Chapter 8 — Quiz

Twenty questions. Answer before you open the <details> block; a retrieval attempt you get wrong teaches more than a correct answer you looked up. Scoring guide at the end.


Multiple Choice

1. Which section of a geotechnical report is the evidence, as opposed to the interpretation?

A. The recommendations B. The boring logs C. The project description D. The limitations paragraph

Answer

B — the boring logs. The recommendations are a generalized summary written for the structural engineer. The logs record what was actually encountered at each depth in each hole, including the SPT blow counts. At Northgate, log B-9 disclosed N-values of 4, 5, and 6 at footing elevation while the recommendations said medium-dense sand at 4,000 psf. Reading only the recommendations cost $59,200 and three calendar days.

2. You have 32,000 BCY of net export and a swell factor of 25%. How many loose cubic yards will you haul?

A. 25,600 LCY B. 32,000 LCY C. 40,000 LCY D. 44,000 LCY

Answer

C — 40,000 LCY. LCY = BCY × (1 + swell) = 32,000 × 1.25 = 40,000. Option A applies the factor backward, which is the classic direction error; B ignores swell entirely and is the mistake that under-prices a haul by about 25%.

3. An excavator has a 2.5 CY bucket, a 22-second cycle, a 0.85 fill factor, and works a 50-minute hour. What is its production in loose cubic yards per hour?

A. 205 LCY/hr B. 232 LCY/hr C. 290 LCY/hr D. 348 LCY/hr

Answer

C — 290 LCY/hr. (3,600 ÷ 22) × 2.5 × 0.85 × 0.833 = 163.6 × 2.5 × 0.85 × 0.833 = 290. Note that 232 (option B) is the same machine expressed in bank cubic yards per hour after dividing by the 1.25 swell factor — a correct number for a different question, and exactly the kind of unit confusion that produces wrong durations.

4. Truck cycle time is 55 minutes and load time is 2.5 minutes. How many trucks keep the excavator working continuously?

A. 13 B. 18 C. 22 D. 28

Answer

C — 22 trucks. Trucks required = cycle time ÷ load time = 55.0 ÷ 2.5 = 22. Running with only 13 does not save money — the hauling cost per yard-mile is roughly unchanged — but it stretches the duration from 16 work days to 27 and keeps the excavator, operator, foreman, and site on the clock the whole time.

5. A #7 reinforcing bar is approximately what diameter?

A. 1/2 inch B. 5/8 inch C. 7/8 inch D. 1 inch

Answer

C — 7/8 inch. The eighth-inch rule: the bar number is the diameter in eighths of an inch, so #7 = 7/8 inch, #4 = 1/2 inch, #8 = 1 inch. Above #8 the bars are sized by area and the mnemonic stops working.

6. Adding water to a concrete mix at the point of placement, beyond what the mix design allows, primarily causes:

A. Faster setting and higher early strength B. Lower strength and greater permeability from capillary voids C. Better long-term durability from more complete hydration D. Increased air entrainment

Answer

B. Hydration needs only a small amount of water; the excess makes the mix flowable but leaves behind an interconnected network of capillary voids as it departs. Voids are where strength isn't, and where chlorides and water get in later. The correct way to gain workability is a superplasticizer, not a hose.

7. On a cast-in-place concrete frame building, what most directly sets the frame's schedule?

A. The compressive strength of the concrete B. The rebar tonnage C. The form cycle time D. The ready-mix supplier's batching capacity

Answer

C — the form cycle time. Concrete arrives in a few hours; formwork is designed, set, stripped, flown, and reshored floor after floor. A cycle planned at 5 days and run at 8 adds 3 days per floor, and on a 12-floor building that is 36 work days — roughly 50 calendar days — with every following trade inheriting the slip.

8. Which excavation-support method protects workers but does not support the surrounding soil?

A. Soldier pile and lagging B. Trench box (shield) C. Secant pile wall D. Soil nailing

Answer

B — the trench box. A shield creates a protected space for people inside it; the soil outside can still move. That distinction matters when someone steps outside the box to make a connection, which is where a large share of trenching fatalities occur.

9. Under OSHA's excavation requirements, a protective system is generally required at what depth, absent stable rock?

A. 3 feet B. 4 feet C. 5 feet D. 8 feet

Answer

C — 5 feet. Below 5 feet, a competent person may still require protection based on conditions, and an excavation 20 feet or deeper requires a system designed by a registered professional engineer. The competent-person inspection is required daily, before each shift, and after any event — rain, vibration, a change in loading — that could alter conditions.

10. Compared with cast-in-place concrete, precast concrete's principal disadvantage for a project already behind on design is:

A. Poorer quality control B. Higher weather sensitivity at the site C. A long lead time from approved shop drawings to delivery D. Greater fireproofing cost

Answer

C. Precast erects fast at the site precisely because someone spent months making the pieces. Lead time from approved shop drawings to delivery commonly runs 10 to 20 weeks. When the constraint is design and procurement, a system whose advantage is field speed does not solve it.

11. A slab on grade is 33,000 SF at 5 inches. What is the neat concrete volume?

A. 458 CY B. 510 CY C. 550 CY D. 611 CY

Answer

B — 510 CY. 33,000 × (5 ÷ 12) = 13,750 CF; 13,750 ÷ 27 = 509.3 → 510 CY. This is Northgate's canonical slab quantity. Add a 5% waste factor and you order 536 CY, or 54 whole 10 CY loads.

12. In the Northgate steel delay, which party was contractually late?

A. Caldwell Structural, the engineer of record B. Ironbridge Steel, the fabricator and erector C. Kestrel, the construction manager D. Meridian Health System, the owner

Answer

C — Kestrel. The anchor-bolt and embed submittal sat 11 days in Kestrel's office against a 5-day allowance — 6 days of slip. Caldwell took exactly the 14 days its contract permitted and was not late at all. Those 6 days landed on a fixed mill rolling slot; the next opening was five weeks out, and after Ironbridge compressed fabrication by 12 days the net was +23 calendar days, moving erection start from August 4 to August 27.


True / False

For each, mark true or false and give a one-line justification.

13. A geotechnical report is a warranty of the subsurface conditions the contractor will encounter.

Answer

False. It is typically furnished as information. Many contracts allow reliance on factual data but not on interpretations and opinions, and many require the contractor to represent that it satisfied itself as to site conditions. What you may rely on is a contract question that varies by form, by owner, and by jurisdiction — read the article.

14. Reinforcement in a slab on grade prevents the slab from cracking.

Answer

False. Concrete shrinks as it cures and it will crack. Reinforcement controls crack width and keeps the pieces working together; control joints decide where the cracks go. Anyone who promises an uncracked slab is selling something.

15. Cutting a truss chord to run a duct is a coordination problem that the framing crew can solve in the field.

Answer

False. A truss is an engineered assembly with a stamped design; every member carries a calculated force. Cutting a chord is a structural failure, not a field fix. The remedy is an engineered repair detail from the truss designer — which is why duct routing belongs in coordination before the trusses are ordered.

16. Under a unit-price contract, the owner generally pays for quantity overruns at the bid unit price without a change order dispute.

Answer

True — that is the point of unit pricing. At Cottonwood Creek, extra drilled-shaft footage is simply measured and paid at $412.00/LF. But most such specifications carry a variation threshold, commonly around 25%, beyond which either party may seek an adjusted unit price, because the contractor's fixed costs no longer spread across the assumed quantity.

17. Once a post-tensioned slab has been stressed and the tails cut, the tendons are no longer a hazard.

Answer

False. The hazard changes but does not go away. A stressed tendon stores enormous energy, and coring, drilling, or saw cutting into one can release it explosively. Any penetration in a PT slab requires tendon location by as-built drawings and scanning, plus a written procedure — which belongs in your safety plan and subcontractor orientation, not only in a specification.

18. Mass timber's main field risk is fire during construction.

Answer

False — or at least, that is not the one that bites most projects. The dominant construction-phase risk is moisture. Exposed panels that sit in rain cup, check, stain, and can delaminate, and because the panel is often the exposed architectural finish, a water stain is a defect you cannot cover. Real mass timber projects run a written moisture management plan. Fire is real, but it is primarily a code and design question resolved before you break ground.


Short Answer

19. Explain, in three or four sentences, why a six-day delay in your own office turned into a twenty-three-day delay on Northgate.

Answer

Lead-time chains do not add — they snap. The six days of slip landed on a discrete, scheduled event: Ironbridge's mill rolling slot, which closed on a fixed date. Missing it did not cost six days; it cost the interval to the next opening, which was five weeks (35 CD). Ironbridge recovered 12 days by running shop overtime and resequencing, leaving a net of 35 − 12 = 23 calendar days — and note the six days are not in that sum, because they are its cause rather than a term in it, or $244,950 of exposure at $10,650 per calendar day. The management lesson is to back-schedule submittal approval dates from the fixed slot, not forward from today.

20. Name the three hold points in an earthwork-and-foundation sequence where an inspector or testing laboratory can stop your job, and say for each what you do two weeks ahead to keep it from becoming a delay.

Answer

(1) Subgrade bearing inspection by the geotechnical engineer before any forms or steel go in — two weeks ahead, give the geotech your footing sequence and standing schedule, and flag the footings you identified from the boring logs. (2) Lift-by-lift compaction testing of structural fill — two weeks ahead, book the testing laboratory by the week off your look-ahead, not by the day, and compute how many tests your specification actually requires so you know your real production rate. (3) Rebar and anchor-bolt inspection before each concrete placement, which is both a special inspection and, in most jurisdictions, a building-department footing inspection — two weeks ahead, confirm who the special inspector is, what notice they require, and whether the AHJ inspection can run the same morning. A fourth worth naming: masonry grout inspection and prism tests, or high-strength bolting and welding inspection on the steel.


Applied Scenario

21. Your job has 47,500 BCY of cut and needs 19,000 CCY of compacted structural fill. Swell is 24%, shrinkage is 11%. The export haul is 9 miles each way. Your excavator produces 265 LCY/hr and loads a 13 LCY truck in 2.9 minutes. Loaded speed averages 23 mph, empty 29 mph, spot 1.0 minute, dump 2.0 minutes. You work 9 productive hours per day.

(a) How many BCY of cut go to fill, and how many are exported? (b) Convert the export to LCY and to truckloads. (c) Compute cycle time and the required truck count. (d) Compute the export duration in work days. (e) Your broker can supply 20 trucks. State the schedule consequence in one sentence.

Answer

(a) Cut to fill = 19,000 ÷ (1 − 0.11) = 19,000 ÷ 0.89 = 21,348 BCY. Export = 47,500 − 21,348 = 26,152 BCY.

(b) LCY = 26,152 × 1.24 = 32,428 LCY. Loads = 32,428 ÷ 13 = 2,494.5 → 2,495 loads.

(c) Haul = 9 ÷ 23 = 0.3913 hr = 23.5 min. Return = 9 ÷ 29 = 0.3103 hr = 18.6 min. Cycle = 1.0 + 2.9 + 23.5 + 2.0 + 18.6 = 48.0 min. Trucks = 48.0 ÷ 2.9 = 16.6 → 17 trucks.

(d) 32,428 LCY ÷ 265 LCY/hr = 122.4 hr ÷ 9 = 13.6 → 14 work days.

(e) Twenty trucks is three more than the excavator can serve, so production and duration are unchanged at 14 work days — you would be paying three trucks to queue, and the right move is to release them or add loading capacity so the fleet you are renting is actually used.


Scoring Guide

Score What it means
18–21 correct (85%+) Strong. You can price and sequence a sitework-and-structure package. Move to Chapter 9.
15–17 (70–84%) Ready to proceed. Re-read whichever of §8.2, §8.3, §8.6, or §8.7 you missed most from.
11–14 (50–69%) Re-read the chapter, then redo Part C of the exercises. The unit conversions and the fleet-balance arithmetic are the two things you must own before estimating in Chapter 12.
Below 11 Work through the chapter with the 📋 Try it drill and Case Study 1 side by side, then retake. Do not skip ahead — Chapters 9, 10, 12, and 14 all assume this material.

The four items to get right no matter what: #2 and #3 (bank versus loose, and production), #7 (the form cycle sets the schedule), #12 and #19 (whose delay it was, and why six days became twenty-three), and #20 (hold points). Those are the ones that show up in your first month on a job.