Chapter 14 — Quiz

21 questions. Every answer and explanation is hidden in a <details> block — commit to your answer before you open it. Scoring guide at the end.

All networks use the elapsed-time convention: ES = 0 for the first activity, EF = ES + Duration.


Multiple Choice (11)

1. The critical path through a network is best described as:

A. The activities the superintendent considers most important B. The chain of activities with zero total float — equivalently, the longest path through the network C. The activities with the highest dollar value D. The activities the owner has designated as milestones

Answer

B. The critical path is a calculated result. It is the longest path through the network, and its activities have zero total float (or the minimum float in the network, if a constraint has driven float negative). Nobody designates it; it emerges from durations and logic, and it moves when either changes.

2. In the forward pass, an activity with three predecessors takes its early start from:

A. The average of its predecessors' early finishes B. The smallest of its predecessors' early finishes C. The largest of its predecessors' early finishes D. The predecessor listed first in the logic

Answer

C — the largest. A merging activity must wait for its slowest predecessor. Taking anything other than the maximum produces a schedule that is optimistic in a way that is very hard to spot later.

3. In the backward pass, an activity with three successors takes its late finish from:

A. The largest of its successors' late starts B. The smallest of its successors' late starts C. The project completion date D. Its own early finish plus its float

Answer

B — the smallest. A bursting activity must finish in time for its most urgent successor. You cannot satisfy one successor and abandon another. Max going forward, min coming back.

4. Activity Q has ES 30, EF 42, LS 37, LF 49. Its total float is:

A. 5 B. 7 C. 12 D. 19

Answer

B — 7. TF = LS − ES = 37 − 30 = 7, and it must equal LF − EF = 49 − 42 = 7. Computing it both ways is a free error check; if the two disagree, you have made a mistake in one of the passes.

5. An activity has total float of 6 and free float of 0. Using all six days will:

A. Delay the project by six days B. Delay the project by no days, but push at least one successor's early start C. Have no effect on anything D. Create negative float on the critical path

Answer

B. Total float protects the project; free float protects your successor. Total float without free float is interfering float — spending it consumes a downstream party's room without moving the completion date. This is exactly how the Northgate steel procurement chain got emptied out.

6. Which of these is a hard logic relationship?

A. Frame Level 2 before Level 3 B. Level 3 rough-in follows Level 2 because the mechanical sub has one crew C. Place spread footings after excavating for them D. Start the curtain wall on the south elevation first

Answer

C. Only C is physics. A and D are preferences (soft logic) — you could reverse them without changing the building. B is resource logic — you could reverse it by hiring a second crew.

7. The single most dangerous constraint type in a CPM schedule is:

A. Start No Earlier Than B. Finish No Later Than C. Mandatory Start or Mandatory Finish D. As Late As Possible

Answer

C. Mandatory constraints override logic. The activity holds its date regardless of its predecessors, which means delay stops propagating at that point. The schedule can then report that a five-week delay had no impact on completion, and nothing in the output looks wrong.

8. A schedule of 340 activities in which 96 activities have no successor will show:

A. Accurate float, because open ends do not affect the calculation B. Artificially high total float on those activities, which will then be filtered out of critical reports C. Negative float throughout D. A shorter project duration than reality

Answer

B. With no successor, an activity's late finish defaults to the end of the project, giving it enormous float. Those activities then disappear from every float-filtered report until one of them stops the job.

9. A negative lag (a lead, such as FS−10) should be:

A. Used freely to model overlapping trades B. Replaced with a start-to-start relationship plus a positive lag C. Used only on the critical path D. Converted to a mandatory constraint

Answer

B. A FS−10 is a badly written SS relationship. It behaves unpredictably when the predecessor's duration changes and is very hard to explain to a third party. If two activities overlap, model the overlap with SS and a lag — that is what SS exists for.

10. Northgate's daily exposure to slipping substantial completion is $10,650 per calendar day. That figure is composed of:

A. Liquidated damages only B. Extended general conditions only C. $5,150 of extended general conditions plus $5,500 of liquidated damages D. The CM fee prorated across the contract time

Answer

C. $5,150/CD of extended general conditions (from a $2,900,000 general-conditions budget over 565 calendar days) plus $5,500/CD of liquidated damages. Both accrue on calendar days, which is why every duration in a schedule must be labeled WD or CD.

11. The cash-flow S-curve on a construction project takes its shape because:

A. Owners prefer to pay slowly at first B. Few trades are on site at the beginning and the end, and many overlap in the middle C. Retention is held at 10 percent until the job is half complete D. Schedules are always cost-loaded evenly

Answer

B. The curve is essentially the accumulation of the manpower curve weighted by the value each trade installs. A cash-flow curve that is a straight line means somebody divided the contract sum by the number of months instead of loading the schedule.


True / False (5) — give a one-line justification for each

12. Free float is always less than or equal to total float.

Answer

True. Free float is limited by the earliest successor's early start; total float is limited by the project finish, which is never earlier. FF can equal TF, but it can never exceed it.

13. If you shorten an activity on the critical path by five days, the project always gets five days shorter.

Answer

False. It gets shorter only until a parallel path takes over. The Cottonwood Creek drill in §14.6.10 shows the knee exactly: shortening girder fabrication buys four days and then buys nothing, because the west abutment chain governs the merge. Re-run the network before you buy acceleration.

14. An owner's acceptance of your baseline schedule transfers responsibility for the sequence and the completion date to the owner.

Answer

False. Standard industry contract language generally reserves means, methods, techniques, sequences, and procedures to the contractor. Acceptance is a review for conformance with the specified requirements; it does not warrant that the sequence works or relieve you of the obligation to finish on time. It is still enormously valuable to you, because it fixes the agreed starting point for every future delay analysis.

15. Weather contingency belongs in the schedule as its own activity so that everyone can see it.

Answer

False. Weather belongs in the calendar, where it automatically makes a January exterior activity longer than the same activity in July. A "weather" bar in the middle of a network is the first thing consumed and the last thing anybody admits was consumed.

16. A project with two critical paths requires you to accelerate both to gain a single day.

Answer

True. Shorten one and the other still governs the completion date. This is the first question to ask of any acceleration proposal: how many critical paths are there, and does this proposal shorten all of them?


Short Answer (3)

17. Explain, in three sentences, why a duration and a cost come from the same two numbers, and name the two numbers.

Answer

The two numbers are quantity and production rate. Duration = quantity ÷ (production rate × number of crews); labor cost = (quantity ÷ production rate) × crew size × hours × wage rate. Change the production rate and both the schedule and the estimate move together, which is why an estimator and a scheduler who disagree about a production rate are having the same argument twice — and why the schedule and the budget are one conversation, not two.

18. A schedule reports 40 work days of float on its driving path. Name four defects that could make that number false, and say which one is silent — producing no visible warning of any kind.

Answer

(1) A constraint on the finish milestone set later than the contract date; (2) open ends — activities with no successor; (3) soft logic modeling work as parallel that must actually interleave; (4) durations padded at the activity level, so the same contingency is counted twice. The constraint is the silent one — it changes every float number in the schedule and produces no flag, no red bar, and no exception report. That is why the constraint count is the first check, not the last.

19. State the "critical path test" and explain what it proves.

Answer

Take a copy of the file, add a large duration (say 100 days) to one activity on the computed critical path, and recalculate. The project finish should move by exactly 100 days. If it moves less, something downstream — a constraint, a calendar, a mandatory date — is absorbing delay, and the schedule cannot compute a true critical path. Repeat on an activity with, say, 12 days of float: the finish should move exactly 88 days. If it does not, the float numbers are wrong.


Applied Scenarios (2)

20. Run this six-activity network completely. Give ES, EF, LS, LF, total float, and free float for every activity; state the project duration and the critical path.

ID Duration (WD) Predecessors
A 4
B 6 A
C 9 A
D 5 B
E 3 C
F 7 D, E
Answer

Forward pass: A 0→4. B 4→10. C 4→13. D 10→15. E 13→16. F starts at max(D 15, E 16) = 16 → 23. Project duration = 23 work days.

Backward pass (LF of F = 23): F 16→23. D LF = 16, LS = 11. E LF = 16, LS = 13. B LF = LS(D) = 11, LS = 5. C LF = LS(E) = 13, LS = 4. A LF = min(LS(B) 5, LS(C) 4) = 4, LS = 0. ✓ (A's LS returns to 0.)

ID Dur ES EF LS LF TF FF
A 4 0 4 0 4 0 0
B 6 4 10 5 11 1 0
C 9 4 13 4 13 0 0
D 5 10 15 11 16 1 1
E 3 13 16 13 16 0 0
F 7 16 23 16 23 0 0

Critical path: A → C → E → F = 4 + 9 + 3 + 7 = 23 ✓

Note B and D: both carry one day of total float, but only D has free float. If B slips one day, the project is fine — but D's early start moves and D's free float disappears. One day of float on that chain, shared between two activities.

21. Your job carries $4,300 per calendar day of combined extended general conditions and liquidated damages, and runs on a five-day calendar. A critical activity can be shortened by 7 work days by adding a second crew, at a cost of $22,000. A parallel path currently carries 4 work days of total float.

(a) How many work days will the acceleration actually buy the project? (b) What is that worth in dollars? (c) Should you do it, and what would you do next?

Answer

(a) Four work days. Once you have compressed the critical path by 4 days, the parallel path — which had 4 days of float — becomes critical too and governs the completion date. The remaining 3 days of compression buy nothing on their own.

(b) 4 WD × 7/5 = 5.6 calendar days. 5.6 × $4,300 = $24,080.

(c) Marginally yes — $24,080 of benefit against $22,000 of cost is a thin $2,080 margin, and it assumes the acceleration performs exactly as priced. What you do next is more important than the yes/no: find out what it would cost to compress the parallel path as well. If the two together can be bought for a reasonable number, you may be able to convert a 4-day gain into a 7-day gain and change the economics entirely. If the parallel path cannot be compressed at all, decline or renegotiate, because you are being asked to pay for seven days and receive four.


Scoring Guide

Score What it means
19–21 correct (90%+) You can run a CPM by hand and read someone else's schedule critically. Move on to Chapter 15
15–18 (70–89%) Ready to proceed. Re-read §14.6.5 (the four floats) and §14.7.3 (constraints) before you build the Willow Street schedule
11–14 (50–69%) Re-do the 📋 Try it drill in §14.6.10 with a pencil, then re-take this quiz. Do not skip the free-float column
10 or fewer Re-read §14.6 from the top and work the additional networks in Appendix B. This chapter is the foundation for Chapters 29, 30, and 33; do not move past it

Questions 20 and 21 are worth double. If you got everything else right and missed those two, you understand the vocabulary but not the calculation — and the calculation is the part that pays.