Chapter 1 Quiz
Twenty-one questions. Answer before opening any <details> block — looking first feels like learning and is not. Scoring guide at the end.
Multiple Choice (10)
Q1. According to the chapter, construction management is fundamentally:
- A. The supervision of craft labor on a job site
- B. The administration of contracts and paperwork
- C. The management of risk under uncertainty
- D. The coordination of the design team
Answer
C. The drawings are a wish and the schedule is a promise; the profession exists to close the gap between them. Supervision (A) is mostly not yours to do — subcontractors direct their own people. Administration (B) is a means, not the work. Coordinating designers (D) is one activity within it, and only under some delivery methods.
Q2. Northgate's total daily exposure to slipping substantial completion is $10,650 per calendar day. That figure is composed of:
- A. $5,500 in liquidated damages plus $5,150 in extended general conditions
- B. $5,500 in liquidated damages plus $5,150 in lost fee
- C. $10,650 in liquidated damages
- D. $5,150 in liquidated damages plus $5,500 in extended general conditions
Answer
A. Liquidated damages are $5,500/CD and are owed to Meridian. The extended general-conditions rate of $5,150/CD is Kestrel's own cost of keeping the job open one more day and is owed to nobody — it just burns. Both clocks run simultaneously, and the second one is the one people forget.
Q3. Under CM at Risk, the construction manager typically joins the project during:
- A. Bidding
- B. Schematic design
- C. Construction documents
- D. After notice to proceed
Answer
B. That early entry is the entire point: it is when a builder's cost knowledge can still change the structural system, the floor-to-floor height, or the envelope. On design-bid-build (A) the builder's first chance to say "that detail won't work" arrives after the price is fixed.
Q4. Kestrel's fee on Northgate is $1,804,800 against a $47,500,000 guaranteed maximum price. As a percentage of the contract, that is approximately:
- A. 1.9%
- B. 3.8%
- C. 4.0%
- D. 10.5%
Answer
B. $1,804,800 ÷ $47,500,000 = 3.8%. Note that the fee was calculated as 4.0% of the $45,120,000 cost subtotal (option C is that number), but expressed against the full GMP it is 3.8%. The thinness of that margin explains a great deal of contractor behavior.
Q5. Kestrel has a contract with Meridian and separate contracts with each subcontractor. Meridian has a separate contract with Halvorsen + Pike. Which statement is correct?
- A. Kestrel may direct the architect because the architect serves the project
- B. The architect may direct Kestrel's subcontractors on quality matters
- C. Kestrel has no contract with the architect, and instructions travel along contract lines
- D. All parties on a project have implied contracts with one another
Answer
C. Drawing the org chart of contracts rather than of people is one of the highest-value habits in this chapter. Instructions that travel outside contract lines are conversations, and conversations do not entitle anyone to money.
Q6. In the "four clocks" triage framework, an item is on the door clock when:
- A. It costs a known amount of money for each day it is delayed
- B. A window closes and cannot be reopened at any price
- C. It costs nothing today and multiplies later
- D. It damages a relationship you will need later
Answer
B. A mill rolling slot, an inspector standing on your site, a concrete truck already batched. The meter clock is (A), the compound clock is (C), the relationship clock is (D). Door-clock items are usually cheap to handle and catastrophic to miss, which is why they deserve the first minutes of your day.
Q7. The anchor-bolt and embed submittal on Northgate sat in Kestrel's own office for 11 days before going to Caldwell Structural, which then took its full contractual 14-day review. The result was:
- A. Steel erection slipped 11 calendar days
- B. Steel erection slipped 14 calendar days
- C. Steel erection slipped 23 calendar days, from August 4 to August 27, Year 1
- D. No schedule impact, because steel had float
Answer
C. Ironbridge Steel missed its mill rolling slot and the next opening was five weeks out. Steel erection was on the critical path. Note carefully where the 11 days were spent: in the contractor's own office. This is not a story about a slow engineer.
Q8. On change order #14, Kestrel incurred $186,400 of cost but could substantiate only $121,000 with contemporaneous records, and settled at $142,750. The unrecovered cost was:
- A. $22,000
- B. $43,650
- C. $65,400
- D. $186,400
Answer
B. $186,400 − $142,750 = $43,650. The $65,400 in option C is the gap between cost incurred and cost provable, which is the more instructive number: it was created by four days of a crew working without time-and-material tickets.
Q9. The chapter argues that safety does not belong as a corner of the triple constraint because:
- A. Safety is legally mandated and therefore not a management decision
- B. Placing it as a corner implies it can be traded against cost, time, or scope
- C. Safety costs are carried in general conditions rather than direct cost
- D. Safety performance cannot be measured
Answer
B. A corner of a trade-off triangle is, by construction, tradeable. Safety is the floor everything stands on — there is nothing below it. And the trade is always available and never announces itself as a safety decision; it announces itself as a schedule decision.
Q10. The scaffold near-miss investigation found three failures. The one the chapter calls "the one that matters and the one nobody wanted to write down" was:
- A. The competent-person inspection tag was two days stale
- B. A scaffold was modified by a trade that did not erect it
- C. A crew was running behind after an acceleration, under unwritten "make it up" pressure
- D. The mason tender was not wearing fall protection
Answer
C. The first two findings are conditions; the third is the system that produced them. Schedule pressure is a hazard exactly like an unguarded edge, and it is created in the trailer, not on the scaffold.
True / False (5)
Give a one-line justification for each — the justification is the actual exercise.
Q11. A guaranteed maximum price means the owner's total cost for the project cannot exceed that number.
Answer
False. A GMP caps the contractor's price for the contracted scope. Owner-directed scope changes still move the number — change order #14 is the proof. And the GMP is only part of Meridian's $61,000,000 total project budget, which also carries design fees, furniture and equipment, medical equipment, owner contingency, permits, and financing.
Q12. Liquidated damages are a penalty imposed on a late contractor.
Answer
False, and the distinction is legal rather than semantic. A true penalty clause is generally unenforceable; a liquidated damages clause is generally enforceable where the amount is a reasonable pre-estimate of damages that would be genuinely hard to calculate when the contract was signed. Enforceability, caps, and treatment of concurrent delay vary by jurisdiction — read your contract and ask a local attorney.
Q13. On Northgate, liquidated damages run from final completion on November 17, Year 2.
Answer
False. They run from substantial completion, September 18, Year 2 — two months earlier. Knowing which date your clause names is worth two months of exposure at $5,500 per calendar day, or $330,000.
Q14. The majority of a construction manager's working day is spent on technical calculation and analysis.
Answer
False. The overwhelming majority is communication: asking, answering, confirming, writing down, repeating. Ray was interrupted 31 times in the day reconstructed in §1.6, and his most valuable half hour was spent sending four emails he had been putting off.
Q15. Because subcontractors are bound by lump-sum contracts, it does not matter financially to the general contractor if their crews are stacked or restarted.
Answer
False. Disruption to a subcontractor's planned sequence becomes their claim, their slowdown, their reduced crew, or their lost interest in your next job — and often all four. A subcontractor's productivity is your schedule whether or not their price is fixed.
Short Answer (4)
Q16. Name the three continuous activities of construction management and state the question each one answers.
Answer
Anticipation — what is going to go wrong, and how early can I see it? Allocation — who owns this risk, and what did they get paid to own it? Communication — does everyone who needs to know, know, and can I prove it? The middle one carries the sentence worth memorizing: if you cannot answer "who owns this risk," you have found the thing that will hurt you.
Q17. Explain in three or four sentences why the cost of making a change rises across a project while the ability to influence cost falls, and name one practical decision that follows from it.
Answer
Early on, the building exists only as information: changing the structural bay spacing or the floor-to-floor height costs a redrawn sheet, and it changes millions of dollars of downstream work. Late on, the building exists as installed material: changing anything costs demolition, rework, delay, and everyone who was waiting — while the remaining decisions are small ones. The two curves cross somewhere around the end of design development.
The practical decision: bring a builder into the design conversation early enough that constructability and cost feedback arrive while they are still free. That is the whole argument for CM at Risk, design-build, and integrated project delivery.
Q18. The chapter insists that "nobody is the villain." Take the architect's row from the cast table and explain a slow submittal review in terms of incentives rather than character — then say what a contractor can do about it.
Answer
The architect is paid a largely fixed fee, is carrying several projects, is personally liable for errors in what they stamp, and is protective of design intent. A submittal that gets a fast, careless approval is a professional liability; a submittal that gets a slow, careful one is only a schedule problem — for you. The incentives point at slow.
What a contractor does: manage the log rather than complain about it. Send submittals in a prioritized sequence tied to fabrication dates rather than dumping fifty at once. Give the reviewer the specific question rather than the whole package. Publish the review clock in the meeting minutes so it is visible. And back-schedule from the fabrication release date so everyone can see which item is actually urgent this week.
Q19. Distinguish the project manager's job from the superintendent's job in a way that goes beyond "money versus means."
Answer
The superintendent owns what happens on the site today and this week. The project manager owns what will be possible on the site six weeks from now — making sure the material, the approved submittal, the permit, the subcontract, and the answer to the open question all exist by the time the field needs them. Their disagreements are usually not about competence; they are about which of the two is defending today and which is defending week 34.
Applied Scenario (2)
Q20. It is 7:15 a.m. Four things are true: (1) a fabricator needs one dimension confirmed today to hold a mill slot; (2) a crew is on a scaffold whose inspection tag is two days stale; (3) the owner wants a tour on Thursday; (4) your six-week look-ahead has not been updated in two weeks. Put these in the order you would act, and give a one-line reason for each.
Answer
The scaffold first, and it is not a ranking — it is handled now, before anything else, because a person is standing on it. Safety is the floor, not a corner.
Then: (1) the fabricator's dimension — a door clock; eleven minutes of your time against a mill slot that, if missed, is worth 23 calendar days at $10,650 per day on a job like Northgate. Then (4) the look-ahead — schedule the ninety minutes now, because a stale look-ahead is the reason items appear on this list at all. Then (3) the tour — free today, but tell the superintendent immediately, because housekeeping, visitor protective equipment, and a safe route are her problem and she needs a day.
Q21. An owner tells you she plans to save the general contractor's fee by hiring nine trades directly on a $310,000 renovation. She is intelligent, she is not being cheap, and she has good reasons. Give the strongest honest response you can in under 200 words — including at least one thing you concede.
Answer
A strong answer concedes something real: the fee is genuine money, the trades she hires are individually competent, and a general contractor does not prevent every problem — a rotted subfloor is a rotted subfloor either way.
Then it names the specific product she is not buying. Sequence, which no single trade sells and which is why drywall closes before the plumbing inspection. The interfaces between scopes, where firestopping, insulation, and back-boxes live and where nine contracts create dozens of gaps. Leverage after payment — retention and lien waivers are the mechanical reasons a contractor comes back to finish. And coordination above the ceiling, before the duct and the sprinkler main try to occupy the same space.
Then a number: on a project of that size the fee runs somewhere in the low-to-mid teens as a percentage, so roughly $42,000 — against a plausible avoidable overrun several times that, plus months of the space not producing.
What you should not say is anything that sounds like fear-selling. A smart owner discounts it instantly, and she will be right to.
Scoring Guide
| Score | What it means |
|---|---|
| 19–21 | You have the chapter. Move to Chapter 2. |
| 15–18 (70%+) | Ready to proceed. Re-read §1.5 and §1.7 before starting Chapter 2 — the constraint model and the canonical Northgate numbers are load-bearing for the whole book. |
| 11–14 | Re-read §1.1, §1.2, and §1.7, then redo Q1–Q10. The lifecycle and the daily-exposure arithmetic are the two things you cannot proceed without. |
| Below 11 | Re-read the chapter and do exercises A1–A10 and C1–C3 before the quiz. Do not treat this as a failure — Chapter 1 introduces about forty terms and a dozen numbers at once. |
The two things to carry out of this chapter regardless of your score: $10,650 per calendar day, and if you cannot answer "who owns this risk," you have found the thing that will hurt you.