Chapter 35 Quiz
24 questions. Answer before you open the <details>. Scoring guide at the end.
Multiple Choice
Q1. Level of development is a statement about:
A. How much geometric detail an element carries B. How much you are entitled to rely on an element C. How far along the design is D. Which software produced the element
Answer
B. LOD describes reliance, not appearance. A manufacturer's model with every louver and bolt head can be worthless if it is not the unit that was bought; a grey box at the exact outside dimension with its exact service clearances at its exact coordinates can be entirely reliable. Detail is a property of the picture. Level of development is a property of the promise.
Q2. You have a coordination model of a hospital floor at LOD 350. Which use is not legitimate?
A. Confirming that duct, sprinkler main, and lights fit inside a corridor ceiling cavity B. Extracting linear feet of 4-inch sprinkler pipe for a change-order price, with the boundary stated C. Extracting square feet of gypsum board for the drywall subcontract buyout D. Identifying a clearance violation in front of an electrical panel
Answer
C. A partition modeled for coordination carries correct thickness and location because that is what coordination needs. It frequently does not carry layer count, run-to-deck versus run-to-above-ceiling, stud gauge, or rating. The model reports wall surface area; the estimate needs board area. On Northgate that difference was 17.8 percent and $306,700.
Q3. Which of these can a geometric clash test never find, at any tolerance and at any level of development?
A. A medical gas rack passing through a diagonal brace B. An electrical panel sitting inside an air handler's filter-pull zone C. Precast panels blocking the mat road the crawler crane leaves through D. Duct insulation overlapping a beam flange by 0.4 inch
Answer
C. The crane and the panels never occupy the same space at the same time, so there is no geometry to test. Note that B is findable — but only if somebody modeled the clearance zone and wrote the rule that tests for intrusion into it. That is the difference between a soft clash and a 4D clash, and most coordination programs are quietly mediocre at the first one.
Q4. Grace's level-two triage took 1,840 raw results to 61. Which statement is correct?
A. 1,779 of the items were software errors B. The raw number measures how many elements are in the model, not how much trouble you are in C. The raw number should always be reported to the owner, for transparency D. Grouping conflicts together conceals real problems
Answer
B. One 60-foot duct main crossing one sprinkler main reports as fourteen element-pair clashes and is one decision. A coordinator who reports raw counts is either inexperienced or hiding. Report the filtered count, the funnel that produced it, and the rules — which belong in the execution plan with a signature on them.
Q5. Gravity drainage sits first in the routing-priority convention because:
A. Plumbing subcontractors have the strongest coordination clauses B. Drainage pipe is the most expensive to move C. Slope is fixed by code and invert elevations are fixed at both ends — essentially zero degrees of freedom D. It is installed first
Answer
C. The convention allocates space in order of decreasing constraint. The system with the fewest options claims its space first, because it is the one least able to recover from a bad decision. You cannot negotiate with gravity.
Q6. Northgate's model extraction returned 338,800 SF of gypsum board against a hand takeoff of 412,000 SF. The primary reason is:
A. The model was built carelessly B. The estimator padded the takeoff C. The model answers a different question — it reports modeled wall surface, and the coordination decisions behind wall heights, layer counts, and opening deductions are correct for coordination and wrong for quantity D. The extraction software rounds down
Answer
C. Not one of the four differences is a modeling error. Every partition is exactly where and as thick as it should be. What failed is the assumption that a model built to answer "does it fit?" can also answer "how much board do I buy?" A precise wrong number is more dangerous than a rough right one, because nobody checks it.
Q7. A 4D simulation will:
A. Compute the critical path B. Level your resources C. Calculate total float D. None of the above — it visualizes a schedule and calculates nothing the CPM did not
Answer
D. 4D finds spatial and sequence conflicts that CPM logic cannot express, and nothing else. It will also animate a schedule that is complete fiction, smoothly and confidently. Garbage in, cinematic garbage out.
Q8. The largest single line in Northgate's $643,500 VDC program cost, and where it sits, is:
A. Laser scanning, in Division 01 B. Subcontractor detailing — $369,000, inside the $40,000,000 direct cost of work C. Grace Lindqvist's time, in general conditions D. Software, in general conditions
Answer
B. Fifty-seven percent of the program is money paid to trade contractors to model. Only $46,000 of the $643,500 sits on a line that says anything about BIM — which is exactly why people believe it is free, and exactly why it fails on projects where nobody added it up.
Q9. A BIM requirement with no budget produces three possible subcontractor responses. Which is the most corrosive?
A. The sub declines and forces a fight B. The sub models badly, with whoever is cheapest C. The sub detail on paper, builds the job from the paper, and produces a model afterward to satisfy the requirement D. The sub submits a change order request
Answer
C. It is worse than no model, because it looks like compliance. The coordination never happened; you bought an expensive record of a process that did not occur. The other two responses at least tell you the truth in month one.
Q10. On the digital-twin spectrum in §35.8, the rungs that pay for most owners today are:
A. 1 and 2 — as-built drawings and an as-built model B. 3 and 4 — as-built model plus structured asset data, imported into the owner's maintenance-management system C. 5 only — the live-instrumented twin D. 2 and 5
Answer
B. Not because rung 5 is fake — hospitals, campuses, airports, and data centers do run real twins — but because rung 5 requires a facilities organization staffed and funded to consume it. Selling a live twin to an owner with four facilities staff and a work-order spreadsheet is selling a monument.
Q11. Kestrel's governing-document sentence in every Northgate MEP subcontract says:
A. The coordinated model governs everything after sign-off B. The contract documents govern everything, always C. The contract documents govern quality, product, performance, and quantity; after coordination sign-off for an area, the coordinated model governs three-dimensional location within that area D. The AHJ decides which document governs
Answer
C. And the reason it matters is that "but the mechanical drawing shows it here" stops being an argument in February. The drawing showed a single line in plan. The model showed a 46-inch insulated envelope at a specific elevation, and eight companies signed it.
True / False — justify in one line
Q12. A manufacturer's chiller model downloaded from a vendor website, with every louver and bolt head, is by definition a high-LOD element.
Answer
False. It can be worthless for coordination if it is not the model number that was actually purchased. Detail is not development.
Q13. The design model, the construction model, and the fabrication model are three stages of the same file.
Answer
False. Three different artifacts, made by different parties, for different purposes, with different legal responsibility. The design model is a wish, the construction model is a plan, the fabrication model is an instruction.
Q14. A soft clash will be found automatically as long as the clash-detection software is configured properly.
Answer
False. A machine cannot test for intrusion into a clearance that nobody modeled. Somebody has to model the access zone and write the rule — which is why an experienced coordinator is worth what they cost.
Q15. On a $2,000,000 tenant fit-out, a full multi-trade coordination program will very often not pay for itself.
Answer
True. Program cost has a floor and scales with parties and congestion; return scales with the rework available to avoid. On a fit-out with an existing grid and two systems there is not much. What does pay: a scan above the ceiling, coordination of the two or three congested spots, layout if you already own the instrument, and a 4D for the one hard week.
Q16. A steel tonnage extracted from an LOD 400 fabrication model can be more accurate than a hand takeoff.
Answer
True. Northgate's extraction returned 984.6 tons against a canonical 985 — because at LOD 400 the model is the fabrication instruction. There is no gap between the representation and the thing. That is what makes this the one place 5D works cleanly.
Q17. Because the 4D model found the crane trap, Wei Chen's CPM schedule was wrong.
Answer
False. Every activity had a defensible duration and a defensible predecessor. Every document in the standard set was correct. There is simply no CPM relationship that can express "the machine will not fit through the hole" — that sentence lives in three dimensions plus time.
Short Answer
Q18. State the hard rule of §35.2 in one sentence, and give one example of violating it that costs real money.
Answer
You may not extract a quantity from, or coordinate a clearance from, an element whose level of development does not support it.
Example: AHU-5 in Case Study 1. The LOD matrix required owner equipment at 400 with vendor data; the vendor package was nine weeks late; the LOD 300 placeholder survived sign-off carrying no coil-pull envelope. Coordination ran clean because there was no zone to test against. Cost: $31,200, found at startup when somebody tried to pull a coil.
Q19. Your first federation places the mechanical model 1,140 feet from the building and rotated. Name the correct fix, how long it takes, and the dangerous "fix" you must watch for.
Answer
Correct fix: a stated coordinate system, a project base point with real-world coordinates, a survey point, stated units, project north versus true north, and a small shared origin-test file — three cubes at known coordinates — that every party inserts and confirms before modeling anything else. About an hour, if written in week one.
Dangerous fix: a detailer who drags their model into place by hand. It now looks right, and every coordinate it will ever produce — every layout point, every sleeve, every hanger insert — is wrong by the amount of the drag. Detect it by checking the model against the shared origin-test file, not by looking at it.
Q20. Explain why "$861,750 ÷ $643,500 = 1.34" is a weaker argument for a coordination program than the distribution of the savings lines.
Answer
Because the ratio hides where the money came from. One line — the crane trap, $261,250 — is 30 percent of the gross savings and 41 percent of the entire program cost, and it came from a single afternoon in June. Two lines are 51 percent. BIM's return is not a steady trickle of small efficiencies; it is a small, certain, budgeted cost that buys down a low-probability, high-consequence risk. You evaluate that the way you evaluate an insurance premium — by what the tail looks like, not by the average.
Q21. What is the difference between "coordinate the model" and "verify the building," and name the Northgate finding that proves you need both.
Answer
Coordinating the model resolves conflicts among what the parties intend to build. Verifying the building confirms that what actually exists matches it. The level-three multi-trade rack proves the gap: the slab deflected about 1¼ inches high over forty feet under wet lightweight topping, between scan three and scan four. The rack had already released against scan three. It was built correctly, to a model that was correct, for a building that had moved — $18,400 and four days. A verification program has a frequency, and things happen between scans.
Q22. An owner says "we want BIM at turnover." Write the three questions that turn that into a scope you can price.
Answer
- Which rung? Do you want an as-built model, an as-built model with structured asset data, or that data imported into the maintenance-management system you actually use? (§35.8 rungs 2, 3, 4.)
- Which data fields, for which assets? Give me the list — tag, type, location, manufacturer, model, serial, install and startup dates, warranty dates and contact, service intervals, spares and filter sizes, responsible subcontractor, document links. Or tell me your system's import format and I will build the list from it.
- Who consumes it, and are they staffed to? If the answer is "nobody yet," you are buying a deliverable, not a capability — and you should buy the smaller one.
The follow-on is the one that saves the job: whatever the answers, capture the data as it arrives — at the submittal, verified at the nameplate, on the daily report. Reconstructing it in the last six weeks from equipment already above a hard ceiling is how you deliver a spreadsheet with 40 percent of the serial numbers wrong.
Applied Scenarios
Q23. (Applied — the job you inherit.) You take over a $31,000,000 project in month 6. The specification requires BIM. The execution plan on file is four pages and restates the specification. No coordinate origin was ever agreed. No MEP subcontract carries a detailing allowance. Level-one sheet metal has already been released for fabrication. The owner asks you, in tomorrow's OAC meeting, what your plan is.
Write the answer: what you do this week, what you do this month, and — the part that takes courage — what you tell the owner you can no longer achieve.
Answer
This week. Three things, none of which requires anyone's permission. (1) Publish a coordinate origin and an origin-test file, and require every party to confirm alignment in writing before the next exchange — one hour, and it is the prerequisite for everything else. (2) Get in writing, by RFI, what level of development the design models are represented to carry, by system, and whether they are represented as suitable for construction coordination. (3) Freeze fabrication release on every area not yet released, and put that in writing to each subcontractor the same day.
This month. (1) Rewrite the execution plan around the four sections that actually decide anything — the LOD matrix, the origin, the exchange schedule with dates, and sign-off authority with a stated obligation. (2) Price a detailing allowance for each MEP trade and take it to the owner as a change or to your own executive as a cost, because you will not get modeling you do not pay for. (3) Scope coordination to the congested areas only — you no longer have the calendar for the whole building, so spend it where the systems concentrate. (4) Get the governing-document sentence into the subcontracts by amendment.
What you can no longer achieve. Level one is gone. Sheet metal is cut; the model cannot change what is already fabricated, and pretending otherwise wastes the one thing you still have. Say so plainly: "Level one will be coordinated in the field, and I expect field rework there. Levels two and three I can still protect, and here is what it costs." An owner who hears that in month 6 can plan. An owner who hears it in month 11 has been managed badly.
Q24. (Applied — the 4D drill.) Here is the Willow Street gym roof sequence as scheduled:
| Week | Activity |
|---|---|
| 34 | Erect gym roof joists, grid A–E |
| 35 | Place gym roof deck |
| 36 | Set and flash RTU curbs |
| 37 | Roofing membrane over the gym, including around the curbs |
| 38 | Set RTU-1 through RTU-4 by crane |
Two constraints. Willow Street's frontage is a two-lane street across from Danforth Elementary School, with a hard crane blackout during arrival and dismissal — the working window is 9:15 a.m. to 2:30 p.m. And each pick takes about 55 minutes including rigging, set, and unhook, with 90 minutes of crane setup and 90 minutes of teardown each day, because the machine cannot stay on the street overnight.
(a) Name the sequence conflict, and say why no clash test would find it. (b) Do the crane-window arithmetic and state how many days the RTU set actually takes. (c) State the corrected sequence and the one procurement fact you must confirm before you commit to it.
Answer
(a) The conflict. Roofing "around the curbs" is scheduled in week 37 and the units land in week 38. You cannot complete the membrane around a curb before the unit is on it, and rigging four rooftop units across finished membrane is how you buy a roofing repair and a warranty argument. There is also a second-order conflict: the crane pick requires the gym roof area clear, and in week 37 the roofing crew is standing on it.
No clash test finds this because the geometry never intersects. The membrane and the units are never in the same place at the same time; the RTU sits on the curb in the finished building and will clash-test clean forever. What conflicts is access, work area, and sequence — which exist only in time.
(b) The arithmetic. The window is 9:15 a.m. to 2:30 p.m. = 315 minutes. Setup and teardown consume 90 + 90 = 180 minutes, leaving 135 minutes of picking. At 55 minutes per pick that is two picks per day, with 25 minutes of spare — not three. Four units therefore take two crane days, not one, and both must fall on days when school is in its normal schedule. Check the school calendar before you pick the dates; an early-dismissal day shortens the window and costs you a pick.
(c) The corrected sequence. Weeks 34–36 unchanged. Week 37: set RTU-1 through RTU-4 across two crane days. Week 38: complete the roofing membrane, including the flashing around the curbs. The procurement fact to confirm first is the RTU delivery date — you have just pulled the set a week earlier, and if the units are not on site in week 37 you have made the schedule worse, not better. Get the delivery confirmed in writing from the manufacturer before you re-logic anything.
Scoring Guide
| Score | Reading |
|---|---|
| 21–24 correct (85%+) | You can write and enforce an execution plan. Go run one. |
| 17–20 correct (70–84%) | Solid. Re-read §35.2 (LOD as reliance) and §35.9 (the economics) before you buy anything. |
| 12–16 correct (50–69%) | The vocabulary landed and the management did not. Re-do the 📋 Try it clash triage in §35.4 with the chapter closed, then re-take. |
| 11 or fewer (below 50%) | Re-read the chapter, then work Case Study 1 and Case Study 2 end to end with a calculator. |
The four to get right regardless of your total are Q1 (LOD is reliance), Q3 (what geometry can never find), Q8 (where the money actually sits), and Q9 (the reverse-engineered model). Everything else in this chapter is downstream of those four.