Case Study 31-1 — Sixty-Five Thousand Four Hundred Dollars of Missing Paper: The CO #14 Autopsy
Kestrel Construction Group, Meridian Health System, the Northgate Outpatient Pavilion, and every person in this case study are illustrative composites. Contract markup percentages, notice periods, and the recoverability of impact costs vary by contract and by jurisdiction; nothing here is legal advice.
Setup
You already know the shape of this one from the chapter's hook. Now we are going to take it apart record by record, because the interesting question is not what went wrong — that part takes one sentence — but exactly which piece of paper was worth exactly how many dollars.
The project. Northgate Outpatient Pavilion. CM at Risk, guaranteed maximum price of $47,500,000, 565 calendar days, extended general conditions stipulated at $5,150 per calendar day.
The event. Week 24. Meridian's imaging vendor substituted a different MRI unit after the GMP was set. Deeper depressed slab, added structural framing, expanded RF shielding, upsized electrical feed. Pri Sethi called Tyler Brandt at 4:50 on a Thursday afternoon and said go ahead, I'll get you paper. She guessed "about $60,000." Jamal Foster's crew started Monday at 6:00 a.m. and worked four days with no time-and-material tickets, no segregated cost code, and no confirming letter.
The money, at the end.
| CO #14 | Amount |
|---|---|
| Owner's verbal understanding of cost | "about $60,000" |
| Kestrel's actual cost incurred | $186,400 |
| Cost substantiated with contemporaneous records | $121,000 |
| Negotiated settlement, eight weeks later | $142,750 |
| Kestrel's unrecovered cost | $43,650 |
| Time claimed / granted | 9 CD / 4 CD |
What happens, record by record
Here is the whole documentary record of CO #14 — not just the holes. I want you to see the records that worked sitting next to the records that did not, because the ones that worked are the ones you will be tempted to skip on your own busy Thursday.
The self-perform cost of $68,150 splits cleanly. Days 5 through 17 were ticketed and coded: $49,100. Days 1 through 4 were not: $19,050. The subcontracted cost of $71,900 was fully papered. That is the entire story of the $121,000.
| Record | Did it exist? | What it actually proved | Dollars it carried |
|---|---|---|---|
| Vendor pad drawing, transmitted by email at 3:47 p.m. Thursday | Yes — timestamped | The event, the date, and that the change originated with Meridian's vendor. Entitlement was never seriously argued | Enabling. Without it, eight weeks becomes eight months |
| Written directive or CCD from Meridian | No | — | — |
| Same-day confirming letter from Tyler to Pri | No | Would have fixed date, scope, authority, and killed "$60,000" before it hardened | Enabling — every line below leans on it |
| Written cost notice, sent day 14 | Yes — just inside the 14-day clock | Preserved the entire cost claim | Gate. Miss it and the number is $0, not $121,000 |
| Written time notice, 7-day clock | No — never sent | — | $25,750 |
| T&M tickets, Monday–Thursday (days 1–4) | No | 264 MH of concrete crew, three pieces of equipment, and the demolition quantity | $19,050 |
| T&M tickets, Friday onward (days 5–17), signed by Pri each morning | Yes | Every hour, every machine, every delivery on the pit after Friday | $49,100 |
| Cost code 03-310-CO14 | Opened Friday — four days late | Automatic payroll capture from day 5. Would have recovered the same $19,050 with no tickets at all | The backstop that also failed |
| Subcontractor change orders — Ironbridge Steel, Cordova RF shielding, Halcyon Electric, Cardinal Mechanical | Yes — executed, with quotes and invoices behind each | Every dollar of subcontracted change cost | $71,900 |
| Ready-mix delivery tickets, Monday | Partly | One ticket covered both the base pour and the changed pour. Quantity, yes; the split, no | Contested; absorbed into the $19,050 |
| Dated photographs of the placed slab before demolition | No — two undated phone photos in a text thread | Would have fixed the demolition quantity and the as-found condition | $5,769 at the VE-04 argument |
| Daily reports, Monday–Thursday | Yes, and useless | "Crew on imaging slab." No scope split, no hours by name, no direction named | ≈ $0 as proof |
| Accepted week-28 schedule update, approved by Meridian | Yes | Four of the nine calendar days, visible on the longest path, in a document the owner had already signed | $20,600 |
| Contemporaneous time impact analysis (fragnet, week 25) | No — Wei Chen ran it in week 30 | — | The other five days |
| Measured-mile baseline on the adjacent slab pours | No | Would have supported the $22,800 of disruption Kestrel believed it suffered | $22,800 claimed, $0 recovered |
The $19,050, in its parts
People treat "four days of missing tickets" as an abstraction. It is not. It is three lines:
| What the tickets would have shown | Arithmetic | Amount |
|---|---|---|
| Concrete crew labor, days 1–4 | 264 MH × $54.00/MH burdened composite | $14,256 | |
| Equipment — breaker attachment, skid steer, pump — 4 days | 4 days × $960/day | $3,840 | |
| Demolition disposal, six roll-off loads of broken slab | Hauler invoices | $954 |
| Total unprovable self-perform cost | $19,050 |
Fourteen thousand dollars of that is people's time. Jamal Foster could tell you every name. He could not tell you which hours went to the changed pit and which went to the base slab work happening thirty feet away on the same days, because nobody was asked to write it down and there was no code to write it into.
The $25,750 is bigger, and nobody expects it
(9 CD claimed − 4 CD granted) × $5,150/CD = $25,750.
Read that again against the $19,050. More than half the documentation gap was time, not work. The four missing days of tickets cost $19,050. One missing notice letter and one un-run schedule analysis cost $25,750. The letter would have taken ten minutes. The fragnet would have taken Wei Chen about two hours in week 25, against a schedule Meridian had already approved.
The eight weeks
Entitlement was never the fight. Meridian's risk register — written into a GMP exhibit during preconstruction — had already assigned imaging-equipment risk to Meridian, and the GMP qualification page named the MRI unit the price was based on (Chapter 6, Chapter 11). Pri never once said this isn't ours. She said this isn't sixty thousand dollars and she was correct about that too.
Here is the ladder.
| Week | What moved | Number |
|---|---|---|
| 24, Thu | Verbal direction. Nothing written | — |
| 24, Fri | Dani Okonkwo asks what cost code the pit goes to. Code 03-310-CO14 opened that afternoon; tickets begin Friday | — |
| 26 | Written cost notice, day 14. No time notice | No number |
| 27 (internal) | Draft COR-14 built at $269,740, including a $22,933 cumulative-impact allowance priced off a published inefficiency table. Ray strikes it before it leaves the building | $269,740 → — |
| 27 | COR-14 revision 1 submitted | $246,807 |
| 29 | Meridian's written response, one page | $98,600, 0 CD |
| 30 | Cordova's final RF shielding invoice comes in $8,600 under its quote. Kestrel reduces its own number, unprompted, and submits revision 2 | $238,207 |
| 30 | Wei Chen runs the time impact analysis — five weeks late | 9 CD claimed |
| 32 | Settlement meeting | $142,750, 4 CD |
COR-14 revision 2, as it sat on the table:
| Line | Amount |
|---|---|
| Kestrel self-perform direct cost | $68,150 |
| Self-perform overhead and profit @ 15% | $10,223 |
| Subcontracted direct cost — Ironbridge, Cordova, Halcyon, Cardinal | $71,900 |
| Subcontractor impact — Cardinal remobilization $7,845, Halcyon out-of-sequence $4,476 | $12,321 |
| Kestrel markup @ 5% on subcontracted work and subcontractor impact | $4,211 |
| Subtotal | $166,805 |
| Bond and insurance @ 1.35% | $2,252 |
| Cost of the work | $169,057 |
| Extended general conditions, 9 CD × $5,150/CD | $46,350 | |
| Disruption to Kestrel's own concrete operation, adjacent pours | $22,800 |
| COR-14, revision 2 | $238,207 |
Week 26 — the phone call nobody enjoys
RAY: Pri, I'm calling before you get paper, because I don't want you to read a number on a page for the first time. The MRI pit is not sixty thousand dollars.
PRI: How far off?
RAY: Far. I'm not going to give you a number today because I'd be guessing and you'd remember the guess. What I can tell you is the subcontract side alone — Ironbridge, Cordova, Halcyon, Cardinal — is over seventy.
PRI: (pause) Okay. That's fair notice and I appreciate it. Put the notice in writing today, would you, because my finance people are going to want the date.
RAY: It went out this morning.
That is the correct call and it cost Ray nothing. Two things about it are worth studying. He gave the number he could stand behind — the subcontract file — and refused the number he could not. And he named the bad news himself, eight weeks before the meeting where it would have looked like an ambush.
Week 29 — the one-page response
Meridian's response was not a build-up. It was a position, and it fit on one page:
| Meridian's week-29 allowance | Amount |
|---|---|
| Subcontracted direct cost, fully documented, with Kestrel's 5% | $75,495 |
| Self-perform, limited to hours on tickets Pri had personally signed, with 15% | $21,850 |
| Allowance for material invoices Kestrel had produced | $1,255 |
| Total | $98,600 |
| Time | 0 CD |
| Impact | $0 |
Note what Meridian left off: bond and insurance. Nothing sinister — their accountant did not know the line existed. Ray put it back in week 32 and got it, because it is a contract entitlement and it is arithmetic, not an argument. At the settled numbers it was worth $1,781.
Note also what the response reveals. Meridian allowed, essentially to the dollar, what Pri had personally signed her name to. The owner's rep's signature on a daily ticket is not a legal concession of anything. It is, functionally, the boundary of what gets paid.
Week 30 — the trailer, before anyone drove anywhere
MARGO: You're going to give back the twenty-two eight.
RAY: I am.
MARGO: Jamal's crew lost that. I watched them lose it.
RAY: I know. I believe you and I believe him. I also can't show it to anybody. There's no measured mile on those pours, there's no separate code, and the daily reports say "crew on imaging slab." If I put a number in front of Pri that I can't open up, she stops believing the hundred twenty-one I can open up.
MARGO: So the crew eats it.
RAY: The company eats it. And then we change how we do this, so nobody eats it again.
WEI CHEN: For the record, I can defend four days off the week-28 update. The other five I'd be reconstructing, and their consultant will take it apart. I'd rather say that first than have it said to me.
That exchange is the whole chapter. Margo is right about the facts. Ray is right about the record. Both of those can be true at the same time, and in a negotiation the record wins.
Week 32 — the settlement, and how the $12,741 works
The meeting itself is in §31.7. What matters here is the arithmetic underneath it, because the markup number surprises people:
| Settlement build-up | Arithmetic | Amount |
|---|---|---|
| Substantiated subcontracted cost | $71,900 | |
| Substantiated self-perform cost (days 5–17) | $49,100 | |
| Substantiated cost | $121,000 | |
| Self-perform overhead and profit | $49,100 × 15% | $7,365 | |
| Kestrel markup on subcontracted work | $71,900 × 5% | $3,595 | |
| Bond and insurance | $131,960 × 1.35% | $1,781 | |
| Contractual markups earned | $12,741 | |
| Priced value of the substantiated work | $133,741 | |
| Extended general conditions, 4 CD granted | 4 × $5,150 | $20,600 | |
| Subtotal | $154,341 | |
| Less: VE-04 demolition shared-risk split | ($5,769) | |
| Less: trade to execute this week and reach the current pay application | ($5,822) | |
| CO #14 as executed | $142,750 |
Kestrel earned its full contract markup — every point of it — on everything it could prove. That was $12,741. It was entirely consumed, and then some, by four days of missing tickets and one unsent letter.
Analysis
Why the loss is $43,650 and not $65,400
The documentation gap was $65,400. The loss was $43,650. The difference is not a discount; it is arithmetic, and it is worth walking:
| Line | Amount |
|---|---|
| Self-perform cost never substantiated (days 1–4) | $19,050 |
| Extended general conditions burned but not paid, (9 − 4) × $5,150 | $25,750 | |
| Less contractual markup actually earned on the substantiated work | ($12,741) |
| Concessions made to close in eight weeks: VE-04 split $5,769 + speed trade $5,822 | $11,591 |
| Unrecovered | $43,650 |
The markup line is doing something specific. Kestrel's profit on this change order was $12,741, and it went to pay for the four days it could not prove. CO #14 did not earn a small margin. It earned nothing and then ate $43,650 of hard cost.
The mechanism, stated once
Every line Meridian paid traced to a record made before anyone was arguing. Every line Meridian did not pay traced to a record made afterward — or to no record at all. Pri Sethi was not looking for a reason to say no. She was looking for something she could put in a board packet.
That is the exchange rate this book keeps quoting from Chapter 25: contemporaneous records are worth roughly ten times reconstructed ones. On CO #14 the rate was worse, because reconstruction did not get a discount. It got a zero.
The seven things Kestrel changed afterward
Ray ran the debrief in week 34. Nobody was disciplined. Seven procedures changed, and every one of them names a specific failure in this case:
- The ninety-minute rule. Any verbal direction to perform work that is not on the drawings triggers three things within ninety minutes, by whoever took the call: a confirming letter to the person who gave the direction, a cost-code request to Lorena Vasquez, and a message to the superintendent that tickets start on the next shift. Nobody waits for the project manager to get out of a meeting. (Fixes: no confirming letter, code opened four days late.)
- Field authority to open a cost code. Any superintendent or assistant superintendent may open a change code without approval. A code opened for nothing costs nothing; a code opened late costs $19,050. (Fixes: the backstop that also failed.)
- Two clocks, two calendars, one card. Northgate's notice periods — 14 days for cost, 7 days for time — are printed on a card taped inside the front cover of every project notebook, and the change log now carries two separate notice-date columns. The time notice goes out even when it says "impact not yet determinable." (Fixes: $25,750.)
- The ticket book lives in the truck. Pre-numbered, triplicate, with the signature acknowledges resources expended, not entitlement or price disclaimer printed on every page. If the owner's representative declines to sign, the ticket is annotated "presented at [time], signature declined," self-signed, and emailed the same day. (Fixes: $19,050.)
- Photograph before you demolish. Any demolition of installed work under a change gets a dated photo set before the first swing, filed to the change number. It is a hold point, not a courtesy. (Fixes: the $5,769 VE-04 concession, which Kestrel lost because it could not show the as-found condition.)
- Wei runs the fragnet in week one, always. Every change over $25,000, and every change touching a critical-path activity, gets a fragnet inserted into the accepted current update within five business days — whether or not Kestrel intends to request time. A "zero days" answer gets written down and stated affirmatively on the change order. (Fixes: five denied days, and buys credibility for the next change that does need time.)
- A job hazard analysis for changed work. Bea Salgado made it a hold point after reading the Monday-morning sequence: demolition, silica, and a 4'-6" excavation inside a building pad, performed under a JHA written for placing a 5-inch slab on grade (Chapter 24). (Fixes: the thing that did not go wrong, which is the only kind of luck you should never spend twice.)
Total cost of all seven: about forty minutes of somebody's day, on the days a change appears.
Discussion Questions
-
Ray struck a $22,933 cumulative-impact line from his own draft before it ever reached Meridian. Argue that he was wrong to — that a negotiator should open high and let the owner discount. Then rebut your own argument using what happened in week 32.
-
Pri Sethi's week-29 response allowed, almost exactly, the hours she had personally signed for. Is that a defensible position for an owner's representative, or is it an abdication of judgment about costs she knows were incurred? Answer as Pri, then answer as Ray.
-
The missing time notice cost $25,750 and the missing tickets cost $19,050 — yet almost every project team in the industry is better at tickets than at time notices. Why? What is structurally different about the two habits, and what would you change in a project's routine to fix the harder one?
-
Kestrel gave a $5,822 concession purely to reach that month's pay application. Compute what that speed was worth if Kestrel's cost of money is 9.0% and the alternative was payment three months later. Was it a good trade? (Hint: it is not close, and the reason is in Chapter 32.)
-
Of the seven procedural changes, exactly one would have recovered the money by itself even if every other failure had still occurred. Which one, and how much would it have saved? Defend your answer against the two runners-up.
Your Turn
You are the project engineer on Northgate. It is 5:10 p.m. on the Thursday of week 24. Tyler Brandt has just hung up with Pri Sethi and walked into the trailer and told you what she said. Nothing has been written yet. You have until you go home.
Produce, in forty-five minutes:
- The confirming letter, addressed to Pri, copied correctly, dated today. Fix the date, the scope, the source, the authority, and the fact that "$60,000" was an estimate and not a price.
- The cost-code request to Lorena Vasquez — one paragraph naming the code, the effective date, what gets charged to it, and who is authorized to charge it.
- A blank T&M ticket for Monday, with every field from §31.3 laid out, including the disclaimer line, and the one field that most tickets omit — what was physically done.
- A three-line instruction to Wei Chen stating what schedule analysis you need, against which schedule update, and by what date.
- One sentence to Jamal Foster that his crew will actually follow at 6:00 a.m. on a Monday.
Then do the part nobody assigns: write down what you would have to give up to do all five tonight. Because the reason none of it happened in week 24 is not that anybody thought it was optional. It is that it was 5:10 p.m. on a Thursday and there were nine other things.