Chapter 7 Quiz

22 questions. Answer everything before opening any <details> block — retrieval only works if you actually retrieve. Scoring guide at the end.


Multiple Choice

1. Which of the following is generally not a contract document?

A. The supplementary conditions B. Addendum No. 3 C. The contractor's approved shop drawings D. Specification Section 09 21 16

Answer

C. Shop drawings are submittals — the contractor's representation of how it intends to build what the contract documents require. Reviewing a submittal does not modify the contract. A, B, and D are all enumerated contract documents in essentially every standard form.

2. The drawings show a 4" slab; Specification Section 03 30 00 says 5". Your contract states the documents are complementary and that the architect interprets conflicts. What do you do?

A. Build 5", because specifications govern over drawings B. Build 4", because figured dimensions govern C. Build the cheaper one and log the savings D. Write an RFI and do not proceed on that scope until you have an answer

Answer

D. Under a complementary clause you have no authority to self-resolve — the architect interprets. A is wrong because "specifications govern over drawings" is one possible regime, not a universal rule. B misapplies the figured-dimension convention, which resolves scaled versus written dimensions on the same drawing, not drawing-versus-spec conflicts.

3. Sheet E-601 most likely contains:

A. An electrical floor plan B. Electrical panel schedules C. Electrical details D. An electrical site plan

Answer

B. The second character is the view type: 6 = schedules and diagrams. Plans are 1, elevations 2, sections 3, large-scale views 4, details 5, schedules and diagrams 6.

4. Which MasterFormat division contains general requirements — submittals, quality requirements, temporary facilities, and closeout?

A. Division 00 B. Division 01 C. Division 02 D. Division 10

Answer

B. Division 00 is procurement and contracting requirements (bid forms, the agreement, general and supplementary conditions). Division 01 is general requirements — and it is the division no trade owns, which is why it defaults to the general contractor.

5. In SectionFormat, which part tells you what will be tested in the field, by whom, and at whose cost?

A. Part 1 — General B. Part 2 — Products C. Part 3 — Execution D. It is never in the specification; it is on the drawings

Answer

C. Field Quality Control lives in Part 3. Part 1 carries submittals, quality assurance, mockups, and warranty; Part 2 carries what you buy.

6. A bulletin (or proposal request) issued by the architect after contract execution is:

A. A directive you must proceed with immediately B. A proposed change issued for pricing, which you must not build C. A modification with the same force as a change order D. A clarification of existing scope with no cost impact

Answer

B. A bulletin is a request for pricing. Building a bulletin is building unpriced, undirected scope. A describes a construction change directive; C describes a change order; D describes what an ASI claims to be.

7. Which format would you use to compare the total cost of an architectural precast enclosure against an insulated metal panel enclosure during schematic design?

A. MasterFormat, because subcontractors bid that way B. UniFormat, because it keeps the building system whole C. Either — they produce identical results D. Neither; you need a detailed takeoff first

Answer

B. UniFormat organizes by building element (B2010 Exterior Walls), which captures everything the change drags with it — framing, insulation, air barrier, sealants, connections, crane requirements — as one system. MasterFormat would price the visible panel section and miss the cascade.

8. Sheet A-311 shows 2" of insulation; sheet A-512 shows 3" for the same assembly. Your contract has an explicit order-of-precedence clause ranking specifications above drawings. Which governs?

A. A-311, because it is the lower sheet number B. A-512, because later sheets supersede earlier ones C. Neither — the precedence clause does not resolve conflicts between two drawings D. The specification, automatically

Answer

C. Order-of-precedence clauses resolve conflicts between document families. Two architectural sheets are the same family. The "large-scale governs over small-scale" convention may help if one is a detail and one is a plan; otherwise the architect must interpret. There is no "lower sheet number" or "later sheet" rule.

9. The most common reason a scope falls through the cracks between two subcontracts is:

A. Subcontractors bidding dishonestly B. The scope lives at a boundary that no designer or bidder is responsible for owning C. Poor estimating software D. The owner changing its mind

Answer

B. Design is divided by discipline, and each consultant is careful inside its own boundary. Nobody is paid to own the seam. That is why Pass 6 of the review method goes deliberately to boundaries — between disciplines, between subcontracts, between furnish and install, at the five-foot utility line.

10. On Northgate, the total daily exposure to slipping substantial completion is:

A. $5,150 per calendar day B. $5,500 per calendar day C. $10,650 per calendar day D. $47,500 per calendar day

Answer

C. $5,150 per calendar day of extended general conditions plus $5,500 per calendar day of liquidated damages.

11. A specification section requires compliance with a published reference standard. The practical effect is:

A. Advisory only — reference standards are guidance B. The entire referenced document becomes binding on you by incorporation C. It applies only if the building code also requires it D. It applies only to the designer

Answer

B. One line imports the whole standard, including its test methods, acceptance criteria, frequencies, and reports. Check which edition applies; if the section is silent and the standard has been revised, that ambiguity is worth an RFI. And where the adopted code is stricter, the code governs, because it is law.

12. You find a discrepancy between the drawings and the specifications, log it internally, and say nothing to the architect. You then build the cheaper reading. Under most standard general conditions, the likely result is:

A. The owner pays, because it is a design error B. Cost is split evenly by default C. You assumed responsibility by proceeding with knowledge of the conflict D. The architect's professional liability insurance responds

Answer

C. Most general conditions impose a duty to study, compare, and promptly report discovered errors, inconsistencies, and omissions. Proceeding with knowledge generally shifts responsibility for the resulting damages to the contractor, and can waive the associated claim.


True / False

Give a one-line justification for each.

13. "Do not scale drawings" exists mainly because architects draw imprecisely.

Answer

False. Three real mechanisms: reproduction (half-size sets, "fit to page" PDFs), printing distortion (paper stretch, non-uniform plotter shrink), and — most importantly — a dimension string states intent while a line is only a representation of it. That is why figured dimensions govern over scaled.

14. A statement made by the owner's representative at a pre-bid meeting is binding on the owner.

Answer

False. Nothing said at a pre-bid meeting binds anyone unless it is reissued as an addendum. If it matters, ask for it in writing before bid.

15. A detail drawing tells you how many places that condition occurs.

Answer

False. A detail tells you how one condition is built. Extent comes from plans, elevations, sections, and schedules. Confusing the two is a classic takeoff error.

16. Division 01 is the least important division because it contains no physical work.

Answer

False. It contains no trade work, which is exactly why it is dangerous: no subcontractor's survival depends on reading it, so everything in it defaults silently to the general contractor's general requirements budget. Ray's $214,000 lesson.

17. An RFI response that adds scope automatically becomes a change order.

Answer

False. An RFI response interprets the documents. If the interpretation adds scope, that is a change — and you have a notice obligation with a deadline. Silence after an RFI response that adds work is how contractors perform free work.

18. Record (as-built) drawings are a closeout deliverable and should be produced at the end of the job.

Answer

False. They are a weekly habit — the field engineer redlines the control set in a distinct color, initialed and dated, about fifteen minutes a week. Reconstructing fourteen months of field changes from memory at closeout produces a fiction, and the owner's facilities team will need the truth at 2 a.m. in year three.


Short Answer

19. State the six passes of the systematic document review method, in order, in one line each.

Answer

(1) Read Division 00 and 01 completely, before any drawing. (2) Cross-check drawings against specs by assembly, not sheet by sheet. (3) Cross-check disciplines against each other at the same location. (4) Check schedules against plans for count. (5) Check details against sections for continuity of the barrier, the vapor retarder, and the rated line. (6) Go deliberately to the seams — between disciplines, between subcontracts, between furnish and install, at match lines and the five-foot utility line.

20. Explain, with the mechanism and not just the conclusion, why an identical discrepancy costs roughly thirteen times more when found in the field than when found in preconstruction.

Answer

The scope delta itself is unchanged — on Northgate's air barrier conflict, $18,900 either way. What changes is everything the delta now has to move: work already installed must be removed and reinstalled ($95,200 across 14,000 SF), failed performance must be investigated and remediated ($22,400), the designer must be paid for supplemental service ($8,600), and the correction consumes critical-path time (11 CD × $10,650/CD = $117,150). $20,200 versus $262,250 — 13.0×. The general principle: in preconstruction a conflict costs the price of an answer; in the field it costs the price of an answer plus the price of everything built on the wrong one.

21. Division 01 is described in the chapter as "the most under-read and most expensive document in the set." Give the mechanism — not the conclusion — and name three specific obligations that typically live there and appear on no drawing.

Answer

The mechanism is incentive. Every other division has a trade attached to it: Division 03 is read by concrete subs, Division 26 by electricians, because that is how each of them prices and gets paid. Division 01 has no trade attached. There is no "general requirements subcontractor," so no bidder's commercial survival depends on reading it — which means everything in it defaults, silently, to the general contractor's general requirements budget. On Northgate that budget is $2,900,000, burning at $5,150 per calendar day for 565 days, whether or not anyone read the document defining what it must cover.

Three obligations that appear on no drawing: an independent testing and inspection agency engaged and paid by the contractor; contractor-prepared composite coordination drawings with a defined review process; and construction waste diversion targets with sorting, hauling, and documentation requirements. Others that qualify: required mockups, temporary heat, monthly progress photography, commissioning support labor, work restrictions in owner-occupied areas, and closeout training and record-document deliverables.


Applied Scenario

22. It is 6:40 a.m. Sheet A-011 shows partition type C-2 as a 2-hour rated wall with one layer of 5/8" Type X each side. Section 09 21 16 requires two layers each side for a 2-hour rating. Sheet G-004 shows the corridor as 1-hour. Eleven people are on the clock and a layout line is snapped.

State: (a) which document governs; (b) the first three things you do in the next ten minutes; (c) the four elements your RFI must contain; (d) the approximate cost of guessing wrong in each direction.

Answer

(a) None of them yet — and that is the right answer. Two of the three documents are architectural drawings, so no order-of-precedence clause resolves it, and under a complementary clause the architect interprets. The real finding is that partition type C-2 is internally inconsistent: a 2-hour rating on a non-loadbearing steel-stud partition generally requires two layers each side or a different listed assembly, so its description does not match the rating it claims.

(b) Stop that specific wall but move the crew to non-conflicted work on the same floor (stopping eleven people costs roughly $600/hour; moving them costs the walk). Check the current revision of A-011 and G-004 against the drawing log, the rated-assembly schedule on the G-series, and the AHJ-stamped permit set. Tell the superintendent and the PM verbally, then in writing, and log it.

(c) Precise references (sheet + revision, section + article) for all three documents; the conflict stated without argument; a suggested resolution; and separate schedule-impact and cost-impact statements.

(d) Guess low (build 1-hour, need 2-hour, caught after finishes): roughly $284,042 — added board, ceiling grid removal and reinstall, re-firestopping, re-taping and painting, 46 replaced door frames because the throat depth no longer matches the wall thickness, re-inspection, and 7 CD of delay. Guess high (build 2-hour, only 1-hour required): roughly $62,540 unrecoverable, because betterment furnished without a directive is not compensable. Write the RFI: 45 minutes, $0.


Scoring Guide

Score Where you are
20–22 correct (90%+) You can be handed a set. Go run the six passes on a real project.
16–19 (70–89%) Solid. Re-read §7.2 (precedence, especially drawing-to-drawing) and §7.7 (Division 01) before moving on.
11–15 (50–69%) The mechanics are there but the judgment is not. Redo the 📋 Try it drill from the chapter without looking at the answer, then retake this.
10 or fewer Re-read the chapter with a real drawing set open beside it. This one does not transfer from reading alone.

70% is the gate. Every chapter after this one assumes you can find things in a set and know which document wins when two of them disagree.