data.

C.4.1 Why man-hours per unit is the more stable measure

A production rate — "465 square feet of contact area per crew-day" — is three assumptions bundled into one number: how many people, how many hours in a day, and how much they install. Change any one of them and the number moves, even when nothing about the work changed.

Man-hours per unit strips out crew size and shift length and leaves only the labor content of the work.

                          crew size × hours per day
   MH per unit  =  ————————————————————————————————————
                     units produced per crew-day

Work the formwork crew both ways:

   Crew of 5, 8-hour day, 465 SFCA per day
     Production rate     = 465 ÷ 8      = 58.125 SFCA per crew-hour
     Man-hours per unit  = (5 × 8) ÷ 465 = 0.0860 MH/SFCA

Now put six people on it and get 540 SFCA a day. The production rate rises to 67.5 SFCA per crew-hour, which looks like an improvement. The man-hours per unit rises too — (6 × 8) ÷ 540 = 0.0889 MH/SFCA — which tells you the truth: you added 20% more labor and got 16% more output. The crew got less efficient per hour of labor, and only the man-hour measure showed it.

Three reasons the profession budgets in man-hours:

  1. It survives crew-size changes. A foreman who adds two people has not changed the labor content of the work.
  2. It survives shift-length changes. Ten-hour days do not make a wall cheaper to frame.
  3. It is the unit your cost report already collects. Timecards record hours, not crew-days (Chapter 28), so man-hours per unit is the measure your own history will produce without any extra effort — which is the entire point of §C.11.

The practical rule: budget in man-hours, schedule in crew-days. The estimate tracks labor content; the schedule needs a duration, and a duration requires you to decide a crew size.

C.4.2 Crew compositions and production rates

Burdened rates in the crew tables are the canonical Northgate rates built in §12.7.1.

Earthwork — mass excavation and haul

Crew Composition Production range MH per unit
Mass excavation, load-and-haul 1 operator (excavator) · 1 operator (dozer/spotter) · 1 laborer/grade checker · truck fleet priced separately 900 – 2,200 BCY per 8-hr day 0.011 – 0.027 MH/BCY (excludes trucking)
Structural excavation, footings 1 operator · 2 laborers 90 – 220 BCY per day 0.11 – 0.27 MH/BCY
Trench and pipe crew, 4–8 in. sanitary 1 foreman · 1 pipelayer · 2 laborers · 1 operator (5 total) 120 – 220 LF per 8-hr day † 160 LF 0.18 – 0.33 MH/LF † 0.25 MH/LF
Backfill and compaction, in lifts 1 operator · 1 laborer with compactor 180 – 420 CCY per day 0.04 – 0.09 MH/CCY

Driver: haul cycle time governs mass excavation completely. A 4-minute change in cycle time can move production 25% without anyone working differently.

Formwork

Crew Composition Production range MH per unit
Foundation wall forms, gang panels, 10 ft 1 foreman ($66.54) · 3 carpenters ($50.47) · 1 laborer ($39.51) = $257.46/hr 380 – 620 SFCA per 8-hr day † 465 0.065 – 0.105 MH/SFCA † 0.086
Footing and pile-cap forms 1 foreman · 2 carpenters · 2 laborers 260 – 450 SFCA per day 0.089 – 0.154 MH/SFCA
Column forms, prefabricated 1 foreman · 3 carpenters · 1 laborer 300 – 520 SFCA per day 0.077 – 0.133 MH/SFCA
Elevated deck forming and shoring 1 foreman · 5 carpenters · 3 laborers 900 – 1,700 SF of deck per day 0.042 – 0.080 MH/SF

Driver: reuse cycles. A form system used eight times and a form system used twice have the same labor content per cycle and wildly different amortized material cost — and the second one has more setup labor per SFCA because there is less repetition to learn from.

Reinforcing steel

Crew Composition Production range MH per unit
Footings and grade beams 1 foreman · 4 rodmen 2.2 – 4.5 TON per 8-hr day 8.9 – 18.2 MH/TON
Slab on grade, mesh or light bar 1 foreman · 3 rodmen 3.5 – 6.5 TON per day 4.9 – 9.1 MH/TON
Walls and columns 1 foreman · 4 rodmen 1.8 – 3.6 TON per day 11.1 – 22.2 MH/TON
Elevated slabs, top and bottom mats 1 foreman · 5 rodmen 2.8 – 5.2 TON per day 9.2 – 17.1 MH/TON

Driver: bar size. A ton of #4 bar is many more pieces, ties, and lifts than a ton of #9. Small bar is expensive per ton and cheap per pound of structure.

Concrete placement and finishing

Crew Composition Production range MH per unit
Spread footings, chute and pump mix 1 foreman ($66.54) · 2 carpenters ($50.47) · 1 cement finisher ($46.47) · 4 laborers ($39.51) = 8 workers, $371.99/hr 45 – 85 CY per 8-hr day † 62 0.75 – 1.42 MH/CY † 1.03
Foundation walls, pumped 1 foreman · 1 finisher · 5 laborers 55 – 110 CY per day 0.51 – 1.02 MH/CY
Slab on grade, laser screed, ride-on trowels 1 foreman · 6 cement masons · 2 laborers · 1 pump operator = 10 workers 5,000 – 9,000 SF per 10-hr day † 6,600 0.011 – 0.020 MH/SF † 0.0152
Elevated slab topping on metal deck 1 foreman · 6 finishers · 3 laborers 4,000 – 8,000 SF per day 0.013 – 0.025 MH/SF

Driver: truck rotation. A slab crew is a queueing system. If the plant cannot keep a truck in front of the pump, the crew's production is set by the batch plant, not by the crew.

Masonry

Crew Composition Production range MH per unit
8-inch CMU, standard, laid 1 foreman · 4 masons · 3 tenders (8 total) 260 – 480 SF of wall per 8-hr day 0.13 – 0.25 MH/SF
8-inch CMU, reinforced and grouted Same crew plus grout pump 180 – 340 SF per day 0.19 – 0.36 MH/SF
Brick veneer, running bond 1 foreman · 4 masons · 3 tenders 220 – 420 SF per day 0.15 – 0.29 MH/SF
Burnished/ground-face CMU 1 foreman · 4 masons · 3 tenders 150 – 280 SF per day 0.23 – 0.43 MH/SF

Driver: scaffolding and material staging. Masonry production is a materials-handling problem wearing a trowel. Tender-to-mason ratio and how far the block travels decide the day.

Structural steel erection

Crew Composition Production range MH per unit
Raising gang, building steel 1 foreman · 4 ironworkers · 1 operator · 1 oiler (7 total) 22 – 45 TON per 8-hr day 1.24 – 2.55 MH/TON
Detail/bolt-up gang 1 foreman · 3 ironworkers 15 – 35 TON per day 0.91 – 2.13 MH/TON
Metal deck laying 1 foreman · 4 ironworkers 4,500 – 9,000 SF per day 0.0044 – 0.0089 MH/SF
Shear studs, welded 2 ironworkers 350 – 800 studs per day 0.020 – 0.046 MH/EA

Driver: tons per piece. A frame averaging 3 tons per piece erects several times faster per ton than one averaging 0.8 tons per piece, because the crane cycle is per pick, not per ton. Northgate's 985 tons is a moderately complex four-story frame.

Metal-stud framing

Crew Composition Production range MH per unit
Interior partitions, 3⅝" @ 16" o.c., 10'-6" walls 1 foreman ($66.54) · 4 carpenters ($50.47) · 1 laborer ($39.51) = 6 workers, $307.93/hr 850 – 1,400 SF of wall per 8-hr day † 1,050 0.034 – 0.056 MH/SF † 0.046
Same, clear-access open plan (warehouse, big-box) Same crew 1,100 – 1,500 SF per day 0.032 – 0.044 MH/SF
Same, occupied-facility corridor with restricted access Same crew 450 – 750 SF per day 0.064 – 0.107 MH/SF
Exterior cold-formed backup framing 1 foreman · 4 carpenters · 1 laborer 550 – 950 SF per day 0.051 – 0.087 MH/SF

Driver: opening density and access. Ray's most expensive estimating mistake lives in the second and third rows of this table: 1,180 SF/day of warehouse framing became 540 SF/day in an occupied hospital corridor, and the mistake was not the rate — it was the undocumented rate.

Gypsum board

Crew Composition Production range MH per unit
Hang, one layer, walls 1 foreman · 3 hangers · 1 laborer 2,600 – 4,600 SF per 8-hr day 0.009 – 0.015 MH/SF
Hang, ceilings and soffits 1 foreman · 3 hangers · 1 laborer 1,600 – 3,000 SF per day 0.013 – 0.025 MH/SF
Tape and finish, Level 4 1 foreman · 4 finishers 2,800 – 5,000 SF per day 0.008 – 0.014 MH/SF
Tape and finish, Level 5 1 foreman · 4 finishers 1,800 – 3,200 SF per day 0.013 – 0.022 MH/SF

Driver: sheet size versus wall height, which is also the driver of the waste factor. A crew hanging 4×12 board vertically on 10'-6" walls throws away eighteen inches off every sheet and handles every sheet twice.

Rough carpentry

Crew Composition Production range MH per unit
In-wall blocking and backing, metal stud 2 carpenters 180 – 400 LF per 8-hr day 0.040 – 0.089 MH/LF
Equipment backing plates 2 carpenters 20 – 45 EA per day 0.36 – 0.80 MH/EA
Wood floor and roof framing, platform 1 foreman · 4 carpenters · 1 laborer 900 – 1,900 SF per day 0.025 – 0.053 MH/SF
Sheathing, walls and roof 1 foreman · 3 carpenters 1,800 – 3,600 SF per day 0.009 – 0.018 MH/SF
Miscellaneous blocking at roof curbs and openings 2 carpenters 90 – 220 LF per day 0.073 – 0.178 MH/LF

Driver: piece count, not quantity. General trades and rough carpentry are the two scopes where a countable physical unit is hardest to define, which is why Kestrel codes 06-1000-L in man-hours rather than a physical unit — an honest choice that costs you the ability to compute a productivity factor. Accept that trade openly rather than inventing a fake denominator.


C.5 Productivity adjustment factors

⚠️ Read these as planning heuristics with explicit caveats. They are not measured constants.

The direction of every effect below is well established across the industry literature. The magnitude on any specific job is not, and several are actively contested. Industry bodies including AACE International, the Mechanical Contractors Association of America, the National Electrical Contractors Association, and the Lean Construction Institute have published extensively on labor inefficiency and its measurement; go to them for the underlying studies and their limits. This appendix does not reproduce their tables and does not invent numbers with their authority attached.

Use these to price a decision. Use measured data from your own job to prove one.

C.5.1 The factor table

Condition Illustrative factor What is actually happening
Baseline: day shift, 40-hour week, clear access, moderate weather, single trade 1.00 The conditions your historical data was collected under — know what they were
50-hour week (5 × 10), sustained 4+ weeks 0.90 – 0.95 Loss grows with duration; the first week is nearly free
60-hour week (6 × 10), sustained 4+ weeks 0.80 – 0.88 Fatigue, absenteeism, error and rework rates all rise together
70+ hour week, sustained 0.70 – 0.82 Beyond this the marginal hour can approach zero net output
Second shift 0.85 – 0.95 Supervision quality is the driver, not darkness. A second shift with a real foreman and a real plan performs
Third shift 0.75 – 0.90 Plus reduced availability of supervision, inspection, and material delivery
Two trades in the same area 0.90 – 0.95
Three trades in the same area 0.80 – 0.90
Four or more trades stacked in one area 0.70 – 0.85 This is what acceleration actually buys you
Sustained cold, below freezing 0.75 – 0.90 Plus temporary heat, enclosure, and protection as direct cost
Extreme heat and humidity 0.85 – 0.95 Plus mandatory rest cycles, which are a schedule input, not a suggestion
Work above ≈30 ft (lift-dependent access) 0.85 – 0.95 Travel time to and from the work, plus material staging
Work above ≈100 ft (hoist-dependent) 0.78 – 0.90 Hoist queueing becomes the constraint on the whole floor
Restricted access / adjacent occupied facility 0.80 – 0.92 Northgate's north property line lives here
Occupied healthcare or laboratory, infection control 0.55 – 0.80 Barriers, negative-pressure enclosures, escorted routes, work windows
Small confined areas, congested overhead 0.75 – 0.90
Repetitive work, third floor and above (learning curve) 1.05 – 1.20 The one factor that works for you
Repetitive work, first cycle (the learning cost) 0.70 – 0.85 Every learning curve is paid for at the start
Rework or out-of-sequence work 0.60 – 0.80 The most expensive condition on this list
Supervision ratio thinner than about 1 foreman per 12–15 workers 0.85 – 0.95 The cheapest productivity purchase on any job is one more foreman
Excessive crew size for the work face 0.75 – 0.92 Adding people to a congested area subtracts output
High crew turnover / heavy use of unfamiliar labor 0.80 – 0.92 Every new person restarts a learning curve

C.5.2 Four cautions that matter more than the numbers

One: the factors are not independent, and you must not simply multiply them. Stacking four trades and running sixty-hour weeks is not 0.78 × 0.84. The conditions overlap — the congestion is part of why the overtime is unproductive — and multiplying them stacks the same loss twice. When you use more than one factor, apply the largest, then adjust modestly for the others, and state in your basis of estimate exactly what you did.

Two: know what your baseline was. A factor is a ratio to a base. If your historical rate was collected on a job that already had two trades in the area, applying a trade-stacking factor to it double-counts. This is why §12.8 says the rate is the smaller half of the answer and the written basis is the larger half.

Three: a factor is a planning aid, not an entitlement. The measured-mile method (Chapter 31) — comparing an unimpacted period of the same work by the same crew to an impacted period — proves disruption. A table of factors does not, and a claim built on published factors alone will be attacked and usually beaten.

Four: the asymmetry. A production loss costs more than it looks like, because material does not care how long you took. Only the time-based portion of the unit cost inflates:

   Production drops 15%  →  time-based cost rises by 1 ÷ 0.85 = 17.6%

On the Chapter 12 formwork example, a 15% production loss raised the unit cost 14.3% and the labor-and-equipment portion 17.6%. Losses compound against you; they do not scale one for one.

C.5.3 Overtime, worked

Because this is the decision people price wrong most often. Baseline: the crew of 5 at $257.46/hr, 58.125 SFCA per crew-hour. Go to 6 × 10 = 60 hours, sustained, at the mid-range factor of 0.84.

   Adjusted rate = 58.125 × 0.84 = 48.825 SFCA/crew-hr

   Baseline week:  58.125 × 40 hr = 2,325.0 SFCA
   OT week:        48.825 × 60 hr = 2,929.5 SFCA
   Additional output:                  604.5 SFCA   (+26.0%)

   Baseline weekly labor: 40 × $257.46                = $10,298.40
   OT weekly labor:       60 × $257.46 + 20 × $104.69 = $17,541.40
   Additional cost:                                      $7,243.00

   $7,243 ÷ 604.5 SFCA = $11.98 per additional SFCA

Baseline labor unit cost is $4.43/SFCA. The marginal square foot bought with overtime costs nearly triple. Sustained overtime is not a productivity strategy. It is a time purchase, and you should know its price before you buy it — which on Northgate is why acceleration and absorption came out within about $13,050 of each other and the decision got made on Meridian's interim clinic lease instead.

⚠️ And the cost that is not in the arithmetic. Sustained sixty-hour weeks raise incident rates. On Northgate, the acceleration after the steel delay produced trade stacking, a rework event on deck-edge detailing, and a near-miss spike in weeks 34 through 36 — 22 near-misses against a running average of about 2.5 a week. An estimate carrying an optimistic production rate is a schedule-pressure generator, and schedule pressure is a hazard exactly like an unguarded edge. Price the rate you can achieve safely.


C.6 Waste, shrinkage, and loss factors

Every material quantity has two versions: the quantity that ends up in the building and the quantity you have to buy. The gap is waste, and it is a real budgetable cost, not a rounding error.

C.6.1 The waste table

Material Typical allowance What drives it
Ready-mix, footings against earth 2 – 5% Over-excavation, spillage, short loads
Ready-mix, formed walls and columns 1 – 3% Form deflection, spillage
Slab on grade 2 – 4% Subgrade tolerance, screed variation
Elevated slab on metal deck 3 – 8% Deck deflection under wet concrete — real, and routinely missed
Reinforcing steel 3 – 7% (laps are quantity, not waste) Cut-offs, damage, mis-fabrication
Structural steel ≈0% Shop-fabricated to length
Metal studs and track 5 – 10% Cut-offs; wall heights versus stock lengths
Gypsum board 8 – 15% Wall heights versus sheet sizes, openings, damage
Dimensional lumber 8 – 15% Cut-offs, culling, defects
Plywood and sheathing 5 – 12% Layout and cutting patterns
CMU 3 – 6% Breakage, culling
Brick 3 – 8% Breakage, blending, culling for color
Pipe (PVC, copper) 3 – 8% Cut-offs, fitting takeouts
Conduit and wire 5 – 12% Pulls, makeup slack, cut-offs
Sheet metal duct 5 – 12% Fabrication drops, field fitting
Acoustical ceiling tile 5 – 10% Border cuts
Resilient flooring and carpet 5 – 15% Pattern match, room geometry, roll width
Paint and coatings 5 – 10% Roller and spray loss, touch-up
Insulation, batt 5 – 10% Friction-fit trimming
Sealant 8 – 20% Joint size variation, gun waste, cure of partial cartridges

These are not universal constants. They vary by crew, by layout, by the stock sizes available in your market, by weather, and by how tidy your site is. A company that tracks its own waste from its own cost reports replaces every number in this table within about three years, and its estimates get better for it.

C.6.2 Earthwork is a different problem: swell and shrinkage

Dirt is not wasted; it changes volume. Three states, three numbers for the same material.

Measure Abbreviation What it is Where you meet it
Bank BCY In place, undisturbed The grading plan, the cut/fill calculation
Loose LCY Excavated, in the truck or the stockpile Hauling, disposal fees, stockpile capacity
Compacted CCY Placed and compacted to spec density The finished embankment, the backfill
Material Typical swell (bank → loose) Typical shrinkage (bank → compacted)
Sand, gravel 10 – 18% 5 – 12%
Common earth / sandy loam 20 – 30% 10 – 15%
Clay 25 – 40% 10 – 20%
Blasted rock 50 – 80% Bulks permanently; needs a project-specific factor

These ranges are directional planning values. Use the project geotechnical report, and on a large earthwork job, a test strip. Do not treat a published range as a number.

C.6.3 The arithmetic of applying them

Material waste — inflate the quantity:

   Quantity to buy = neat quantity × (1 + waste factor)

Northgate footings: 1,216.43 CY neat × 1.019 = 1,240 CY carried. The estimate does not carry the geometry; it carries the geometry plus a named, quantified allowance.

Bank to loose — inflate for haul:

   LCY = BCY × (1 + swell)

32,000 BCY × 1.25 = 40,000 LCY. At $18.50 per loose cubic yard hauled and dumped, that is $740,000 — an equivalent bank-measure rate of $23.13/BCY. Extend the bank quantity against the loose rate and you are $148,000 short on one line.

Bank to compacted — deflate for fill:

   CCY = BCY × (1 − shrinkage)

12,000 BCY × 0.88 = 10,560 CCY. If the grading plan needs 12,000 CCY in place, you are 1,440 CCY short and must import 1,440 ÷ 0.88 = 1,636 BCY of borrow.

C.6.4 The two rules that keep waste from costing you twice

Rule one: pick a place and put it there. Either inflate the quantity or inflate the unit price — never both. Kestrel's convention is quantity, because a quantity you can see is a quantity you can audit. Doing both on Northgate's footings alone manufactures $4,414 of phantom cost. Scale that across forty divisions.

Rule two: waste is a material factor, not a labor factor. Your crew does not install the waste. Applying a waste factor to labor hours budgets crew time to install concrete that went home in the drum. (The exception: material handled twice — cut-off drywall carried to a dumpster — is a real labor cost, but you capture it in the productivity rate, not in a waste factor.)


C.7 The burdened labor rate — a build-up template

The wage is not the cost. The burdened rate is the cost, and on commercial work the gap runs roughly 35% to 55% of the base wage, and higher on high-hazard classifications and union work.

C.7.1 The template, blank and worked side by side

Fill the middle column for your own market. The right-hand column is the canonical Northgate carpenter from §12.7.1, carried through so you can see the shape.

# Component Basis — fill this in Northgate carpenter (illustrative)
1 Base wage `$__________ /hr` | $34.00
2 Health and welfare `$______ /hr` or `____% of base` | $4.85
3 Retirement / 401(k) ____% of base $1.36 (4.0%)
4 Vacation, holiday, sick accrual ____% of base $1.87 (5.5%)
5 Other negotiated fringes (training, apprenticeship, industry funds) $______ /hr
A. Wage plus fringes $42.08
B. Taxable wage base (base + taxable fringes; bona fide plan contributions are commonly excluded, vacation/holiday commonly included) $__________ $35.87
6 Social Security (FICA) 6.2% × B $2.22
7 Medicare 1.45% × B $0.52
8 Unemployment (FUTA + SUTA, blended effective) ____% × B $1.04 (2.9%)
Payroll taxes subtotal $3.78
9 Workers' compensation manual rate ÷ 100 × EMR × B $2.88 (9.80/100 × 0.82 = 8.04%)
10 General liability insurance ____% × B $0.68 (1.90%)
11 Small tools and consumables ____% × A $1.05 (2.5%)
12 Other (uniforms, per diem, travel, drug testing, badging) $______ /hr
FULLY BURDENED HOURLY COST $50.47
Burden factor = burdened ÷ base 1.484 → 48.4%

C.7.2 Six notes that decide whether the template is right

The taxable wage base is not the same as wage plus fringes. Bona fide contributions to a benefit plan are generally not taxable wages; vacation and holiday pay generally is. Compute payroll taxes on line B, not on line A. Get this backwards and you over-burden every hour in the estimate. Tax treatment of fringes varies and changes — confirm the current treatment with your controller, not with a textbook.

FUTA has a low annual wage cap and SUTA varies enormously by state and by your own experience rating. The blended figure in any template is company-specific and year-specific. "Look up the rate" is the wrong instinct; "ask accounting for last year's effective rate" is the right one.

Workers' compensation is priced by class code, and the spread is brutal. Manual rates are set by state rating bureaus, vary by jurisdiction, and change. Below is the shape of the spread, expressed as a multiple of a carpentry rate — not as rates, because rates are jurisdictional:

Classification Illustrative multiple of the carpentry rate Why
Clerical / office 0.03 – 0.08× Almost no injury exposure
Estimator / project management (field-visiting) 0.10 – 0.20× Occasional site exposure
Electrician, plumber, HVAC 0.55 – 0.85× Lower fall and struck-by exposure than framing
Painter, drywall finisher 0.75 – 1.00× Ladders and lifts
Carpenter (interior/general) 1.00× (reference)
Concrete, excavation, pipe-laying 1.10 – 1.60× Trench, equipment, and struck-by exposure
Mason, scaffold-dependent 1.20 – 1.80× Fall-from-scaffold exposure
Roofer 2.5 – 4.5× Falls, hot work
Structural ironworker 3 – 6× Falls from height at the leading edge, steel erection
Demolition, high-hazard 3 – 6× Structural instability, unknowns

That table is the answer to "why is an ironworker's burden a multiple of a carpenter's." It is not a judgment about the person. It is the insurance market pricing the observed frequency and severity of injury in that class of work. Two consequences for you: use the correct class code for each classification in each crew — Northgate's laborer burdens to $39.51 in a framing crew and $40.74 in a trench crew, same person, same wage, different work — and understand that if your estimating system carries one burdened laborer rate for the whole job, it is wrong somewhere.

Your experience modification rate multiplies all of it. Kestrel's EMR of 0.82 reflects a good loss history and is worth (1.00 − 0.82) × manual rate × total payroll on every hour the company works. That is the most direct financial argument for a safety program you will ever see, and Chapter 24 makes it properly.

Small tools and consumables — blades, bits, screws, string, chalk, gloves, layout paint — are real and are usually carried as 2–4% of labor because tracking them per unit is not worth the effort.

Union and prevailing-wage work is a different build-up with the same structure. The fringe package is defined by the collective bargaining agreement or the wage determination, contribution rates are specified rather than negotiated, and certified payroll makes the reporting non-optional. Prevailing- wage requirements, thresholds, and reporting vary by jurisdiction and by funding source — the federal Davis-Bacon framework and state "little Davis-Bacon" statutes are not the same and do not always reach the same work. Check the solicitation, not your memory.

C.7.3 The canonical Northgate burdened rates

Use these for internal consistency when working the book's examples.

Classification Base wage Burdened Note
Foreman $46.00 | $66.54
Carpenter $34.00 | $50.47
Cement finisher $31.00 | $46.47
Pipelayer $32.00 | $49.01 Excavation class code, 11.60% comp
Equipment operator $38.00 | $57.26
Laborer — framing/general crew $26.00 | $39.51 7.10% comp
Laborer — trench/excavation crew $26.00 | $40.74 Higher comp class

Three different rates, three different jobs — do not mix them up. An individual burdened rate (above) prices one person's hour. A crew composite — Kestrel's carpentry composite is $58.40/MH and its concrete-crew composite is $54.00/MH — is the weighted average cost of a man-hour from a mixed crew including its foreman, and it is what you use to price a change order. A site-wide blended rate — Northgate's is $66.00/MH across everybody from a laborer to a sheet-metal journeyman — is what you use to price a site-wide disruption, and it is meaningless for any single trade.


C.8 General conditions checklist

General conditions are the cost of having a project rather than the cost of building the building. Nothing in this list becomes part of the finished structure, and on Northgate it is $2,900,000 — 7.25% of the cost of work.

The TD column is the one that matters: time-dependent items are billed per unit of time and convert directly into a daily burn rate. One-time items do not.

C.8.1 Project staff

Item TD? Note
Project executive / operations manager (allocation)
Senior project manager Carried longer at both ends for precon and closeout
Project manager / assistant project manager
Project superintendent The longest-duration line on most jobs
Assistant superintendent(s) Peak field period only — this is the line most often cut on bid day
Field engineer / project engineer
Project accountant (allocation)
Safety manager (allocation)
Scheduler / project controls (allocation)
VDC/BIM support (allocation) Front-loaded into coordination
Quality control manager (allocation)
Administrative assistant (allocation)
MEP coordination manager, where the job warrants one

Staff is $1,578,000 of Northgate's $2,900,000 — 54.4%. Carry that ratio in your head. On most commercial buildings project staff runs between half and two-thirds of general conditions. If your GC estimate puts staff at 30%, you have either forgotten somebody or double-counted the facilities.

C.8.2 Field office and utilities

Item TD? Note
Field office trailers — rental
Trailer delivery, set, skirt, steps, decks, and removal One-time, both ends
Office furnishings, equipment, supplies
Temporary electrical service — install and remove
Temporary electrical — distribution, maintenance, consumption
Temporary water and sanitary service
Temporary heat, enclosure, and fuel Seasonal, not monthly — count the winters
Temporary lighting — install, maintain, remove Mixed Install and removal one-time; maintenance time-dependent
Portable sanitary facilities Size to the peak workforce, not the average
Drinking water and ice

C.8.3 Temporary facilities and site services

Item TD? Note
Temporary fencing, gates, screening Plus relocations, which are real and forgotten
Jobsite signage and graphics
Temporary roads, crane mats, construction entrance Plus maintenance, which is time-dependent
Temporary protection — floor, stair, corner, elevator Mixed Install one-time; maintenance and replacement time-dependent
Dust partitions and infection-control barriers Mixed
Accessible path of travel maintained around the site
Winter conditions — snow and ice control, ground protection Seasonal
Site security — after-hours patrol, cameras, badging
Temporary stairs, ladders, and ramps Mixed
Traffic control, flagging, street occupancy permits

C.8.4 Safety

Item TD? Note
Safety orientation and badging Scales with turnover, not with duration alone
Personal protective equipment, GC-supplied
Fall-protection hardware, anchors, and horizontal lifelines Mixed
Guardrail systems, hole covers, and their maintenance Maintenance is the real cost; installation is not
First aid, AED, emergency supplies
Safety signage, barricades, warning tape
Drug testing and background screening
Site-specific safety plan development and JHA facilitation
Incident investigation reserve

C.8.5 Cleanup and waste

Item TD? Note
Progressive cleanup labor
Dumpsters, hauling, and tipping
Waste sorting and diversion for a rating system or code See Chapter 36
Final cleaning Priced per SF. Budget more than one clean
Post-punch and pre-occupancy touch-up cleaning

C.8.6 Equipment and small tools

Item TD? Note
Hoisting — tower crane, mobile crane, personnel hoist, material hoist Plus one-time erection and dismantling
Forklifts and telehandlers
Small tools and consumables
Jobsite vehicles and fuel
Survey equipment, robotic total station, layout
Scaffolding for common use If it belongs to nobody, it belongs to you
Equipment mobilization and demobilization Real, often forgotten, sometimes larger than a week of rental

C.8.7 Communication and technology

Item TD? Note
Network, internet, and cellular service
Project-management platform seats
Computers, tablets, printers, plotters Mixed
Reproduction, plotting, and shipping
Progress photography, drone, and reality capture
Radios and site communications

C.8.8 Quality, testing, and permits

Item TD? Note
Contractor's own quality control and inspections
Mockups and benchmark installations
Pre-installation conferences
Independent testing laboratory Depends Read the supplementary conditions — owner-retained on Northgate, contractor-retained on many jobs, and that single sentence is worth six figures
Special inspections Depends Same question
Permits and fees not paid by the owner
Surveying, control, benchmarks, and the as-built survey Mixed

C.8.9 Closeout

Item TD? Note
As-built drafting and record-drawing production Cheap weekly, expensive at the end
O&M manual compilation
Warranty administration
Owner training coordination and recording
Commissioning support labor Carry more than you think from functional-test start
Demobilization, trailer removal, site restoration
Attic stock inventory and storage
Punch crew and pick-up labor Runs on a calendar and is routinely underfunded

C.8.10 Converting the checklist into a burn rate

   General-conditions burn rate = total general conditions ÷ contract duration in calendar days
Project GC total Duration Computed Contract rate Total daily exposure with LDs
Northgate Outpatient Pavilion $2,900,000 | 565 CD | $5,132.74/CD $5,150/CD $10,650/CD (+ $5,500 LDs)
Willow Street Community Center $680,000 | 425 CD | $1,600.00/CD $1,600/CD $2,800/CD (+ $1,200 LDs)
Rivermont Elementary #12 $1,612,000 | 610 CD | $2,642.62/CD $2,400/CD as bid The gap is the point: shaving the burn rate on bid day reduces your own extended-GC recovery later

Roughly $2.28 million of Northgate's $2.9 million is time-dependent. It does not care how much work got done this month. It only cares that the month happened. A schedule slip is already a cost problem, automatically, the instant it happens, before anybody argues about who caused it.

⚖️ The honest caveat on extended general conditions. A stipulated daily rate is an average, and extended general conditions are really a marginal rate at the end of the job — by then the assistant superintendent has rolled off, the trailers are down to one, and temporary heat is finished. A true marginal build-up might be materially lower; conversely, an extension landing at peak staffing can cost more than the stipulated rate. A stipulated rate trades accuracy for the elimination of a fight. That is usually a good trade, and it is a trade, which means somebody is slightly better off. Know which side you are on before you agree to the number.


C.9 The pre-bid estimate review checklist

Two people, about ninety minutes on a job of Northgate's size, before any number leaves the building.

Quantities

  1. Does every quantity cite the sheet and detail it came from?
  2. Was every quantity checked by a second method — count against schedule, area against $/SF, tonnage against SF of building?
  3. Are units labeled on every line? (Yes, every line.)
  4. Have all addenda been incorporated, and has the drawing log been reconciled to the issued-for-bid revision of every sheet?
  5. Do quantities from the enlarged plans, details, and schedules agree with the overall plans?
  6. Is every conceptual factor (lb/CY of rebar, $/SF checks) flagged for replacement when real information arrives?

Unit costs

  1. Is every labor rate burdened, and does the burden use current rates from accounting?
  2. Is the workers' compensation class code correct for each classification in each crew?
  3. Does every production rate have a stated basis and stated conditions?
  4. Has waste been applied exactly once — in the quantity or in the price, not both?
  5. Are earthwork quantities in the right measure (bank, loose, or compacted) for the rate they are extended against?
  6. Is freight in? Is sales tax in, and is the treatment correct for this jurisdiction and this project type?
  7. Is equipment priced with mobilization, demobilization, and idle time?

Subcontracts and quotes

  1. Has every quote been read to the end, including the exclusions on the second page?
  2. Does the bid tab compare scope-corrected numbers rather than face amounts?
  3. Is there an independent in-house number for each major trade, and has any large variance been explained?
  4. Is every quote logged with its validity date, with escalation carried for anything bought after that date?
  5. Have shared exclusions — items every bidder excluded — been circled separately and assigned somewhere?
  6. Does each package have at least two real bidders, or a flagged and loaded plug?

Indirects and markups

  1. Do the general conditions match the current schedule duration, and were they re-run after the last schedule change?
  2. Is contingency tied to a risk register with named risks?
  3. Is escalation applied to the correct scope and the correct window — the unbought portion only?
  4. Is the bond computed on the final price, using the divisor method?
  5. Is the markup the markup that produces the margin you intend?
  6. Are gross-receipts or contractor's excise taxes, where they apply, computed on the price and included in it?

The document

  1. Is there a basis-of-estimate page, and could a stranger price this job from it?

C.10 The bid-day checklist

Bid day failures are almost never estimating failures. They are clerical failures at high speed, and they are enormous.

Item When
All addenda received, logged, acknowledged, and priced T−48 hr
Coverage confirmed: every package has ≥2 real bidders or a documented plug T−24 hr
Alternates, unit prices, and allowances priced and cross-checked against the bid form T−24 hr
Bid bond executed, sealed, dated, and physically in the envelope T−24 hr
Bid form filled out completely — every blank, including the ones that seem stupid T−4 hr
Subcontractor listing form complete, where public bidding rules require it T−4 hr
Quantities cross-checked against the takeoff summary T−4 hr
General conditions verified against the current schedule duration T−4 hr
Bond and insurance recomputed on the current contract value T−2 hr
Escalation base re-checked against what is actually bought T−2 hr
Every plug identified, loaded, and announced with its total T−90 min
Column sums reconciled two ways; formulas verified; formula cells locked T−60 min
$/SF sanity check and variance-to-prior-estimate explanation T−60 min
Final review meeting: who moves the number, and by how much T−45 min
"What did we forget?" — every person in the room speaks once, out loud T−40 min
Number transcribed to the bid form; two people read it back digit by digit T−35 min
Bid physically at the delivery location T−30 min
Receipt confirmed, time-stamped T−5 min

Three rules do most of the work: one person touches the summary; every quote is logged with time, company, number, and stated exclusions before it is evaluated; and the bid leaves early. A bid that is technically finished at 1:58 and physically outside the building at 2:00 is worth nothing.

And the "what did we forget" ritual is not a formality. Everybody speaks — the quote takers, the scribe, the estimator who did earthwork, the person who has been quiet for four hours. "Go around. One thing each. If you have nothing, say nothing." A twenty-three-year-old field engineer saying "we never got a number for the temporary chain-link along Ferry Street" saved $71,000.


C.11 Build your own historical database

Everything above this line is a starting point. This section is the destination.

The reason the numbers in this appendix are illustrative is not modesty. It is that your own data beats anyone's book, and it beats it by a wide enough margin that a company which generates its own history and one which does not are playing different games. Published data is compiled from broad surveys and adjusted by location factor. It cannot know your crews, your foremen, your form system, your subcontractor pool, your site conditions, or your supervision ratio. Your cost report knows all six.

Twenty completed jobs of your own work is a better predictor of your cost than any published table. The catch is that the history only exists if somebody deliberately builds the machinery that produces it — and that machinery is designed before notice to proceed, not at closeout.

C.11.1 Structure cost codes so they generate history

This is Chapter 28's subject, and it is an estimating subject before it is an accounting one.

Kestrel's code has three parts:

        03    -    3100    -    L
        ▲          ▲            ▲
    DIVISION    ACTIVITY     COST TYPE
   CSI Master-  the countable   L = labor
   Format div.  unit of work    M = material
                                E = equipment
                                S = subcontract
                                O = other / indirect

Five requirements. Miss any one and the code produces no usable history.

# Requirement Why history dies without it
1 A CSI MasterFormat spine Your specs, your bids, your estimate, and your schedule of values already use it. A different spine means somebody translates, and translation is where data goes to die
2 A countable unit of measure on every self-perform code No unit, no unit rate. No unit rate, no forecast and no history. 06-1000-L is measured in man-hours because "general trades" has no common denominator — an honest choice with an honest cost
3 Cost type separated: L / M / E / S "12% over" tells you nothing. "Labor 22% over, material on budget, equipment 4% under" tells you the crew is burning hours — a supervision problem you can act on this week
4 Right granularity: at least ~200–400 MH per self-perform code, and no more than 6–10 codes on a foreman's normal day Too coarse and the overrun is invisible until the money is gone. Too fine and the foreman splits his day by guess, which manufactures precise-looking invented data — worse than no data, because people believe it
5 The same structure in five places: the estimate, the control budget, the field time cards, the accounts-payable coding, and the schedule of values If any one diverges, the cost report is fiction and the history is unusable

The single sentence to remember: a company that codes its costs sloppily is not just failing at cost control — it is destroying its own estimating database, and it will not notice for three years.

C.11.2 What to capture at job close

Held two weeks after substantial completion, while the team still exists — not after final completion, when everyone has scattered (Chapter 40).

The estimator and the project accountant sit down for a day and produce one table. Here is what a row must contain:

Field Example Why it is there
Cost code 03-3100-L The key everything joins on
Work item Spread footings — form, place, finish Plain language, so a stranger can use it
Unit CY No unit, no rate
Final quantity 1,240 CY The denominator
Estimated unit cost $332.26/CY What you thought
Actual unit cost $385.48/CY What happened
Variance +16.0% The headline
Diagnosis Two winter placements with blankets and heat; add a cold-weather factor when the pour window crosses December The field that makes the row worth having
Conditions at collection Day shift, single crew, clear access, no stacking So the next estimator knows the baseline the rate belongs to
Man-hours per unit 1.19 MH/CY The stable measure (§C.4.1)
Reuse / repetition 148 repeat footings, gang forms Explains why a rate beat or missed
Keep or discard for the library Keep the base rate; note the event separately The judgment call

The last two rows are where most companies destroy their own data. Northgate's structural steel erection came in at $712/ton against an estimated $655/ton — and the entire variance is the acceleration premium and the second crew after the steel delay. Drop $712 into the unit-cost library and you have permanently overpriced steel erection on every future bid because of one job's one-time event. The right entry is $655, plus a documented note about what acceleration costs when it happens.

A variance without a diagnosis is a number. A variance with a diagnosis is an estimating standard.

Capture four other things in the same session:

  • Productivity by cost code in MH/unit, with the conditions.
  • Waste factors actually experienced, which within about three years will replace every number in §C.6.
  • General conditions actual versus estimated, item by item, which is how you learn that final cleaning is three cleans and commissioning support is 1.5 staff-days a week rather than 0.5.
  • Subcontractor performance evaluations, honestly — including the failures that were yours. These feed the next prequalification.

C.11.3 Normalize before you reuse — time, location, size

A rate from a job three years ago in another city on a building twice the size is not your rate. Three adjustments, applied in this order, before the number enters the library or comes out of it.

1. Time — escalation via a published cost index.

Engineering News-Record publishes construction cost indices — its Construction Cost Index and Building Cost Index are the two most widely used in North America — that track the movement of a fixed market basket of labor and materials over time. Trade associations and government agencies publish others. Use one consistently; do not switch indices mid-library.

                                       index at target date
   Adjusted cost = historical cost × ————————————————————————
                                     index at historical date

Worked: a footing labor rate of $332.26/CY from a job three years ago, with the index up 14.2% since:

   $332.26 × 1.142 = $379.44 / CY

Two cautions. Escalate labor and material separately where you can, because they move independently — a general index blends them and will be wrong on a material-heavy or a labor-heavy scope. And do not escalate what you have already bought. Northgate escalates only the $26,400,000 that was not under firm quote at GMP execution; escalating the whole cost of work would double-count the third of the job already locked and hand a competent owner's estimator a $190,000 error to find.

2. Location.

Published cost data ships with location factors that adjust a national average to a specific city. Use them for published data. For your own data, the more useful adjustment is a direct wage and material comparison: what does a carpenter cost there against here, and what does ready-mix cost there against here? A location factor is a blend; a wage comparison is a fact.

                                    target-market burdened wage
   Adjusted labor = historical × ————————————————————————————————
                                  source-market burdened wage

And note what a location factor cannot tell you: subcontractor availability, market appetite, backlog, weather, code differences, and permitting duration. Those are not cost adjustments. They are schedule and risk adjustments, and they belong in the risk register and the general-conditions duration, not in a multiplier.

3. Size.

Cost per square foot does not scale linearly. Larger buildings generally cost less per square foot — mobilization, general conditions, and setup spread over more area — but the effect flattens, and above a certain size complexity starts adding it back. Small projects carry a genuine size penalty that is mostly general conditions and mobilization, not unit costs.

Two practical rules:

  • Do not adjust unit costs for size. A cubic yard of footing concrete does not know how big the building is. Adjust the general conditions and the mobilization, which is where the size effect actually lives.
  • Adjust element quantities, not element rates. A bigger building has a lower ratio of exterior wall to floor area, which is a quantity effect that a UniFormat estimate (§C.2) captures automatically and a $/SF estimate hides.

C.11.4 A worked normalization

You are bidding a 96,000 SF outpatient building in a different metro. Your best data is Northgate: 132,000 SF, three years old, footings at an actual $385.48/CY including a documented cold-weather event.

   Step 1 — clean the number.
     Strip the one-time cold-weather event noted in the diagnosis field.
     Cleaned base rate:                                    $352.00 / CY

   Step 2 — time. Index up 14.2% over three years.
     $352.00 × 1.142                                     = $401.98 / CY

   Step 3 — location. Target market carpenter burdened rate is 8% lower;
     ready-mix is 6% higher. Labor is ~20% of this unit cost, material ~73%.
     Labor portion:     $401.98 × 0.20 × 0.92            =  $73.96
     Material portion:  $401.98 × 0.73 × 1.06            = $311.05
     Equipment portion: $401.98 × 0.07 × 1.00            =  $28.14
     Adjusted                                             = $413.15 / CY

   Step 4 — size. NO adjustment to the unit cost.
     Instead, re-run general conditions against the new duration and
     the new staffing plan, and re-run mobilization.

   Carry:  $413 / CY, basis documented.

Now write down the basis, because the number is worthless without it: "Footing concrete placed and finished, $413/CY. Basis: Kestrel historical actual, Northgate Outpatient Pavilion, cost code 03-3100, 1,240 CY, cleaned of a documented cold-weather event; escalated 14.2% by published cost index over 3 years; adjusted for target-market wages (−8% labor) and ready-mix (+6% material). Assumes day shift, single crew, clear access, no trade stacking, gang forms on repeat footings."

That paragraph is worth more than the number, because it converts a guess into a managed condition that a second person can check, argue with, and improve.

C.11.5 Where published data legitimately fits

None of this means published data is useless. It means it has a job, and the job is not "be your primary basis on work you self-perform."

Use published data for Do not use it for
Scopes you rarely touch and have no history on Your self-perform trades
A first-pass conceptual estimate before quantities exist A number you will sign
A sanity check on a number that surprised you A substitute for a quote in a live market
Establishing the structure of an assembly you have never priced Presenting a published figure as though it were company data
Location and time adjustment methodology Proving a disruption claim

And whichever you use, note in the basis of estimate which source, which edition, and which adjustments you applied. An estimate that cannot say where its numbers came from is not an estimate; it is a rumor with a dollar sign.


C.12 If you remember nothing else from this appendix

  1. The division tells you where to file it; the scope sheet tells you who bought it. Money falls off the edges of divisions, not out of their middles.
  2. UniFormat for conceptual, MasterFormat for detailed — and the translation between them is where scope gaps are born.
  3. Man-hours per unit is the stable measure. Production rates bundle crew size and shift length into a number that moves when nothing about the work changed.
  4. Adjustment factors price a decision; measured data proves one. Do not multiply them together and do not present them as entitlement.
  5. Apply waste exactly once, to the quantity, and never to labor.
  6. The wage is not the cost. Build the burden from class codes and current accounting rates, and remember that the same laborer costs different amounts in different crews.
  7. General conditions are a rate, not a quantity. Sort every line into time-dependent or one-time, divide by the duration, and you have the number that turns every schedule conversation into a cost conversation.
  8. Every number in this appendix is illustrative. The numbers that will make you money are the ones your own cost report generates — which is why §C.11 is the only section here you cannot get from anybody else.

Related: Appendix A — Construction Math Reference · Appendix D — Forms and Templates Library · Appendix H — Software and Tools Directory · Chapter 11 · Chapter 12 · Chapter 13 · Chapter 16 · Chapter 20 · Chapter 28