Chapter 19 Quiz — Subcontractor Management

Twenty-two questions. Answer before you open the <details>. Scoring guide at the end.


Multiple Choice

1. On the Northgate project, subcontracts total $32,800,000 against a $40,000,000 direct cost of work. What percentage of the work is subcontracted, and what is the typical range for a commercial building project?

A. 62 percent; typical range 50–70 percent B. 82 percent; typical range 80–90 percent C. 82 percent; typical range 40–60 percent D. 95 percent; typical range 90–100 percent

Answer

B. $32,800,000 ÷ $40,000,000 = 82 percent. The chapter gives 80–90 percent as the typical range for commercial building work, with the honest caveat that it varies widely by market, project type, and how much the general contractor self-performs.


2. Which is the most useful source of leverage over a subcontractor?

A. The subcontract's termination-for-cause clause B. The schedule and the coordination process C. Making their work easy and profitable — clean released areas, access, information, decisions D. Paying them correctly and on time

Answer

C. The chapter ranks the four sources in order: (1) make their work easy and profitable, (2) pay correctly and on time, (3) the schedule and coordination process, (4) the enforcement clauses. Number one is first because it is immediate, compounding, and almost entirely within your control — and because it directly changes the subcontractor's own economics on your job.


3. A general contractor who reaches for the subcontract's enforcement clauses first has usually:

A. Been unusually decisive B. Already failed at the first three sources of leverage C. Protected the project's schedule D. Complied with the notice requirements

Answer

B. Enforcement is slow, expensive, and it does not put a worker on your floor tomorrow. When a troubled job's file is thick with cure notices, the chapter's advice is to go look at the RFI log, the released-area log, and the payment history first — the general contractor's own fingerprints are on the cause about two-thirds of the time.


4. Why is manpower described as a leading indicator?

A. Because it is reported first in the daily report B. Because construction production over a period of weeks is roughly proportional to labor hours applied, so a crew shortfall today shows up as a progress shortfall weeks later C. Because subcontractors always overstate their headcount D. Because it is the only number the superintendent controls

Answer

B. Progress this month was purchased by hours worked last month. A shortfall is visible in the daily report weeks before it appears in the percent-complete column — which is precisely the window in which correction is still cheap. The second mechanism matters too: manpower is self-reported in advance, so a firm that commits to a curve and does not staff to it has revealed a commitment problem, not just a schedule problem.


5. Your four-week rolling manpower average for a critical-path trade is 79 percent of the committed curve. Under the chapter's thresholds, what is the correct action?

A. Green — note it and move on B. Yellow — field conversation with the foreman C. Orange — written notice of the schedule requirement and a demand for a recovery plan D. Red — terminate for cause

Answer

C. 75–84 percent is orange: a written notice of the schedule requirement with a recovery plan requested, including dates. Note that "terminate for cause" is not even the red action — red is a formal notice per the subcontract plus evaluation of supplementation. Termination sits at rung 6, after a cure period has run.


6. Which of these will most reliably destroy a backcharge in a dispute?

A. Charging 10 percent overhead B. Using a supplemental crew from another subcontractor rather than your own forces C. Starting the supplemental work on a verbal instruction without a written cure notice D. Waiting until the following month to notify the subcontractor of the amount

Answer

C. The cure notice and the opportunity to cure are almost always conditions precedent to the supplementation remedy. Without them your deduction is a naked withholding that the subcontractor can dispute and will probably win — and they may have a claim against you for interfering with their work. (D is also damaging and will cost you money, but C is usually fatal.)


7. A general contractor is ordinarily which employer under OSHA's multi-employer worksite framework?

A. The creating employer B. The exposing employer C. The correcting employer D. The controlling employer

Answer

D. The controlling employer — the one with general supervisory authority over the site, including the authority to correct hazards or require others to correct them. The standard applied is reasonable care, generally understood as less than what is required of the employer whose own people are exposed, but decidedly not zero: periodic inspections appropriate to the hazards, an effective correction system, and actual enforcement. An employer can occupy more than one role at once.


8. Trade stacking costs production through five channels. Which of the following is not one of them as the chapter presents it?

A. Physical interference B. Dilution of supervision C. Higher wage rates D. Rework and damage

Answer

C. The five channels are physical interference, waiting and restarting, dilution of supervision, extra material handling, and rework and damage. Wage rates do not change because a space is crowded; the hours required to do the same work go up. (Premium time for acceleration is a separate cost, and a separate line.)


9. What makes a "measured mile" analysis more defensible than a productivity-loss figure quoted from a published table?

A. It produces a larger number B. It is derived from this project's own records, comparing a genuinely unimpacted period to an impacted one C. Courts require it D. It does not require the other side to agree on causation

Answer

B. The measured mile compares the same crew doing the same kind of work with and without the impact, on this job, from the records. Its weakness is comparability — different wall heights, a different crew, a different position on the learning curve, or different weather will contaminate it, and a competent opposing consultant will say so quickly. It is a good method used carefully, not a magic one.


10. Kestrel holds subcontractor money an extra 30 days, earning roughly $13,800 in float. The chapter argues this is a bad trade primarily because:

A. It violates federal law B. The accounting is difficult C. The reputational cost is priced into every future bid, and one lost crew can cost six figures in schedule D. Subcontractors will file liens immediately

Answer

C. The float earned is small and certain; the cost is large and diffuse — a point or two added to future bids, and the risk that a foreman moves his crew to a general contractor who pays on time. The chapter's illustration puts a 15-working-day interior progress loss at roughly 21 calendar days, or about $223,650 at $10,650 per calendar day. (Slow payment may also run afoul of prompt-payment statutes, which vary by jurisdiction — but the business case alone is decisive.)


11. In the Try-it drill, two trades were significantly behind on manpower — Halcyon Electric and Sightline's board crew. Why is only one of them the correct target of a written notice?

A. Sightline's subcontract is smaller B. Sightline's shortfall is a downstream symptom of Halcyon's, because board cannot be hung until walls close and walls cannot close until electrical rough-in is inspected C. Sightline is self-performed D. Board work is not on the critical path

Answer

B. Reading the dependency, not just the variance, is the whole skill. Sightline's framing crew was running at 101 percent of plan in the same period, which is strong evidence the company is willing and able to staff the job — they simply had nowhere to put the board crew. A letter to Sightline would have been answered with a letter that made Kestrel look like it did not understand its own schedule.


12. What does a long punch list at the end of a project usually indicate?

A. A thorough closeout process B. That the mockup and first-work-inspection mechanisms failed earlier in the job C. That the architect is difficult D. That retention was set too low

Answer

B. A punch list is evidence the first two quality mechanisms — mockups and benchmark installations, and first-work inspections — did not do their job. It is a bill for the inspections nobody performed in month eleven, and it arrives at the most expensive possible moment.


True / False

For each, state true or false and give a one-line justification.

13. A performance bond protects the general contractor's schedule as well as its money.

Answer

False. A performance bond is a money instrument, not a schedule instrument. In Case Study 2 the bond substantially covered the excess cost of completion, and the school still opened 38 days late — costing $91,200 in liquidated damages and $117,800 in extended general conditions that the bond did not touch. Expect 30–60 days from default declaration to productive replacement work, plus a relearning curve.

14. A subcontractor delayed by another subcontractor will normally pursue the offending subcontractor directly.

Answer

False. They come to you — because you hold their contract, you wrote the schedule, and you have the money. Whether you can push that cost down to the responsible trade depends on your claims-against-other-subcontractors provision and on whether your daily reports and handoff log identify which trade caused what.

15. Escalating to the owner of a subcontracting firm, over the head of their project manager, is inherently an aggressive act.

Answer

False. The manpower decision is usually made above the project manager's level, so the manpower conversation belongs there too. What makes it aggressive or not is the execution: tell their project manager you are making the call before you make it, lead with facts rather than accusations, state that you have done your own job first, and bring an offer.

16. A general contractor's coordination obligation guarantees that no subcontractor will be delayed by another.

Answer

False. The obligation is generally read as a duty to coordinate reasonably and in good faith and to provide reasonable access — not a warranty against all interference. But a general contractor who actively interferes, fails to sequence at all, or repeatedly releases and un-releases areas is in materially different territory than one who ran a disciplined process and still had a bad month. The specific language and its interpretation vary by contract form and jurisdiction.

17. Requiring a subcontractor to work uncompensated Saturdays to recover a delay the owner caused is a legitimate use of the subcontract's recovery obligation.

Answer

False. That is constructive acceleration. The recovery obligation applies to delays the subcontractor caused. If the delay is yours or the owner's and you want it recovered faster, that is a change and it costs money. The test is a single question asked before you direct anything: who caused the delay I am asking them to absorb?

18. A no-damage-for-delay clause reliably prevents a subcontractor from recovering money for delay in any jurisdiction.

Answer

False. Enforceability is highly jurisdiction-dependent, and courts in a number of states recognize exceptions — commonly for active interference, bad faith, delays not contemplated by the parties, or abandonment. Treating such a clause as a force field is how general contractors eventually meet a judge who disagrees. Read your clause and your state's law, and ask counsel before you rely on it.


Short Answer

19. Explain the threshold concept of this chapter in three sentences, and describe one concrete behavior that changes once a manager crosses it.

Answer

You do not manage the work; you manage the people who contracted to do the work. Your leverage is the subcontract, the schedule, and the coordination — not authority, because a subcontractor's crews answer to their own company's economics and not to your instructions. A general contractor who tries to command instead of enabling and holding accountable will fail at both.

Concrete behavior change: faced with a short-handed trade, a manager who has crossed the threshold first audits their own performance — released areas, open RFIs, payment history — and looks for a way to make the work easier or more profitable, before writing anything. A manager who has not crossed it sends an email with the schedule attached and the words "per the subcontract" in it, and is surprised when nothing happens.

20. Name the six rungs of the escalation ladder and explain specifically what is lost by skipping directly from a field conversation to supplementation.

Answer

(1) Field conversation with the foreman. (2) Conversation with their project manager and, where warranted, the firm's owner, confirmed by email. (3) Written notice of the schedule requirement plus a demand for a recovery plan. (4) Recovery plan accepted or rejected in writing, with dates. (5) Formal cure notice per the subcontract, copying the surety if bonded. (6) Supplementation, backcharge, or termination for cause.

Skipping to supplementation forfeits the remedy itself. The supplementation and backcharge rights in nearly every subcontract are conditioned on written notice and a genuine opportunity to cure; without them, your deduction is a withholding you cannot substantiate, the subcontractor may have a claim against you for interference, and you have handed them a grievance they will use to color every other disputed item for the rest of the job.

21. A subcontractor's estimator tells you they carry a 3 percent "aggravation allowance" on some general contractors and none on others. Explain where that allowance lives on a bid form, why you cannot negotiate it out at buyout, and what it implies about the return on running a disciplined coordination process.

Answer

It lives nowhere identifiable — buried in the labor productivity factor, the general-conditions line, the contingency, or the fee. You cannot negotiate it out at buyout because it was baked in before the number was written; the only way to remove it is to have earned a different reputation over years of behavior. Three percent of Cardinal Mechanical's $6,400,000 Northgate subcontract is $192,000 on one trade on one job, which is the return on releasing areas cleanly, answering RFIs promptly, paying inside terms, deciding quickly, and running a real coordination meeting — none of which appears on any cost report, and all of which appears in the bids you receive.


Applied Scenario

22. You are the project manager on a $31,000,000 laboratory building. It is month nine. Your mechanical subcontractor holds a $7,200,000 subcontract, is on the critical path, and has run at 71 percent of its committed manpower curve for five straight weeks. In the same five weeks your team has: released two of the four promised areas late (by 9 and 14 days), left three of their RFIs open past the response date, and paid two applications 18 days late because of an internal approval backlog.

Their project manager has stopped returning calls within a day. Your superintendent wants to send a cure notice this week.

Write your plan for the next ten business days. Be specific about sequence, who does what, and what goes in writing.

Model answer

Do not send the cure notice. It would be answered with a letter listing your late releases, your open RFIs, and your late payments, and it would convert a recoverable schedule problem into a claim that runs against you.

Days 1–2 — fix your own side, in writing. Close the three overdue RFIs or issue interim directions so their detailing can proceed. Get the two late applications paid and instruct accounting in writing that this subcontractor's applications are processed on a fixed date, no exceptions. Publish a released-area log showing exactly what is available now and what is coming, by date, and hold those dates.

Day 2 — the field conversation (rung 1). Superintendent walks the areas with their general foreman. Ask what they need. Note it in the daily report.

Day 3 — the phone call (rung 2). You call their project manager. Tell him what you have fixed, ask what else blocks him, and ask what it would take to get to the committed curve. Confirm the conversation by email the same day — facts, commitments, dates. This is your contemporaneous record.

Days 4–5 — escalate to the firm's owner, having told their PM first. Same structure: fact, your own performance stated affirmatively, consequence as information, a question, and an offer (accelerated payment terms; two additional clean released zones).

Days 5–10 — measure. Roll up crew counts daily. Update the manpower table. Compute the projected completion at the observed rate and check it against the CPM total float so you know whether this actually reaches substantial completion.

In parallel, day 1 — protect quietly. Check the waiver matrix for preliminary notices from their tier. Check whether the subcontract is bonded and locate the bond. Do not send anything to the surety yet; there is no default and the cause is at least partly yours.

If the curve has not moved by day 10: rung 3 — a written notice of the schedule requirement with a recovery plan due in five business days, stating your now-corrected performance with references, and quantifying the projected slip in weeks and dollars.


Scoring Guide

Score Reading
20–22 Strong. You can run a trade coordination process and you know when — and when not — to write a letter.
17–19 Solid. Re-read §19.5 (the ladder and the thresholds) and §19.6.4 (interference and the duty to coordinate).
14–16 Adequate. Work the Try-it drill in §19.5.7 again from scratch, and re-read §19.2 until the leverage order is automatic.
Below 14 Re-read the chapter, then work Case Study 2 and Exercise C5. The pattern you are missing is usually the difference between a variance and a dependency.

70 percent (16 of 22) or better means you are ready to proceed to Chapter 20.