Chapter 28 Quiz — Cost Control

23 questions. Answers and explanations are hidden — work each one before you open it, and do the arithmetic on paper rather than in your head. Scoring guide at the end.


Multiple Choice

1. Of the five numbers on a cost report — budget, committed, cost to date, cost to complete, and forecast at completion — exactly one requires human judgment. Which, and why does it matter?

A. Budget, because contingency transfers are discretionary B. Committed, because pending changes must be estimated C. Cost to date, because accruals are estimates D. Cost to complete, because it is the only number that decides whether the report is useful

Answer

D. Budget is a controlled document. Committed is a stack of signed agreements. Cost to date is invoices and payroll, with a small judgment component in the accruals. Forecast at completion is arithmetic — cost to date plus cost to complete. Cost to complete is somebody's opinion, and it is the only column that can still be changed by a decision. A cost report that can be produced without a human being making a judgment is not a cost report; it is a spending statement with extra columns.

2. The Northgate month-nine report showed $210,000 favorable. After the autopsy, that $210,000 was best described as:

A. A genuine buyout saving that later evaporated B. An accounting error C. The net buyout variance — $340,000 of savings less $130,000 of buyout overruns — and nothing else D. The unspent portion of contingency

Answer

C. Six packages bought below the estimate for $340,000 (curtain wall $118,000, HVAC $86,000, finishes $64,000, electrical $42,000, fire suppression $18,000, elevators $12,000); four bought above it for $130,000 (earthwork $46,000, miscellaneous metals $38,000, site paving $24,000, masonry $22,000). `$340,000 − $130,000 = $210,000.` The number was a report about procurement, presented where readers expect a report about the job. It contained no information about production, no information about accruals, and no information about the $1,620,000 of scope nobody had bought.

3. A cost code that is physically 100 percent complete shows cost to date $478,000 and a forecast at completion of $412,000. The implied cost to complete is:

A. $0, because the code is finished B. Negative $66,000 — the report is asserting that a completed footing will refund money C. $66,000, an overrun D. Not computable without the percent complete

Answer

B. Cost to complete = forecast − cost to date = $412,000 − $478,000 = ($66,000). That line is telling you, in the plainest language a spreadsheet has, that nobody re-forecast the code — the forecast was left at budget and the cost-to-complete column was computed as the difference. The correct forecast for a physically complete code is its cost to date, full stop: $478,000, variance ($66,000). A completed code is the easiest forecast on the report and the one most often skipped, because "done" feels like it needs no attention.

4. Kestrel has an executed subcontract with Ironbridge Steel for $6,180,000 and no pending changes. The correct forecast for that code, and the reason:

A. Budget, because the estimate is the baseline B. Cost to date ÷ percent complete, because that is the actual rate C. $6,180,000, because a subcontract converts a productivity risk into a price you already know D. Budget × (1 − percent complete), added to cost to date

Answer

C. Forecast = executed subcontract value + executed changes + pending changes you expect to owe. Unless scope changes, you direct extra work, or the subcontractor fails, the number will not move. This is a large part of why general contractors subcontract so much work: you give up margin and you buy certainty. Every dollar you self-perform is a dollar whose cost you must forecast with judgment instead of read off a contract.

5. You should believe a unit-rate trend when:

A. The superintendent agrees with it B. At least 10 percent of the quantity is installed C. At least 20 to 25 percent of the quantity is installed AND at least three consecutive periods point the same direction D. The variance exceeds 10 percent

Answer

C. Both conditions, not either. Twenty to twenty-five percent, because early rates are contaminated by mobilization (a fixed cost over a tiny denominator), by a real learning curve, and by the noisiness of small denominators. Three periods, because one period is an event, two is a coincidence, and three is a system — and a system will keep producing that rate until somebody changes it. Note that the investigation is never premature. Only the forecast can be.

6. A subcontractor performed $34,000 of work you directed verbally, with no subcontract change and no invoice. Recording it correctly at period end has what effect?

A. Cost to date rises; the forecast is unchanged B. Cost to date and forecast at completion both rise, dollar for dollar C. The forecast rises; cost to date is unchanged D. Neither moves until the change order is executed

Answer

B. This is a Type 2 accrual — an unrecorded commitment. It is real, new, unbudgeted cost that appeared out of a conversation, so both columns move together. Contrast a Type 1 timing accrual — ready-mix delivered but not invoiced — where cost to date rises and the forecast does not, because the work was already in the forecast and you have merely recognized consuming some of it. A Type 2 accrual is, in substance, a change order that has not been written yet.

7. Which percent-complete method is structurally incapable of ever signalling a problem?

A. Units installed B. Cost-to-cost C. Milestone / weighted steps D. Level of effort

Answer

D. Level of effort measures elapsed duration ÷ total duration, so it reports progress whether or not anything happened. By construction it always says you are exactly on plan. It is the right method for supervision, temporary facilities, and cleanup — costs that genuinely accrue with time — but you must never read it as evidence about production. Cost-to-cost is circular (a wrong forecast produces an equally wrong percentage, and spending inefficiently makes you look further along); milestone credits money moved to a vendor as progress; units installed understates early effort.

8. Your masonry code is $22,000 over because you bought it over budget. Your elevator code is $12,000 under because you bought it under. Transferring $12,000 of budget from elevators to masonry is:

A. Legitimate, because the totals do not change B. Legitimate if the project executive approves it C. Concealment, because the work did not move — only the variance did D. Legitimate only on a lump-sum contract

Answer

C. The test is one question: did the work move, or did only the overrun move? The masonry work will still cost what it costs and the elevator work will still cost what it costs, so the transfer changes no dollar on the job. What it does is delete two pieces of true information — that you bought masonry badly and elevators well — that your estimating department needs for the next bid and your project executive needs this month. The tell is timing: legitimate transfers happen when the work happens; concealment transfers happen in a batch in the last three days of the month.

9. You open an unfamiliar cost report. Thirty-eight of its forty-two lines show forecast exactly equal to budget. The first thing this tells you is:

A. The job is well managed B. Nobody forecast anything — the report is the budget wearing a costume C. The estimate was accurate D. The codes are too coarse

Answer

B. This is red flag #1, and it is the fastest read on any report. A report where nothing moved is suspicious, not reassuring. Ask for the method column; any line whose method is "budget" is unforecast. Then check whether the cost-to-complete figures on those lines are exactly budget minus cost to date — if they are, they are plugs, not forecasts, and the variance column is a column of zeroes because nobody computed anything.

10. A self-perform code has a total quantity of 46,000 SF and a budget of $322,000. To date, 20,700 SF are installed at a cost of $169,740. The cost to complete by the unit-rate method is:

A. $152,260 B. $177,100 C. $207,460 D. $377,200

Answer

C.

Actual unit rate   = $169,740 ÷ 20,700 SF = $8.20/SF   (budget rate: $322,000 ÷ 46,000 = $7.00/SF)
Percent installed  = 20,700 ÷ 46,000 = 45.0%
Quantity remaining = 46,000 − 20,700 = 25,300 SF
Cost to complete   = 25,300 SF × $8.20 = $207,460
Forecast           = $169,740 + $207,460 = $377,200
Variance           = $322,000 − $377,200 = ($55,200), 17.1% over

The distractors are the three most common errors: A is budget minus cost to date — the plug. B is the remaining quantity at the estimated rate, which quietly asserts the crew is about to become 17 percent more productive tomorrow for no stated reason. D is the forecast at completion, not the cost to complete.

11. Northgate's $190,000 concrete labor overrun, compared against Kestrel's fee on the whole project, is approximately:

A. 2 percent of the fee B. 10 percent of the fee C. 25 percent of the fee D. 40 percent of the fee

Answer

B. $190,000 ÷ $1,824,800 = 10.4 percent. One badly-run self-perform package worth $1.2 million ate a tenth of the profit on a $48 million building. That is the arithmetic of general contracting, and it is why a project manager who thinks $190,000 is a small number on a big job has the scale exactly backwards.

12. At Northgate month nine, contingency was 54 percent drawn against 37 percent of the work complete. The correct reading of that 17-point gap is:

A. Normal and requires no comment B. Evidence of poor productivity C. The earliest reliable warning a job gives — risks are materializing faster than work is completing D. Proof that the contingency was underfunded at bid

Answer

C. Contingency is consumed when identified risks materialize; work is consumed as the job progresses. If the first is outrunning the second, the risk register was optimistic and the remaining reserve will not cover the remaining risk. On Northgate the gap was defensible — soils, dewatering, steel acceleration, an embed misplacement, rock in a trench, winter protection, every dollar nameable and front-loaded — but defensible is not comfortable. The dangerous version is the drawdown nobody can itemize, because that is contingency being used as a slush fund for overruns.


True / False

Give a one-line justification for each.

13. A favorable cost variance at month nine of a nineteen-month building job is good news.

Answer

False. At month nine the structure is done and the entire expensive interior has barely started, so a favorable variance is a report about work that has not happened yet. It usually means one of two things: you bought the job well, or the report has not caught up with reality. On Northgate the $340,000 of buyout savings sat on top of $15,818,000 of unperformed work in those same six packages — a cushion of 2.1 percent, on the packages where two-percent adverse moves live.

14. Correcting a missed accrual on a self-perform code moves the forecast by exactly the amount of the accrual.

Answer

False, and the error runs in the expensive direction. On a unit-rate forecast, forecast at completion = cost to date ÷ percent complete, so a missed cost understates the forecast by the missed amount ÷ percent complete. A $10,500 accrual missed on a code that is 42 percent complete hides $25,000. At 25 percent complete the same $10,500 hides $42,000. The accrual does not merely change the cost; it corrupts the evidence the forecast is built from.

15. Forecasting cost to complete as budget × (1 − percent complete) is arithmetically incapable of showing an overrun.

Answer

False — and the distinction is worth being precise about. Budget × (1 − percent complete) can show an overrun once cost to date exceeds budget × percent complete. On the Northgate elevated deck it would have produced $264,000 × 0.42 = $110,880, a forecast of $298,880 against a $264,000 budget — an overrun, though only about half the real one. The method that is genuinely incapable is the one the field engineer actually used: carrying the forecast at budget and letting cost to complete be the plug. A forecast structurally incapable of delivering bad news is not a forecast.

16. Charging one project's costs to another project to smooth a report is aggressive accounting, but it is not fraud.

Answer

False. It misstates two contracts' cost of the work, it misstates the company's work-in-progress schedule, and on a cost-reimbursable or guaranteed-maximum-price contract it takes money from an owner who is paying the cost of their work. It also never stays small, because the month you would move it back is always a month in which another job needs the room. The damage is rarely the dollars; it is what discovery does to a surety's confidence in every number the company has ever submitted.

17. Because subcontracted work is forecast at its committed value, a subcontractor's productivity is not the general contractor's problem.

Answer

False. On a fixed price it is not your direct cost, which is exactly why the committed method works. But a subcontractor losing money is a schedule risk and a forecast risk: pending changes you have not carried, backcharges that shrink in negotiation, and — the one that hurts — a distressed subcontractor whose default replaces a contract price with an emergency price. Watch pay applications against production, crew size trends, supplier calls, and lien notices, and carry the risk in writing even when you do not yet carry it in dollars.

18. Because cost control looks forward and must be timely, it is acceptable to accrue a cost from the superintendent's quantity log rather than from an invoice.

Answer

True, with one condition that is not optional: the accrual must be documented, sourced, labeled as an accrual, and reversed when the invoice lands. Yards placed times the purchase-order unit price is a defensible basis; a plug is not. Accrue from the field's record of what was performed, not from accounting's record of what was invoiced — and never guess in secret.


Short Answer

19. Explain, with arithmetic, why a job that is 60 percent billed and 75 percent spent is already in trouble even when no single line on the cost report shows a variance.

Answer

Billing 60 percent of a $40,000,000 contract earns $24,000,000 of revenue. Spending 75 percent of a $36,000,000 cost budget spends $27,000,000. You are $3,000,000 underwater right now.

The trap is that no line has to show a variance for that to be true. Every code can be forecast at budget; the budget column and the forecast column can be identical on all four hundred lines; the report foots; the report is accurate. It is also useless, because it is reporting the plan back to you.

The relationship between money spent and work produced is the entire signal. Cost to date on its own is noise. Cost to date divided by work produced is a unit rate, and that rate applied to the work remaining is a forecast. That chain — actual cost, over actual quantity, times remaining quantity — is the whole of cost control, and it runs toward the future.

20. Why does the current actual unit rate beat the estimated unit rate as a predictor, even when the estimator is excellent? And what does forecasting at the estimated rate implicitly assert?

Answer

Because the actual rate is a measurement of the entire production system as it really is — this crew's composition, this superintendent's sequencing, this site's material haul, this design's detailing complexity, this subcontractor's cooperation, this month's weather. The estimate priced a typical version of the work, by someone who had not met any of those things. When a prediction and a measurement disagree, the measurement wins.

Forecasting the remaining work at the estimated rate implicitly asserts that all of those factors are about to change at once — which they occasionally do, but only when somebody deliberately changes them. Hence the asymmetry: to forecast at the actual rate you owe nothing; to forecast better than actual you owe a written, specific, mechanical reason with a date. "Jamal split the level-4 topping into two placements and added a dedicated finishing crew effective November 8" is a reason. "We expect to improve" is a hope with a number attached.

21. A project manager brings you a $200,000 fade in month four. Describe the two possible reactions an executive can have, and explain — using the arithmetic of when an overrun is preventable — why one of them is far more expensive than the other.

Answer

Reaction one: "How did you let this happen?" Difficult forty minutes, a note in the file, a reputation as the project manager who has problems.

Reaction two: "What are we changing, and when do we know if it worked?" — with the forensics saved for the lessons-learned session at closeout, where they teach something.

The first reaction is more expensive, and the arithmetic says why. An overrun caught at 25 percent complete is mostly preventable; an overrun caught at 75 percent complete is mostly history. A company that makes bad news costly to deliver teaches every project manager to carry the number at budget and hope — which does not stop fades, it only delays them until they are four times bigger and nothing can be done. The pressure to hide bad news comes almost entirely from how organizations react to it. You get the reports your reaction deserves.


Applied Scenarios

22. At Northgate month twelve, you find a further $88,000 of unforecast cost on the direct cost of work. Starting from the corrected month-nine roll-up — direct cost of work forecast $41,240,000, general conditions $2,948,000, insurance and bonds $907,000, against a budget of $45,007,000 for those three lines, with contingency remaining $608,000 — compute the new projected contingency at completion and each party's share of the savings. Then state what changes once contingency reaches zero.

Answer
Direct cost of work, forecast      $41,240,000 + $88,000 = $41,328,000
General conditions, forecast                              $2,948,000
Insurance and bonds                                         $907,000
Subtotal before contingency, forecast                    $45,183,000
Budget for the same three lines                          $45,007,000
Variance                                                   ($176,000)

Projected contingency at completion = $608,000 − $176,000 = $432,000
   Meridian's 75%  = $324,000
   Kestrel's 25%   = $108,000

Kestrel's projected share falls from $130,000 to $108,000. Kestrel loses $22,000 of the $88,000 — 25 cents on the dollar — and Meridian loses $66,000.

Once contingency reaches zero, that ratio goes to 1:1. Kestrel eats overruns dollar for dollar, because that is what "guaranteed" means. That is the real reason an overrun matters this early: not the $22,000 it costs this month, but that it consumes the cushion protecting you from every remaining risk on the job — and the marginal cost of the next overrun is four times higher on the far side of zero.

23. A later Northgate report shows the HVAC line as follows: budget $4,310,000 · committed $4,224,000 · cost to date $2,956,800 · percent complete per Cardinal Mechanical's schedule of values 62 percent. Two directed changes have been performed and not priced; your estimate is $61,000. Sofia Marchetti's crew count on site has fallen from 22 to 13 over six weeks.

Compute the forecast, the variance, and the gap between money spent and work complete. Then say what you do this week.

Answer
Forecast at completion = committed + pending
                       = $4,224,000 + $61,000 = $4,285,000
Cost to complete       = $4,285,000 − $2,956,800 = $1,328,200
Variance               = $4,310,000 − $4,285,000 = $25,000 FAVORABLE

Money spent  = $2,956,800 ÷ $4,224,000 = 70.0% of the committed value
Work complete = 62%
Gap = 8 points

Two separate things are true and you must not confuse them. The forecast is $4,285,000 — that is your cost, because it is a fixed-price subcontract, and the buyout saving has fallen from $86,000 to $25,000 because you directed $61,000 of work.

The 8-point gap and the crew count are a different signal entirely. Billing ahead of production plus a crew halving over six weeks is the classic distress pattern. This week: verify installed quantities independently rather than accepting the schedule of values; check whether the two suppliers who called have been paid and whether any preliminary lien notices have arrived; require a manpower plan and a six-week look-ahead in writing by Friday; and price what it would cost to complete the balance with somebody else, so that if you need that number you are not computing it under duress. Carry the $4,285,000 in the forecast and write the risk note. A distressed subcontractor is a schedule risk and a forecast risk before it is ever a cost variance.


Scoring Guide

Score Reading
21–23 correct You can build, read, and defend a cost report. Move to Chapter 29.
17–20 correct Solid. Re-read §28.6 (the four methods and when to believe a trend) and §28.9 (the red-flag checklist) before moving on.
13–16 correct Rebuild the Northgate concrete labor table in §28.6 by hand, on paper, and re-work the 📋 Try it drill without looking at the answer.
Under 13 Re-read the chapter with a calculator. Foot the month-nine report in §28.4 yourself — cost to date plus cost to complete equals forecast, budget minus forecast equals variance — and do not move on until it comes out.

70 percent (16 of 23) is the threshold to proceed. Every question here has an analogue on a real monthly report, and on a real monthly report the answer key is a job that finishes eleven months later.