Chapter 34 Quiz — Construction Finance and Accounting

21 questions. Every answer and explanation is hidden — work each one before you open it. Have a calculator. Scoring guide at the end.


Multiple Choice

1. A work-in-progress schedule has eleven columns. How many of them are genuine inputs, and which one is the only genuinely soft number on the page?

A. Two inputs; the soft one is amount billed to date B. Four inputs; the soft one is total estimated cost at completion C. Six inputs; the soft one is percent complete D. Four inputs; the soft one is contract amount

Answer

B. The four inputs are contract amount, total estimated cost at completion, cost incurred to date, and amount billed to date. Everything else — estimated gross profit, gross profit percentage, percent complete, revenue earned, gross profit earned, and the over/(under) billing — is a mechanical consequence. Three of the four inputs are verifiable against the general ledger and the contract file. Total estimated cost at completion is a forecast, produced by a project manager, and it is where every construction accounting problem in history has lived.

2. A job has a $16,000,000 contract amount, $15,200,000 of total estimated cost at completion, and $9,120,000 of cost incurred to date. Revenue earned to date is:

A. $9,120,000 B. $9,600,000 C. $9,504,000 D. $10,000,000

Answer

B. Percent complete = $9,120,000 ÷ $15,200,000 = 60.00%. Revenue earned = $16,000,000 × 0.60 = $9,600,000. Check the gross profit two ways: $9,600,000 − $9,120,000 = $480,000`, and `estimated gross profit of $800,000 × 0.60 = $480,000 ✓. If those two disagree, you have an arithmetic error, not an accounting question.

3. Same job. Amount billed to date is $10,240,000. On the balance sheet this produces:

A. A $640,000 current asset called costs and estimated earnings in excess of billings B. A $640,000 current liability called billings in excess of costs and estimated earnings C. $640,000 of additional revenue D. Nothing; billings do not appear on the balance sheet

Answer

B. $10,240,000 − $9,600,000 = $640,000 over-billed. Over-billing is money collected for work not yet performed, so it is a current liability — a loan from the owner, repayable in work rather than in cash. Note what it is not: it is not revenue and it is not profit. Billings do not appear anywhere in the percentage-of-completion profit calculation.

4. A project manager learns of a $1,400,000 scope gap and leaves it out of her forecast "to see if she can absorb it." What has she done to the figures her company reports?

A. Nothing yet; the cost has not been incurred B. Understated percent complete and understated revenue C. Overstated percent complete, overstating revenue and gross profit D. Overstated cost incurred to date

Answer

C. Leaving the gap out keeps the denominator of the percent-complete calculation too small, so percent complete comes out too high. Revenue earned is contract × percent complete, so revenue is overstated — and because the job's expected profit has also shrunk by $1,400,000, the overstatement of gross profit is larger still. She has not absorbed anything. She has borrowed from a future period and told nobody.

5. An experienced CFO sees a large under-billing on a job. Her first question is not "when will you bill it?" It is "show me why the cost moved." Why?

A. Under-billings are always a billing-cycle timing difference B. A hidden cost overrun disguises itself as an under-billing C. Under-billings reduce the company's bonding capacity directly D. Under-billed jobs cannot bill retention

Answer

B. If a job's true cost at completion has risen and the forecast has not been updated, the denominator stays too small, percent complete comes out too high, and revenue earned comes out too high — while billings, which are driven by physical progress an owner's representative verified in the field, do not move. The gap opens between them and appears on the WIP as an under-billing. Of the four causes of under-billing — timing, unbilled change work, poor billing discipline, and an unrecognized cost overrun — only the first is benign.

6. Rivermont Elementary School #12's estimated gross profit percentage ran 4.91 → 4.11 → 3.59 → 3.08 → 2.39 across five consecutive reporting periods, on a job now 79 percent complete. The most defensible reading is:

A. Five unrelated events, each explained at the time B. One wrong estimate, released in increments small enough to survive each conversation C. Normal margin erosion on any hard-bid public school D. An accounting error in the percent-complete calculation

Answer

B. The largest single-period fade on that job is $180,000 on a $22,400,000 contract — eight tenths of one percent, and easy to explain away. Read the cumulative column instead. A job that fades in every period for five periods is not experiencing five unrelated events. It is experiencing one thing, released at the rate the organization will tolerate rather than the rate it was discovered. That pattern is precisely what a surety underwriter asks for multiple years of WIP schedules in order to see.

7. Kestrel earned $9,430,000 of net income on $410,000,000 of revenue in Year 1 — a 2.30 percent net margin. A single $4,000,000 loss job represents approximately:

A. 1 percent of the year B. 10 percent of the year C. 42 percent of the year D. 100 percent of the year

Answer

C. $4,000,000 ÷ $9,430,000 = 42.4%. One bad estimate, one unrecovered delay, or one uninsured event consumes almost half the company's annual net income. That ratio is the entire argument for forecasting discipline: at a low-single-digit net margin, cost control is not administration, it is the business.

8. Kestrel's working-capital turnover is $410,000,000 ÷ $20,332,080 = 20.2×. What does that number say?

A. Kestrel turns its inventory 20 times a year B. Every dollar of Kestrel's liquidity is supporting twenty dollars of annual volume C. Kestrel could support $20,332,080 more revenue D. Kestrel's bonding program is 20 times too large

Answer

B. Working-capital turnover measures how much annual volume each dollar of liquidity carries. Many underwriters get uncomfortable somewhere around fifteen to twenty times — thresholds vary by surety, sector, and market — so 20.2× is at or slightly past the edge. Note that Kestrel's program is conservatively supported at 7.4 times working capital. The obligations the surety has guaranteed and the volume the company is actually running are two different questions, and people confuse them constantly.

9. Sureties prefer audited financial statements over reviewed ones primarily because:

A. Audited statements are prepared faster B. An audit produces a legally binding guarantee of accuracy C. An audit tests the WIP schedule, including a challenge to total estimated cost on every significant contract D. Reviewed statements omit the balance sheet

Answer

C. An audit confirms contract amounts with owners, tests cost to date against the ledger, confirms billings, and challenges the total estimated cost at completion on every significant contract. That last procedure is the one that catches an optimistic forecast, which is why hidden fade surfaces at the year-end audit at so many contractors. An audit does not merely cost more. It removes the place the problem was hiding. No audit is a guarantee of accuracy; it provides reasonable, not absolute, assurance.

10. A contract's forecast moves from a $480,000 estimated profit to a $290,000 estimated loss. The job has already recognized $336,000 of gross profit. The charge to earnings in the period is:

A. $290,000 — only the loss B. $626,000 — the reversal plus the full loss C. $770,000 — the total movement in estimated gross profit D. Nothing until the job closes out

Answer

B. $336,000 + $290,000 = $626,000. An anticipated loss on a contract is not spread across the remaining work: the entire estimated loss is charged to income in the period it becomes known, and the profit previously recognized reverses.

Option C is the fade — `$480,000 − $(290,000) = $770,000` — and it is a different number for a different purpose. The $144,000 gap between the fade and the charge is profit that had not yet been recognized on the old forecast; it never touches the income statement because it was never there. Learn that distinction. It is the one people get wrong in the room.


True / False — give a one-line justification for each

11. Two jobs are each exactly 50 percent complete by cost and exactly on budget. Job A is billed at 50 percent of contract; Job B at 58 percent. Job B has recognized more gross profit.

Answer

False. Profit under percentage-of-completion is driven by percent complete and estimated gross profit; billings do not appear in the calculation at all. Both have earned exactly 50 percent of their expected gross profit. Job B has more cash, which is a different thing — and that cash is an advance against work Job B has promised and not performed.

12. Over-billings and under-billings are netted against each other on a contractor's balance sheet.

Answer

False. Over-billed jobs are summed and reported as a current liability; under-billed jobs are summed and reported as a current asset. They never net. Kestrel's balance sheet at January 31, Year 2 shows $2,915,920 of over-billings and $818,000 of under-billings; the net figure of $2,097,920 appears only on the WIP schedule.

13. A job that fades $400,000 has, by definition, lost money.

Answer

False. Fade is the decline in a job's estimated gross profit from one reporting period to the next. A job can fade $400,000 and still finish profitably. What fade measures is not the outcome — it is the quality of the forecast that produced the outcome, which is why a surety looks at it before almost anything else.

14. A bonding program is an asset the contractor owns, and a surety may not reduce it once granted.

Answer

False. It is a credit line the surety can withdraw, and its withdrawal is correlated with the contractor's need for it — the surety reduces the program at exactly the moment fade appears, which is the moment the contractor most needs to replace backlog. Every capacity heuristic in §34.7 describes a relationship, not a contract.

15. A late gain on a job is always good news and does not require explanation.

Answer

False. You should be able to name, for every gain on your WIP, the specific event that produced it — a settled claim, a favorable buyout, a released contingency whose named risks passed without occurring. Fair Oaks Water Plant Expansion's $150,000 gain at 95 percent complete has exactly such an explanation. "The job is going well" is not an event, and consistent late gains across many jobs mean the WIP has been understating profit and management has been steering on bad information in the other direction.


Short Answer

16. In three sentences, explain the chain that runs from a project manager's cost-to-complete forecast to a surety's decision about a $60,000,000 single-project limit.

Answer

The cost-to-complete forecast sets total estimated cost at completion, which is the denominator of the percent-complete calculation. Percent complete sets the revenue and gross profit the company recognizes this period, which flow into the income statement and, through the over/under-billing lines, onto the balance sheet. Those statements go to the surety, which sizes and prices the program against working capital, net worth, and — most heavily — the pattern of fade across several years of WIP schedules. Every dollar of revenue and profit the company reports this period was computed from a number a project manager produced.

17. Name the four causes of an under-billing and rank them from most benign to most dangerous, with a one-line reason for the ranking.

Answer
  1. Timing — the billing cycle closed just before a big cost hit; it fixes itself next month.
  2. Poor billing discipline — a schedule of values that does not track how cost incurs, or a project manager under-billing to avoid an argument; self-inflicted and correctable this month.
  3. Unbilled change work — you are performing changes that are not approved and cannot yet be billed; unpriced, unfunded work you are financing, and the entitlement clock may be running.
  4. An unrecognized cost overrun — the estimate moved and nobody admitted it; the worst, because the under-billing is not a billing problem at all and the reported revenue is already wrong.

18. Fair Oaks Water Plant Expansion: contract $16,510,000, billed to date $16,014,700, total estimated cost $15,470,000, cost incurred to date $14,696,500. This is a healthy job — 95 percent complete, a 6.30 percent estimated gross margin, the best percentage on Kestrel's schedule. Compute the net cash it will consume or generate over its remaining life, and say what the answer teaches.

Answer
  • Remaining to bill = $16,510,000 − $16,014,700 = $495,300
  • Remaining cost to complete = $15,470,000 − $14,696,500 = $773,500
  • Net cash consumption to finish = $495,300 − $773,500 = $(278,200)

A good job with the best margin on the schedule will still consume $278,200 of cash before it finishes. That is the lesson: over-billing is not a cushion, it is an advance, and the back end of every over-billed job is funded by the company rather than by the job. Multiply that across six or eight contracts closing out in the same two quarters and you have §34.8's Step 5 — the reason a contractor must book new work faster than it finishes old work purely to stay liquid. That is not a strategy. It is a treadmill.

19. Explain why "growth is a use of cash, not a source of it," using a contractor going from $120,000,000 to $165,000,000 of revenue at a 95 percent cost of revenue, roughly sixty days of cost carried, and a 2.5 percent net margin on the incremental volume.

Answer
  • At $120,000,000: `(60 ÷ 365) × $114,000,000 = $18,739,726` of cash tied up in work.
  • At $165,000,000: `(60 ÷ 365) × $156,750,000 = $25,767,123`.
  • Incremental working capital required: $7,027,397.
  • Incremental profit produced: $45,000,000 × 0.025 = $1,125,000.

The growth demanded roughly $7,000,000 of additional liquidity and returned about $1,100,000. The other $5,900,000 has to come from the line of credit, retained earnings, slower payment to subcontractors, or over-billing — and none of those is free or infinite. A company growing at that rate is financing that many more front-end cash troughs simultaneously, every year, and the faster it grows the further behind it falls. That is why fast-growing contractors fail and slow-growing ones do not, and it has nothing to do with how well they build.


Applied Scenarios

20 — Build the row and read it.

A job carries a contract amount of $23,500,000 including approved change orders, a total estimated cost at completion of $22,325,000, cost incurred to date of $14,511,250, and billings to date of $15,510,000. Last quarter its estimated gross profit was $1,410,000.

Compute (a) estimated gross profit and percentage, (b) percent complete, (c) revenue earned, (d) gross profit earned, (e) over/(under) billing, (f) the fade in the period, and (g) the net cash the job will consume or generate over its remaining life. Then state, in one sentence, whether this job belongs on the operations meeting agenda and why.

Answer

(a) $23,500,000 − $22,325,000 = $1,175,000`; `÷ $23,500,000 = 5.00% (b) $14,511,250 ÷ $22,325,000 = 65.00% (c) $23,500,000 × 0.65 = $15,275,000 (d) $15,275,000 − $14,511,250 = $763,750` (check: `$1,175,000 × 0.65 = $763,750 ✓) (e) $15,510,000 − $15,275,000 = $235,000 over-billed (f) $1,175,000 − $1,410,000 = $(235,000) of fade. The margin fell from 6.00 percent to 5.00 percent in one period. (g) Remaining to bill = $23,500,000 − $15,510,000 = $7,990,000`; `remaining cost = $22,325,000 − $14,511,250 = $7,813,750; net cash generation of $176,250 over the remaining life — barely positive.

Yes, it belongs on the agenda — not because of the cash position, which is roughly neutral, but because a full percentage point of margin disappeared in a single period at 65 percent complete, and that is exactly the point in a job's life when the remaining cost is committed enough to be knowable and unfinished enough to still be wrong. Ask what moved, when it moved, and how much of the remaining $7,813,750 is committed by subcontract versus estimated.

21 — The company view, and what one fade does to it.

A contractor reports total current assets of $27,600,000, total current liabilities of $19,200,000, annual revenue of $118,000,000, and an aggregate bonding program of $95,000,000.

(a) Compute working capital, the current ratio, working-capital turnover, and the aggregate program as a multiple of working capital.

(b) Next quarter, one job that has recognized $610,000 of gross profit to date is re-forecast into a $240,000 loss position. Compute the charge to income, the new working capital, and the new current ratio.

(c) Using the 10× to 20× working-capital heuristic, state the approximate effect on supportable bonding program, and then state in one sentence why the arithmetic understates the real consequence.

Answer

(a) - Working capital = $27,600,000 − $19,200,000 = $8,400,000 - Current ratio = $27,600,000 ÷ $19,200,000 = 1.44 - Working-capital turnover = $118,000,000 ÷ $8,400,000 = 14.0× - Aggregate ÷ working capital = $95,000,000 ÷ $8,400,000 = 11.3×

Both multiples sit inside the ranges most underwriters are comfortable with. This is a company with room.

(b) The full estimated loss is recognized now and the recognized profit reverses: - Charge to income = $610,000 + $240,000 = $850,000 - New working capital = $8,400,000 − $850,000 = $7,550,000 - New current ratio = $27,600,000 ÷ ($19,200,000 + $850,000) = $27,600,000 ÷ $20,050,000 = 1.38 - New working-capital turnover = $118,000,000 ÷ $7,550,000 = 15.6×

(c) At roughly 10 to 20 times working capital, $850,000 of lost liquidity corresponds to something on the order of $8,500,000 to $17,000,000 of supportable aggregate program — hedged, because every surety applies its own view and the multiple moves with market, sector, and history.

Why the arithmetic understates it: the ratio movement is modest and survivable, but what the underwriter actually prices is whether this company knows what is happening inside its own jobs — and a profitable job that becomes a loss job in one period is evidence that it does not. Confidence is not a line on the balance sheet, and it is the thing that gets withdrawn first.


Scoring Guide

Score Reading
19–21 correct (90%+) You can build a WIP schedule, read one, and explain to a project manager why their forecast is a financial statement input. Go straight to Chapter 35.
15–18 (70–89%) Solid. Re-read §34.3 (over- and under-billing) and §34.4 (fade) and redo any calculation item you missed — the arithmetic has to be automatic, not reconstructed.
11–14 (50–69%) The vocabulary is landing but the mechanics are not. Work the §34.5 📋 Try it schedule from a blank page, then Part C of the exercises, before you go on.
10 or below Start again at §34.2 and build the Northgate row yourself, on paper, from the four inputs. Do not read forward until gross profit earned = revenue earned − cost to date and = estimated gross profit × percent complete agree without your having to think about it.

Anything you missed in questions 4, 5, 10, or 16 deserves a second pass regardless of your total. Those four are the chapter: the denominator, the disguise, the loss rule, and the chain from your spreadsheet to somebody else's $60,000,000 decision.