Chapter 22 — Quiz
Twenty-one questions. Answer each one before opening the explanation. A scoring guide is at the end.
Multiple Choice
Q1. Formwork on a cast-in-place concrete building typically represents what share of the in-place cost of the concrete?
A. 5 to 10 percent B. 15 to 25 percent C. 40 to 60 percent D. 75 to 90 percent
Answer
C. Formwork commonly runs 40 to 60 percent of the in-place cost of concrete — more than the concrete itself and usually more than the reinforcing. This is why form-system selection and cycle time drive both the cost report and the schedule on a concrete frame, and why "cheaper forms" that increase carpenter hours are usually more expensive.
Q2. Which single variable has the largest effect on the lateral pressure a wall form must resist?
A. The height of the wall B. The rate of placement C. The strength class of the concrete D. The spacing of the reinforcing
Answer
B. Wall height sets the ceiling (full liquid head at roughly 150 psf per foot of fluid depth), but the actual design pressure depends on how much of the pour is still fluid when you reach the top — which is governed by placement rate, modified by temperature, admixtures, mix, and consolidation. Two crews placing the same wall at different rates impose very different loads on the same form.
Q3. A 12-foot wall is placed so fast that the entire depth is still fluid. At 150 pcf, the lateral pressure at the base is approximately:
A. 900 psf B. 1,200 psf C. 1,800 psf D. 2,400 psf
Answer
C. 12 ft × 150 pcf = 1,800 psf. This is straightforward hydrostatics, not a code provision, and it is the number your form must be able to resist if the whole depth is fluid at once.
Q4. Which cylinder should be broken to decide whether shores may be removed from an elevated slab?
A. A lab-cured cylinder at 7 days B. A field-cured cylinder, cured alongside the member C. Either — the difference is administrative D. A lab-cured cylinder at 28 days
Answer
B. A lab-cured cylinder tells you about the mix under controlled conditions and is the basis for acceptance. A field-cured cylinder — or an accepted maturity method — tells you about this member's actual temperature and moisture history, which is the question a stripping decision asks. Using a lab cylinder to make a field decision overstates the strength of a slab that spent four cold nights under a tarp.
Q5. In reshoring, the slab:
A. Never carries its own weight alone B. Is allowed to deflect under its own dead load before the shores are replaced C. Is jacked back up to its original elevation D. Carries no construction load at all
Answer
B. Reshores go in after the slab has deflected under its own weight, snugged rather than jacked. The slab therefore carries its own dead load permanently, and the reshores carry only the additional construction loads that arrive later. Option A describes backshoring, where the shores are replaced in a sequence that never lets the slab deflect on its own.
Q6. Under the U.S. construction standard for excavations, a protective system is generally required at a depth of:
A. 3 feet or greater B. 4 feet or greater C. 5 feet or greater D. 8 feet or greater
Answer
C. Five feet or greater, unless the excavation is entirely in stable rock — and a competent person still evaluates whether protection is needed below that depth. Separately, excavations 20 feet or greater require a protective system designed by a registered professional engineer, and means of egress are required in trenches 4 feet deep or greater within 25 feet of lateral travel.
Q7. A supported scaffold must be restrained from tipping when its height exceeds:
A. Two times the minimum base width B. Three times the minimum base width C. Four times the minimum base width D. Six times the minimum base width
Answer
C. Beyond a height-to-base ratio of four to one, guys, ties, or braces are required, installed on a defined vertical and horizontal pattern per the manufacturer or a qualified person. This is one of the handful of scaffold numbers worth carrying in your head, because it is easy to check by eye and frequently violated on narrow towers.
Q8. The load classes for scaffold platforms are commonly:
A. 10, 20, and 30 psf B. 25, 50, and 75 psf (light, medium, heavy duty) C. 50, 100, and 150 psf D. There are no standard classes; each scaffold is engineered
Answer
B. Light duty 25 psf, medium duty 50 psf, heavy duty 75 psf. A masonry scaffold carrying block and mortar is a heavy-duty application, and putting block on a light-duty frame because it happened to be the scaffold already standing is a real and common failure.
Q9. Which dewatering method is most appropriate for a deep excavation in fine sands and silts where wellpoints and deep wells both underperform?
A. Open sump pumping B. An eductor (ejector) system C. A single deep well D. Sheet piling alone
Answer
B. Eductor systems use high-pressure water to create a vacuum at each well, delivering lower flow at higher head — which is exactly what low-permeability soils require. Sump pumping in fine sand pulls fines and destabilizes the base; a single deep well cannot draw water fast enough from silt; and sheet piling is a cutoff, not a dewatering method (though it may be the right answer for a different reason — protecting the neighbors from drawdown settlement).
Q10. A dewatering system costs $300,000 over 150 days, of which $150,000 is fixed. A one-week delay in reaching the shut-off criterion costs approximately:
A. $2,000 B. $7,000 C. $14,000 D. $21,000
Answer
B. The time-related cost is ($300,000 − $150,000) ÷ 150 = $1,000 per calendar day, so a week is about $7,000. Using the $2,000/day average would have doubled the answer, because the average includes mobilization and installation that a delay does not re-buy. Getting this distinction wrong in front of an owner damages your credibility on everything else you present.
Q11. Lowering the groundwater table beneath an adjacent building can cause settlement because:
A. The water was physically holding the building up B. Removing pore water increases effective stress in the soil, which consolidates it C. The pumping vibrates the soil D. The excavation removes lateral support
Answer
B. Below the water table, pore water pressure carries part of the load. Draw the water down and the effective stress on the soil skeleton increases, consolidating it — and the settlement zone extends well past your property line. Option D is a real and separate mechanism (excavation removing lateral support), which is why monitoring covers both. Controls: monitoring wells, settlement points with action thresholds, recharge wells, and — before anything else — the pre-construction condition survey.
Q12. Before steel erection begins on a footing or pier, the controlling contractor must provide the steel erector with:
A. A verbal confirmation from the superintendent B. Written notification that the concrete has attained sufficient strength C. A copy of the mix design D. Nothing — the erector determines this independently
Answer
B. The U.S. steel erection standard requires written notification from the controlling contractor that the concrete in footings, piers, and walls has attained adequate strength before erection begins. In practice that means somebody on your team turns cylinder breaks into a piece of paper. Related requirements in the same standard: a minimum of four anchor rods per column, and no field repair, replacement, or modification of anchor rods without the approval of the structural engineer of record.
True / False
Give a one-line justification for each answer.
Q13. A scaffold that was correctly erected nine days ago and has not been damaged does not need to be inspected again before use.
Answer
False. A competent person must inspect the scaffold and its components for visible defects before each work shift and after any occurrence that could affect structural integrity. Nine days of use by multiple trades is precisely the condition in which planks get moved, ties get removed, and material gets stacked past the load class.
Q14. "Temporary" means a structure can be designed with a lower factor of safety because it will not be in service long.
Answer
False. A temporary structure carries its full design load every day it stands, and it has less margin than a permanent one — no long-term redundancy from finishes and partitions, no second load path, and no time to notice distress before a sudden failure. Short service life does not buy you margin; it removes the warning.
Q15. A trench shield (trench box) holds the trench walls back and prevents a cave-in.
Answer
False. A shield protects workers inside it if the walls collapse; it does not support the soil. Shoring systems support the soil. Both are legitimate protective systems, but confusing them leads people to make wrong decisions about spoil setback, adjacent loads, and what happens outside the box.
Q16. An engineer of record's "approved" stamp on a delegated shoring design transfers responsibility for the shoring to the engineer of record.
Answer
False. The engineer of record's review of a delegated design is generally limited to conformance with the design intent of the permanent structure — not verification of the specialty engineer's calculations. Responsibility for the temporary structure remains with the party whose means and methods it is. Read the actual language in your specification and your contract, and note that the rules for delegated design vary by jurisdiction.
Q17. Direct-fired temporary heaters are a good choice for drying out a building before flooring installation.
Answer
False, on two counts. Direct-fired heaters put combustion products — including a great deal of water vapor — into the space, so you are humidifying a building you are trying to dry. They are also a carbon monoxide hazard in an enclosed space. Indirect-fired heaters vent combustion products outside and deliver only clean warm air.
Q18. Reshores may be tightened firmly to take as much load off the young slab as possible.
Answer
False. Reshores are snugged, not jacked. Over-tightening lifts the slab above and loads the slab below in a direction and magnitude nobody designed for. The correct amount of tightening is part of the engineered scheme, and the crew has to be told what it is.
Short Answer
Q19. Explain, in three or four sentences, why the multi-floor progressive collapses that have historically killed the most people in cast-in-place construction begin as a local overload.
Answer
In a shored structure, floors are coupled rather than independent: a shore stack ties three or four young slabs into one load-sharing system, distributing construction loads according to relative stiffness. If one floor in that stack is overloaded and fails, its load does not disappear — it is delivered instantly and dynamically to the floor below, which is younger, weaker, and already carrying its share. That floor fails and delivers two floors' worth of load to the next one down. Coupling is what turns a local overload into a building, which is why the reshoring scheme is an engineered design with a drawing, not a field judgment.
Q20. State the modification-control rule for temporary structures, and explain why "train the crews to be careful" is not an adequate substitute for it.
Answer
The rule: no temporary structure may be altered, moved, cut, loaded beyond its rating, or partially dismantled by anyone other than the erecting contractor's competent person; a trade needing a modification requests it; every modification triggers re-inspection and re-tagging before reoccupancy; any modification discovered after the fact stops work on that structure until the competent person clears it.
Why training is not a substitute: the failure mode is not carelessness, it is unawareness of category. Halcyon's electricians did not decide to modify a scaffold and do it badly. They moved a board, and they had no idea they had touched a structure. You cannot train people to be careful about a hazard they do not know they created. The rule works because it changes the situation — it makes the structure something you have to ask about — rather than trying to change the person.
Q21. Name the four release decisions in this chapter that require a signature rather than an opinion, and say who signs each.
Answer
- Shore and reshore release — the concrete superintendent (one named person), on a written strength result from field-cured cylinders meeting the specified criterion.
- Brace release for steel, precast, or masonry — the erection or bracing engineer, in writing, by area.
- Excavation support removal — the shoring engineer, in writing, in stages.
- Dewatering shut-off — against the structural engineer's uplift criterion, in writing.
The common structure: a stated criterion, a measurement, and one named person whose signature is on it. Every one of these is a place where schedule pressure and physical risk push in opposite directions on the same step, which is exactly why the decision is removed from the person feeling the pressure.
Applied Scenario
Q22. It is Friday at 4:15 p.m. Your concrete foreman reports the 3-day break on the level-3 deck at 3,290 psi. The specification requires 75 percent of a 4,500 psi design strength before shore removal. The forms are needed Monday for the level-4 pour, which is on the critical path at a combined exposure of $10,650 per calendar day. The testing laboratory does not work weekends under the current agreement. The foreman proposes stripping Saturday morning "since it'll be stronger by then anyway."
Write your response as a set of decisions, with reasons. Address: the criterion, the proposal, the laboratory constraint, the schedule consequence, and what you change so this does not recur.
Answer
The criterion. 75% × 4,500 = 3,375 psi. The break was 3,290 psi. It does not meet the criterion. Nothing is stripped. The number is the number, and the gap being small is irrelevant — a criterion you set aside when it is close is not a criterion.
The proposal. "It'll be stronger by then" is a prediction, not a measurement, and the whole point of the criterion is that the release runs on measurement. Concrete does gain strength over a weekend, which is why the right answer is to measure it Saturday, not to assume it.
The laboratory constraint. This is the actual problem and it is solvable this afternoon. Call the lab and buy a Saturday morning break — typically a few hundred dollars as an additional service. If the concrete has reached 3,375 psi Saturday morning, you strip Saturday and lose nothing.
The schedule consequence if the lab cannot come. You strip Monday morning and lose most of a day on the critical path — roughly $10,650. Say it out loud, in the schedule update, so the number is visible. Do not recover it by shortening a different cure.
What changes: 1. Amend the testing agreement to include weekend and holiday breaks at a stated rate, for the duration of the frame. It costs a few thousand dollars and buys back days at $10,650 each. 2. Look at the mix. If the mix cannot reliably make 3,375 psi at the cycle age and the temperatures you are actually getting, that is a preconstruction decision showing up in the field, and it is fixable now with an early-strength mix for the remaining floors. 3. Put the cylinder break on the schedule as an activity with a duration and a responsible name, so nobody discovers on a Friday afternoon that the lab is closed.
And the underlying point: the foreman is not wrong to want the panels. He is being asked to hit a cycle that was not fully resourced, and the honest response includes fixing the resourcing, not just saying no.
Scoring Guide
| Score | Reading |
|---|---|
| 19–22 correct (86%+) | You can run this. Go build the Willow Street temporary-structures plan. |
| 15–18 correct (70–85%) | Solid. Re-read §22.2.5 and §22.2.6 — stripping criteria and reshoring are where the misses cluster, and they are the two that hurt people. |
| 11–14 correct (50–69%) | Re-read the chapter with the register in §22.9 in front of you, then redo Q13 through Q21. |
| 10 or fewer (under 50%) | Start with §22.1 and §22.2 and work the 📋 Try it cycle drill before continuing to Chapter 23. This material sits underneath the safety chapter, and the safety chapter assumes it. |
70 percent or better means you are ready to proceed. But note the special case: if you missed Q4, Q5, Q18, or Q21, go back regardless of your total. Those four are the ones that get people killed.